BLD-Final | 3/29/2009 | 3/30/2009 | 3/30/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/29/2009 at 11:05:51 AM. Contact: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 3/29/2009 | 3/30/2009 | 3/30/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
Code Occupancy Approval | | | 3/26/2009 | | PASS |
|
|
|
Landscaping and parking lot striping has been completed. Ok for permanent occupancy.
|
BLD-Framing/Rough-in | 3/11/2009 | 3/12/2009 | 3/12/2009 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 3/11/2009 at 6:26:03 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/2/2009 | 3/3/2009 | 3/3/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/2/2009 at 3:10:03 PM. Contact: ###-####. Interior partition walls ok. Also reinspected priviously installed ceiling grid, system has been matched to exisiting system. ok.
|
BLD-Framing/Rough-in | 2/25/2009 | 2/25/2009 | 2/25/2009 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/25/2009 at 6:50:01 AM. Contact: ###-####. Needs to match existing system were new grid is being installed.
|
BLD-Framing/Rough-in | 2/19/2009 | 2/19/2009 | 2/19/2009 | A | PART |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 2/19/2009 at 5:59:49 AM. Contact: ###-####. Frame infill of large doorway at existing (old) front entry OK.
|
FIRE-Final Inspection | 2/4/2009 | 2/5/2009 | 2/5/2009 | A | PART |
Troy Cobbley
|
|
|
The new addition is ok to occupy.
|
FIRE-Final Inspection | 2/3/2009 | 2/4/2009 | 2/4/2009 | P | FAIL |
Troy Cobbley
|
|
|
The access controlled egress doors are not operational yet. The inspection will be called in for tomorrow.
|
BLD-Final | 1/28/2009 | 1/29/2009 | 1/30/2009 | P | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 1/28/2009 at 9:42:10 PM. Contact: ###-####. ok to move in to new addition they are working on front entry doors they are also going to add several exit signs in nw section also sink in break room needs to be lowered to 34 inches
|
FIRE-Final Inspection | 1/28/2009 | 1/29/2009 | 1/29/2009 | P | FAIL |
Troy Cobbley
|
|
|
The new addition is basically complete. I gave my permission for furniture and office equipment to be moved into this new area but business is not to be done until the main entry doors/hardware is installed and inspected. Also six office doors/hardware are backordered and the hardware is missing from the double doors into the Mail Room. The fire sprinkler system and fire alarm systems are complete for the new addition. Fire lane signs are being installed until weather permitting the fire lane striping can be completed.
|
BLD-Framing/Rough-in | 1/26/2009 | 1/26/2009 | 1/26/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/26/2009 at 6:47:14 AM. Contact: ###-####. Ceiling grid pahase 4.
|
BLD-Other | 1/20/2009 | 1/20/2009 | 1/20/2009 | P | PART |
Mike Jordan
|
|
|
ceiling grid for phase 2 and 3.
|
BLD-Framing/Rough-in | 1/20/2009 | 1/20/2009 | 1/20/2009 | A | PASS |
Mike Jordan
|
|
|
chris - ###-#### - ceiling grid - ok per john menard. Phase 1 ok.
|
BLD-Framing/Rough-in | 1/15/2009 | 1/15/2009 | 1/15/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/15/2009 at 9:33:43 AM. Contact: ###-####. Expansion anchors at bottom track for dalse canopy.
|
BLD-Framing/Rough-in | 1/14/2009 | 1/15/2009 | 1/15/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/14/2009 at 4:41:30 PM. Contact: ###-####. Expansion anchors in bottom track for canopy framing. wip on false canopy.
|
BLD-Framing/Rough-in | 1/13/2009 | 1/14/2009 | 1/14/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/13/2009 at 9:17:28 PM. Contact: ###-####. remainder of soffit at main canopy.
|
BLD-Framing/Rough-in | 1/13/2009 | 1/13/2009 | 1/14/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/13/2009 at 8:16:20 AM. Contact: ###-####. soffit for false canopy. hardlid for janitors closet.
|
BLD-Conference | 1/9/2009 | 1/12/2009 | 1/12/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/9/2009 at 4:34:38 PM. Contact: ###-####. Discussed fireproofing material that was used. A different material was applied than was submitted and approved. In place material will be ok, contractor to apply more to obtain required density. Material applied has been approved by architect of record. Will have new approved submital scanned into permit at city hall.
|
BLD-Framing/Rough-in | 1/9/2009 | 1/12/2009 | 1/12/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/9/2009 at 4:33:29 PM. Contact: ###-####. Framing for hardlid in existing bldg. for card reader room.
|
BLD-Framing/Rough-in | 1/6/2009 | 1/6/2009 | 1/6/2009 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 1/6/2009 at 9:22:17 AM. Contact: ###-####. HArdlids for south restrooms ok. Framing for southeast canopy, Needs to install expansion anchors as shown on aproved plans.
|
BLD-Framing/Rough-in | 12/31/2008 | 12/31/2008 | 12/31/2008 | P | PART |
Jim Sly
|
|
|
CHRIS Phone #: ###-#### Hard lids....North restrooms....Curtain wall framing at South canopy OK.
|
BLD-Energy code compliance | 12/18/2008 | 12/19/2008 | 12/19/2008 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/18/2008 at 9:53:11 PM. Contact: ###-####. BAtt insul. at exterior walls, east and north walls ok.
|
BLD-Framing/Rough-in | 12/19/2008 | 12/19/2008 | 12/19/2008 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/18/2008 at 9:53:11 PM. Contact: ###-####. Steel stud framing for canopy at main enterance.
|
BLD-Framing/Rough-in | 12/18/2008 | 12/18/2008 | 12/18/2008 | P | PASS |
Mike Jordan
|
|
|
869-534 - chris
|
BLD-Energy code compliance | 12/18/2008 | 12/18/2008 | 12/18/2008 | P | PART |
Mike Jordan
|
|
|
###-#### - chris
|
BLD-Energy code compliance | 12/16/2008 | 12/16/2008 | 12/16/2008 | P | PASS |
Mike Jordan
|
|
|
###-#### - chris . Exterior CMU walls ok.
|
BLD-Framing/Rough-in | 12/11/2008 | 12/11/2008 | 12/11/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/11/2008 at 11:17:59 AM. Contact: ###-####. Interior steel stud framed walls. Still needs backing for ada in restrooms and plumbing ri insp as well. Will need to provide materila at roof decking for smoke partitions.
|
BLD-Framing/Rough-in | 12/5/2008 | 12/5/2008 | 12/5/2008 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/5/2008 at 8:44:02 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 12/2/2008 | 12/2/2008 | 12/2/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 12/2/2008 at 10:02:12 AM. Contact: ###-####. Interior steel stud 7ft. partition walls ok. Also reveiwed special insp. reports to date.
|
BLD-Concrete | 10/15/2008 | 10/15/2008 | 10/15/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/15/2008 at 9:23:46 AM. Contact: ###-####. Grout placement cancelled for today. Did review special insp. reports. Noted several faling compaction tests. Contractor noted that failing areas had been retested.
|
BLD-Concrete | 9/30/2008 | 9/30/2008 | 9/30/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/30/2008 at 11:09:33 AM. Contact: ###-####. Masonry: 0 to 4ft. elevation, grid G between grids 5 to 9. ok for grout placement after special insp. is ok.
|
BLD-Footing | 9/26/2008 | 9/26/2008 | 9/26/2008 | P | DEFR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/26/2008 at 9:55:44 AM. Contact: ###-####.
|
BLD-Footing | 9/23/2008 | 9/24/2008 | 9/24/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/23/2008 at 11:21:47 AM. Contact: ###-####. exterior column pad footings at south end of bldg.
|
BLD-Footing | 9/16/2008 | 9/17/2008 | 9/17/2008 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/16/2008 at 5:12:50 PM. Stemwall on gridline G between grids 5 -8.5.
|
BLD-Footing | 9/16/2008 | 9/16/2008 | 9/16/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/16/2008 at 7:36:56 AM. Contact: ###-####. Exterior stemwalls on east and south ends.
|
BLD-Footing | 9/15/2008 | 9/15/2008 | 9/15/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/15/2008 at 11:03:09 AM. Contact: ###-####. All interior column pad footings, exterior footing on grid G between grids 5 -8.5
|
FIRE-Conference | 9/15/2008 | 9/15/2008 | 9/15/2008 | A | DONE |
Troy Cobbley
|
|
|
The new office area in the existing building next to the breakroom is ok to occupy.See the city approved plans for the location signed and marked with todays date.
|
FIRE-Final Inspection | 9/12/2008 | 9/12/2008 | 9/12/2008 | P | FAIL |
Troy Cobbley
|
|
|
This inspection actually turned into a conference on the remodeled area of the existing building next to the break room. I agreed that people could move in when a emergency light/exit sign is installed over the exit way to the corridor.
|
BLD-Framing/Rough-in | 9/9/2008 | 9/10/2008 | 9/10/2008 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/9/2008 at 5:40:59 PM. Contact: ###-####.
|
BLD-Footing | 9/9/2008 | 9/10/2008 | 9/10/2008 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 9/9/2008 at 5:39:21 PM. Contact: ###-####. Exterior footings on grids C and G between grids 7 to 11 and on grid 11 between grids c to G. Spoke with engineer from Tamarack engineering on vertical reinforcement. Should be #4 at 16" oc then #6 verts at 24"oc for masonry const. RFI will be sent to contractor. Ok to place conc. once special insp agency has inspected the completed work.
|
BLD-Framing/Rough-in | 8/28/2008 | 8/28/2008 | 8/28/2008 | P | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/28/2008 at 9:29:31 AM. Contact: ###-####. Interior steel stud 7ft. partition walls for new offices in existing portion of bldg. phase 1.
|
BLD-Framing/Rough-in | 8/26/2008 | 8/27/2008 | 8/27/2008 | P | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/26/2008 at 5:46:11 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Aug 27 2008 10:35AM.
|