BLD-Final | 5/28/2009 | 5/29/2009 | 5/29/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
DOC - Permit Finaled | 5/29/2009 | 5/29/2009 | 5/29/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 5/28/2009 | 5/29/2009 | 5/29/2009 | A | PART |
Tom Arcoraci
|
|
|
Adam Phone #: ###-####
|
FIRE-Final Inspection | 5/28/2009 | 5/29/2009 | 5/29/2009 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 5/26/2009 | 5/26/2009 | 5/26/2009 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy is being given until 5/29/2009 with Jason Blaise, Mark Sentenno and Scott Areleno's permission. The Area of Refuge equipment needs to be installed and tested. The address has been changed from a Hartman street address to Liberty Street.
|
BLD-Final | 5/22/2009 | 5/26/2009 | 5/26/2009 | A | PART |
Jim Storey
|
|
|
adam - late morning please Phone #: ###-#### temp l/c isued. pending equment instal verifaction in area of refuse.
|
FIRE-Final Inspection | 5/21/2009 | 5/21/2009 | 5/21/2009 | P | FAIL |
Troy Cobbley
|
|
|
Provide a letter from plan review stating that the exit sign on the roof can be deleted. Provide and test all items pertaining to the Area of Refuge. Provide testing of the elevator and fire alarm interconnections. The building address does not match the address the central station give to the boise fire dept. This will have to have approval.
|
BLD-Conference | 5/21/2009 | 5/21/2009 | 5/21/2009 | P | PASS |
Tom Arcoraci
|
|
|
needs com and sign at area of refuge
|
FIRE-Final Inspection | 5/19/2009 | 5/20/2009 | 5/20/2009 | P | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm and fire sprinkler permits need to be finaled. Also the Area of Refuge items as listed on the fire and building review comments have not been addressed. One exit sign needs to be added on the roof stair entrance.
|
BLD-Conference | 5/19/2009 | 5/19/2009 | 5/19/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/15/2009 | 5/15/2009 | 5/15/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/13/2009 | 5/13/2009 | 5/13/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/12/2009 | 5/13/2009 | 5/13/2009 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 5/7/2009 | 5/7/2009 | 5/7/2009 | P | PASS |
Tom Arcoraci
|
|
|
Ceiling inspection please-- Dale Phone #: ###-####
|
BLD-Other | 5/6/2009 | 5/7/2009 | 5/7/2009 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 5/6/2009 | 5/6/2009 | 5/6/2009 | P | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/5/2009 | 5/6/2009 | 5/6/2009 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 5/5/2009 | 5/5/2009 | 5/5/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Final Inspection | 4/28/2009 | 4/29/2009 | 4/29/2009 | A | FAIL |
Troy Cobbley
|
|
|
This was actually a conference for the placement of the exterior electric alarm bell. Per mark sentenno the bell can be placed on the glass wall above the fdc or 15'-0" to the west, above the glass panels, in the rock wall.
|
BLD-Conference | 4/28/2009 | 4/29/2009 | 4/29/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 4/27/2009 | 4/29/2009 | 4/28/2009 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Conference | 4/24/2009 | 4/24/2009 | 4/24/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Conference | 4/23/2009 | 4/23/2009 | 4/24/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
FIRE-Conference | 4/2/2009 | 4/2/2009 | 4/2/2009 | P | DONE |
Troy Cobbley
|
|
|
Dale and I went over fire extinguisher placement and placement of the knox key box.
|
BLD-Framing/Rough-in | 3/23/2009 | 3/24/2009 | 3/24/2009 | A | PASS |
Tom Arcoraci
|
|
|
Dale Phone #: ###-#### wip ok
|
BLD-Framing/Rough-in | 3/6/2009 | 3/9/2009 | 3/10/2009 | P | PASS |
Tom Arcoraci
|
|
|
adam - ceiling grid Phone #: ###-####
|
BLD-Wall cover | 3/3/2009 | 3/3/2009 | 3/3/2009 | P | PART |
Tom Arcoraci
|
|
|
|
BLD-Other | 2/5/2009 | 2/5/2009 | 2/5/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 1/26/2009 | 1/26/2009 | 1/26/2009 | P | PASS |
Tom Arcoraci
|
|
|
dale-fire stop inspection Phone #: ###-#### wip ok
|
BLD-Other | 1/20/2009 | 1/21/2009 | 1/21/2009 | A | PASS |
Tom Arcoraci
|
|
|
dale - fire stop Phone #: ###-####
|
BLD-Framing/Rough-in | 1/16/2009 | 1/16/2009 | 1/16/2009 | P | PART |
Tom Arcoraci
|
|
|
dale - partial wall Phone #: ###-####
|
BLD-Framing/Rough-in | 1/7/2009 | 1/7/2009 | 1/7/2009 | P | PASS |
Tom Arcoraci
|
|
|
dale Phone #: ###-#### wip ok
|
BLD-Framing/Rough-in | 12/16/2008 | 12/16/2008 | 12/16/2008 | P | NR |
Tom Arcoraci
|
|
|
dale wip ok
|
BLD-Framing/Rough-in | 12/12/2008 | 12/16/2008 | 12/16/2008 | A | CANC |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 12/12/2008 | 12/12/2008 | 12/12/2008 | P | PART |
Tom Arcoraci
|
|
|
dale Phone #: ###-#### wip ok
|
BLD-Conference | 12/8/2008 | 12/11/2008 | 12/11/2008 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 12/8/2008 | 12/8/2008 | 12/8/2008 | P | PART |
Tom Arcoraci
|
|
|
dale Phone #: ###-#### par ok wip
|
BLD-Footing | 11/4/2008 | 11/5/2008 | 11/5/2008 | A | PASS |
Mike Jordan
|
|
|
Dale Phone #: ###-####. #rd floor slab on deck, south half ok. Special insp. has approved also.
|
BLD-Other | 10/17/2008 | 10/20/2008 | 10/20/2008 | A | PASS |
Jim Storey
|
|
|
dale Note: 1st in morning for structural steel concrete Phone #: ###-#### third floor deck ok 2/3 north to center of deck ok to place concrete. si signed off.
|
BLD-Concrete | 9/25/2008 | 9/26/2008 | 9/26/2008 | A | PART |
Jim Sly
|
|
|
Ken Phone #: ###-#### - pouring at 12:30 Grade Beams At North and West walls OK pending MTI special insp, tests and approvals.
|
BLD-Foundation | 9/22/2008 | 9/23/2008 | 9/23/2008 | A | PART |
Mike Jordan
|
|
|
DALE Phone #: ###-####. INterior and exterior column pad footings on grids 4 and 5. Will have special insp.
|
BLD-Foundation | 9/18/2008 | 9/19/2008 | 9/19/2008 | A | PART |
Mike Jordan
|
|
|
gale - 10:00 pouring concrete Phone #: ###-####
|
BLD-Foundation | 9/16/2008 | 9/16/2008 | 9/16/2008 | A | PASS |
Jim Storey
|
|
|
Dale Phone #: ###-#### 3dr floor at stair towers ok mti on site ok
|
BLD-Footing | 9/9/2008 | 9/10/2008 | 9/10/2008 | A | PART |
Jim Sly
|
|
|
dale Phone #: ###-#### North stair tower 2nd floor walls OK pending MTI special insp. tests and approvals.
|
BLD-Foundation | 9/3/2008 | 9/4/2008 | 9/4/2008 | A | PART |
Jim Sly
|
|
|
dale Phone #: ###-#### Grade beams at East and South wall appear OK........Pending MTI special inspection, tests and approvals.
|
BLD-Foundation | 8/29/2008 | 8/29/2008 | 8/29/2008 | A | PART |
Mike Jordan
|
|
|
dale- ###-####. INterior column pad footings.
|
BLD-Footing | 8/22/2008 | 8/25/2008 | 8/25/2008 | A | PASS |
Mike Jordan
|
|
|
dale Phone #: ###-####. Mat footing for north stair tower and mech. room. Also reveiwed all special insp. reports to date.
|
BLD-Footing | 8/19/2008 | 8/20/2008 | 8/20/2008 | P | PART |
Mike Jordan
|
|
|
Dale Phone #: ###-####. Column pad footings for grade beams at gridline 1 and h.
|
BLD-Footing | 8/18/2008 | 8/19/2008 | 8/19/2008 | A | PART |
Jim Storey
|
|
|
Dale- late morning if possible Phone #: ###-#### placed w si
|
BLD-Foundation | 8/12/2008 | 8/13/2008 | 8/13/2008 | A | PART |
Mike Jordan
|
|
|
dale - after 10:00 please Phone #: ###-####. MAt footing for elevator and stair tower. wip on bottom mat. All soils have been tested and evaluated by MTI (special insp) will also have specail insp on all aspects of const.
|