BLD-Final | 12/23/2008 | 12/23/2008 | 12/23/2008 | A | PASS |
Tom Arcoraci
|
|
|
Gordon Phone #: ###-####
|
BLD-Other | 11/21/2008 | 11/24/2008 | 11/24/2008 | A | PASS |
Tom Arcoraci
|
|
|
gordon Note: structural - if any problems please call him Phone #: ###-####
|
BLD-Final | 10/29/2008 | 10/31/2008 | 10/31/2008 | P | PART |
Dave Hannah
|
|
|
Gordon- call 30 mins prior to going Phone #: ###-#### ok for temp occ c/n on site
|
FIRE-Final Inspection | 10/29/2008 | 10/31/2008 | 10/31/2008 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 10/10/2008 | 10/10/2008 | 10/10/2008 | P | FAIL |
Troy Cobbley
|
|
|
See the city approved plans, front sheet, for a list of deficiencies
|
Code Occupancy Approval Temp | | | 10/10/2008 | | DONE |
|
|
|
Staff has granted the builder a 30 day temporary occupancy due to teh fac tha tthe screen located on teh south elevation has not been installed, the parkign is not striped properly, and a DR modification application is currently going though the process to eliminate the trellis on the west elevation and the landscaping on the east side of the buildilng. By November 10, 2008, the modification will have to be processed and the front screen and parkign issues must be remedied or final occupancy will not be issued. ANT 10-10-08
|
BLD-Framing/Rough-in | 9/2/2008 | 9/2/2008 | 9/2/2008 | P | PASS |
Dave Hannah
|
|
|
inspection done on bld08-01581
|
BLD-Foundation | 8/22/2008 | 8/25/2008 | 8/25/2008 | A | PART |
Dave Hannah
|
|
|
gordon Phone #: ###-#### roof drain catch basins ok to pour
|