FIRE-Final Inspection | 4/22/2009 | 4/22/2009 | 4/22/2009 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
BLD-Final | 4/22/2009 | 4/22/2009 | 4/22/2009 | P | PASS |
Dave Hannah
|
|
|
Mik Phone #: ###-#### ok for perm occ
|
BLD-Final | 4/21/2009 | 4/21/2009 | 4/21/2009 | P | NR |
Mike Jordan
|
|
|
Mick ###-####. Neesd fire/ life safety final to pass.
|
FIRE-Final Inspection | 4/21/2009 | 4/21/2009 | 4/21/2009 | P | FAIL |
Troy Cobbley
|
|
|
Provide the street address on both sides of the building as discussed, provide and mount the fire extinguisher as discussed, provide the occupant load sign (49) as discussed and provide modifications as discussed for the hvac system for proper placement of the duct smoke detector with a remote annunciator or provide verification that the hvac unit in question does not exceed 2,000cfm.
|
BLD-Other | 4/20/2009 | 4/20/2009 | 4/20/2009 | P | PASS |
Mike Jordan
|
|
|
Mic- ceiling Phone #: ###-####. Ceiling grid ok. Architect has provided additional details for 2hr. wall as noted in c/n. All work on 2hr. wall is complete.
|
BLD-Other | 4/6/2009 | 4/7/2009 | 4/7/2009 | P | NR |
Mike Jordan
|
|
|
Nick- ceiling Phone #: ###-####. Needs ri insp. first.
|
BLD-Conference | 4/2/2009 | 4/2/2009 | 4/2/2009 | P | PASS |
Mike Jordan
|
|
|
Mic Phone #: ###-####. Contractor had questions on ceiling grid installation requirements.
|
BLD-Conference | 12/17/2008 | 12/17/2008 | 12/17/2008 | P | DONE |
Mike Jordan
|
|
|
mick - please call 1/2 hr prior Phone #: ###-####
|
BLD-Framing/Rough-in | 8/25/2008 | 8/26/2008 | 8/26/2008 | A | PART |
Mike Jordan
|
|
|
mick Phone #: ###-####. 1st. layer of 5/8 type x for 2hr fire barrier wall,
|
BLD-Framing/Rough-in | 8/21/2008 | 8/22/2008 | 8/22/2008 | A | PART |
Mike Jordan
|
|
|
mick - please call 1/2 hr prior so he can meet you there Phone #: ###-####. ok to cover 2nd side of 2hr. fire barrier wall.
|
BLD-Conference | 8/19/2008 | 8/19/2008 | 8/19/2008 | A | PASS |
Mike Jordan
|
|
|
Noted inactivity on job site. Called contractor to check on job status. Contractor noted that job was on hold temporarily, but should start back up in the next day or two.
|
BLD-Framing/Rough-in | 7/17/2008 | 7/18/2008 | 7/18/2008 | A | PART |
Mike Jordan
|
|
|
nick Phone #: ###-####. Provided UL appears to be incorrect for installation. Architect to provide details for membrane and thru penetrations for 2hr fire barrier wall.
|
BLD-Framing/Rough-in | 7/11/2008 | 7/11/2008 | 7/11/2008 | P | PART |
Mike Jordan
|
|
|
Ryan Phone #: ###-####. Neds to provide UL for 2hr fire barrier wall and provide UL datta for membrane and thru penetrations. Provide ceiling details from architect. Remove wood penetrations from 2hr. wall and repair. c/n posted. ok to cover except for 2hr. wall. no grid.
|