BLD-Final | 6/9/2009 | 6/10/2009 | 6/10/2009 | A | PASS |
Mike Jordan
|
|
|
Jerry Phone #: ###-####.. All issues resolved. Ok for perm occ.
|
BLD-Final | 12/15/2008 | 12/16/2008 | 12/16/2008 | A | PART |
Mike Jordan
|
|
|
jerry Phone #: ###-####. ok for temp occ. Will be ok for perm occ once phase 2 has been completed and passed.
|
FIRE-Final Inspection | 12/15/2008 | 12/15/2008 | 12/15/2008 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given as per the project scope of work until the phase II of the project is complete.
|
FIRE-Final Inspection | 12/11/2008 | 12/12/2008 | 12/12/2008 | P | FAIL |
Troy Cobbley
|
|
|
Provide missing emergency lighting/exit signs as marked on the plans and relocate the occupant load signs as discussed.
|
BLD-Other | 12/11/2008 | 12/11/2008 | 12/11/2008 | P | PASS |
Mike Jordan
|
|
|
jerry Note: rebar Phone #: ###-####. Column pad footings for new partition wall and for post and beam assembly for removal of bearing wall.
|
FIRE-Alarm Testing | 12/11/2008 | 12/11/2008 | 12/11/2008 | P | CANC |
Troy Cobbley
|
|
|
jerry Phone #: ###-#### Inspection cancelled from web by: Patricia Smith
|
FIRE-Final Inspection | 12/3/2008 | 12/4/2008 | 12/4/2008 | P | CANC |
Troy Cobbley
|
|
|
Not ready for a life safety final
|
BLD-Other | 11/17/2008 | 11/18/2008 | 11/18/2008 | A | PASS |
Mike Jordan
|
|
|
jerry - ceiling grid cover - after 10:00 please Phone #: ###-####. Ceiling grid, 1st. floor ok.
|
BLD-Other | 11/12/2008 | 11/12/2008 | 11/12/2008 | P | PASS |
Mike Jordan
|
|
|
Ceiling grid, 2nd. floor only. ok
|
BLD-Other | 11/11/2008 | 11/12/2008 | 11/12/2008 | A | DEFR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 11/11/2008 at 3:11:32 PM. Contact: ###-####.
|
FIRE-Supply Line Cover | 11/10/2008 | 11/10/2008 | 11/10/2008 | P | PASS |
Troy Cobbley
|
|
|
This inspection was for the covering of the sprinkler piping on the second floor. This piping can be covered.
|
BLD-Other | 11/6/2008 | 11/6/2008 | 11/6/2008 | P | PART |
Mike Jordan
|
|
|
jerry Note: ceiling Phone #: ###-####. Ceiling grid, 1st. floor, area at warehouse were new was aded to existing. New portion installed as existing was installed.
|
FIRE-Conference | 11/3/2008 | 11/3/2008 | 11/3/2008 | P | DONE |
Troy Cobbley
|
|
|
jerry Phone #: ###-####
|
BLD-Other | 10/30/2008 | 10/31/2008 | 10/31/2008 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/30/2008 at 12:55:15 PM. Contact: ###-####. Masonry wing wall and added parapet at 3hr. wall location. Also reviewed special insp. reports. Also recieved and submitted calcs from architect for 3hr. hallow core precast panel.
|
BLD-Framing/Rough-in | 10/30/2008 | 10/31/2008 | 10/31/2008 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/30/2008 at 12:54:35 PM. Contact: ###-####. Framing for added stairway. Plan mod has been submitted to city per contractor.
|
BLD-Footing | 10/22/2008 | 10/22/2008 | 10/22/2008 | A | PART |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 10/22/2008 at 6:44:56 AM. Contact: ###-####. Stemwalls and column pedestals for new canopy on north side of bldg.
|
BLD-Foundation | 10/20/2008 | 10/21/2008 | 10/21/2008 | A | PART |
Mike Jordan
|
|
|
jerry Note: rebar Phone #: ###-####. Column pad footings and footings for new canopy at north side of bldg. Special insp. on site.
|
BLD-Conference | 10/17/2008 | 10/20/2008 | 10/20/2008 | A | DONE |
Mike Jordan
|
|
|
jerry Note: for t-bar Phone #: ###-####
|
BLD-Framing/Rough-in | 9/26/2008 | 9/26/2008 | 9/26/2008 | P | PART |
Mike Jordan
|
|
|
jerry Phone #: ###-####. Hardlids in restrooms, 2nd floor.
|
BLD-Framing/Rough-in | 9/25/2008 | 9/25/2008 | 9/25/2008 | P | NR |
Mike Jordan
|
|
|
No framing insp done. ESC issues were not resolved from last insp. see esc permit.
|
BLD-Framing/Rough-in | 9/25/2008 | 9/25/2008 | 9/25/2008 | P | PASS |
Mike Jordan
|
|
|
jerry Phone #: ###-####
|
BLD-Framing/Rough-in | 9/16/2008 | 9/17/2008 | 9/17/2008 | A | PART |
Mike Jordan
|
|
|
jerry Phone #: ###-####. 1st. floor interior framed walls only. No grid or hardlids. Also gave contrctor c/n to have architect provide a listed aproved assembly for 3hr. exterior loading dock wall. Existing wall is hallow core precast conc. wall. Assembly submitted was for a solid conc. wall.
|
BLD-Framing/Rough-in | 8/29/2008 | 8/29/2008 | 8/29/2008 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 8/29/2008 at 6:59:16 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 8/18/2008 | 8/19/2008 | 8/19/2008 | A | PART |
Mike Jordan
|
|
|
jerry Phone #: ###-####. interior framed walls only, 2nd floor. No grid or hardlids.
|
BLD-Framing/Rough-in | 8/8/2008 | 8/11/2008 | 8/11/2008 | A | NR |
Mike Jordan
|
|
|
Jerry Phone #: ###-####. Needs ri insp. from other trades first.
|
BLD-Framing/Rough-in | 8/4/2008 | 8/5/2008 | 8/5/2008 | A | PART |
Mike Jordan
|
|
|
Jerry Phone #: ###-####. Framing for new open stairway from existing mezz. ok. to rock and install handrails.
|