BLD-Final | 5/12/2009 | 5/12/2009 | 5/12/2009 | P | PASS |
Mike Jordan
|
|
|
joe - around 1 please Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 3/4/2009 | 3/6/2009 | 3/6/2009 | P | PART |
Tom Arcoraci
|
|
|
Joe Phone #: ###-#### ok for temp
|
FIRE-Final Inspection | 3/5/2009 | 3/6/2009 | 3/6/2009 | A | PASS |
Troy Cobbley
|
|
|
LIfe safety passed. Alan is to verify the operation of the fire smoke dampers. Mark Senteno approved the narrow gates and the deletion of the Opticon systm and the Knox key box
|
FIRE-Final Inspection | 3/4/2009 | 3/5/2009 | 3/5/2009 | A | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm permit needs to be finaled. Mount the occupant load signs, provide signage on the riser room and facp rooms as discussed. Provide exit discharge light at the main exit.
|
FIRE-Final Inspection | 3/3/2009 | 3/4/2009 | 3/4/2009 | A | FAIL |
Troy Cobbley
|
|
|
The only items inspected today was the exit signs/emergency lighting. See the city approved plans for locations where devices are missing or inoperative.
|
BLD-Final | 3/2/2009 | 3/3/2009 | 3/3/2009 | A | NR |
Mike Jordan
|
|
|
Joe Phone #: ###-####. Needs other trades and zoning first. Contacted Joe wtih EKC and let him know what needed to be completed prior to structural sign off.
|
FIRE-Conference | 3/2/2009 | 3/2/2009 | 3/2/2009 | P | DONE |
Troy Cobbley
|
|
|
All a/v's are now meeting the height requirements of NFPA 72.
|
BLD-Wall cover | 2/25/2009 | 2/26/2009 | 2/26/2009 | A | PASS |
Jim Storey
|
|
|
Joe- cover Phone #: ###-#### new entry ok to cover 2 layers 5/8 gyp
|
BLD-Framing/Rough-in | 2/25/2009 | 2/25/2009 | 2/25/2009 | P | DEFR |
Jim Storey
|
|
|
Joe- cover Phone #: ###-#### work not ready for insp. defered to am.301
|
BLD-Framing/Rough-in | 2/18/2009 | 2/19/2009 | 2/19/2009 | A | PART |
Jim Sly
|
|
|
Joe Phone #: ###-#### Framing OK Panic vestible....Fire caulk OK at interrogation area rated walls.
|
BLD-Conference | 2/11/2009 | 2/11/2009 | 2/11/2009 | P | PART |
Mike Jordan
|
|
|
Inspected required structural upgrade, also inspected membrane and thruogh penetrations for 1hr. wall. Info from architect is incomplete, received design listings only no details. Called and left message with architect.
|
BLD-Other | 2/5/2009 | 2/5/2009 | 2/5/2009 | P | PASS |
Mike Jordan
|
|
|
joe Note: rebar - 4:00 pour schedule Phone #: ###-####
|
BLD-Footing | 1/30/2009 | 2/2/2009 | 2/2/2009 | A | DONE |
Tom Arcoraci
|
|
|
joe Phone #: ###-#### flag pole
|
BLD-Framing/Rough-in | 1/21/2009 | 1/21/2009 | 1/21/2009 | P | PART |
Mike Jordan
|
|
|
Performed general walk through to see progress of job. Noted that contractor has received membrane and thru penetration details from architect. wip
|
BLD-Footing | 1/21/2009 | 1/21/2009 | 1/21/2009 | P | PASS |
Mike Jordan
|
|
|
Remainder of footing for masonry screen wall.
|
BLD-Framing/Rough-in | 1/12/2009 | 1/12/2009 | 1/12/2009 | P | PASS |
Mike Jordan
|
|
|
1hr. wall, 2nd layer ok.
|
BLD-Framing/Rough-in | 1/7/2009 | 1/8/2009 | 1/8/2009 | A | PART |
Mike Jordan
|
|
|
joe Phone #: ###-####. Interior steel stud framing at 1hr. walls for I occ. hardlids ok, 1st. layer ok. Issued c/n for architect to provide UL approved assemblies for all membrane and thru penetrations.
|
BLD-Foundation | 1/8/2009 | 1/8/2009 | 1/8/2009 | A | PART |
Mike Jordan
|
|
|
wip on conc. art wall. Will have special insp.
|
BLD-Framing/Rough-in | 12/29/2008 | 12/30/2008 | 12/30/2008 | P | PART |
Jim Sly
|
|
|
Joe Please call first If possible around 3pm Phone #: ###-#### 1st layer 2hr walls near S.W. corner of bldg...OK
|
BLD-Other | 12/29/2008 | 12/29/2008 | 12/29/2008 | P | PART |
Jim Sly
|
|
|
logan- stem wall Phone #: ###-#### OK pending MTI special insp, tests and approvals.
|
BLD-Framing/Rough-in | 12/23/2008 | 12/23/2008 | 12/23/2008 | P | PASS |
Mike Jordan
|
|
|
Interior steel stud framing for soffitts.
|
BLD-Framing/Rough-in | 12/11/2008 | 12/11/2008 | 12/11/2008 | P | PASS |
Mike Jordan
|
|
|
nterior steel stud framed walls for area D.
|
BLD-Footing | 12/10/2008 | 12/11/2008 | 12/11/2008 | A | PART |
Mike Jordan
|
|
|
logan Phone #: ###-####. Footings for art wall. Noted special insp.
|
BLD-Framing/Rough-in | 12/8/2008 | 12/8/2008 | 12/8/2008 | P | PART |
Mike Jordan
|
|
|
Joe Phone #: ###-####. Interior steel stud framed walls in area D.
|
BLD-Framing/Rough-in | 11/12/2008 | 11/12/2008 | 11/12/2008 | P | PART |
Mike Jordan
|
|
|
joe Phone #: ###-####. Interior steel stud framed walls in areas A , B. ok to one side only.
|
BLD-Footing | 11/3/2008 | 11/4/2008 | 11/4/2008 | P | DEFR |
Mike Jordan
|
|
|
logan Phone #: ###-####. Footings for new vestibule. Already placed when on site. Did note that special insp. was done.
|
BLD-Footing | 10/30/2008 | 10/31/2008 | 10/31/2008 | A | PASS |
Mike Jordan
|
|
|
logan Phone #: ###-####. Footing for permiter screen wall, South and west portions of site. Special insp. also on site.
|
BLD-Footing | 10/23/2008 | 10/24/2008 | 10/24/2008 | P | PART |
Mike Jordan
|
|
|
logan Phone #: ###-####. Fooring for screenwall, Southwest end of site. Will have special insp.
|