FIRE-Final Inspection | 1/13/2010 | 1/13/2010 | 1/13/2010 | P | PASS |
Forrest France
|
|
|
C/N items completed, fire life safety finaled.
|
BLD-Final | 1/5/2010 | 1/6/2010 | 1/6/2010 | A | PASS |
Forrest France
|
|
|
Correction items completed, fire life safety final approved.
|
BLD-Final | 1/5/2010 | 1/5/2010 | 1/6/2010 | P | PASS |
Jim Storey
|
|
|
final set per angie b.
|
BLD-Final | 9/29/2009 | 9/29/2009 | 9/29/2009 | P | PART |
Jim Storey
|
|
|
need to test exit door mag lock control devices that are deactavated for temp occ at this time. pending engineer of record letter of review of all rfi's and si records for complance of design. temp occ. aproved.
|
FIRE-Final Inspection | 9/10/2009 | 9/15/2009 | 9/15/2009 | A | PART |
Forrest France
|
|
|
George Phone #: ###-####
|
BLD-Final | 8/4/2009 | 8/5/2009 | 8/7/2009 | A | PART |
Jim Storey
|
|
|
george Phone #: ###-#### temp occ. ok for training of three groups to cert. for fork lift oparation. life saftey in drygoods and office in place and aproved for this use.
|
BLD-Framing/Rough-in | 7/23/2009 | 7/24/2009 | 7/24/2009 | A | PART |
Jim Storey
|
|
|
j.c. - ceiling grid for cover Phone #: ###-####
|
BLD-Conference | 7/22/2009 | 7/22/2009 | 7/22/2009 | A | PASS |
Jim Storey
|
|
|
wlked deep freezer/parshiables and exterior site for final review/ waiting for landings in progess exit signage being added to north end of smal freezer in tunal/ fire stopping of ele piping and glazing at machine rm pending instaltion. all other isues ok.
|
FIRE-Final Inspection | 6/2/2009 | 6/2/2009 | 6/3/2009 | P | PART |
Forrest France
|
|
|
On site conference regarding fire alarm permit work site inspection schedule and related fire sprinkler system interconnections.
|
BLD-Energy code compliance | 5/28/2009 | 5/29/2009 | 5/29/2009 | A | PART |
Jim Sly
|
|
|
JC ###-#### Main office....Bldg envelope Energy code....OK.
|
BLD-Energy code compliance | 5/27/2009 | 5/28/2009 | 5/28/2009 | P | NR |
Jim Sly
|
|
|
jc Phone #: ###-####.....Re-Sched.....
|
BLD-Framing/Rough-in | 5/21/2009 | 5/21/2009 | 5/21/2009 | P | PART |
Jim Storey
|
|
|
CFraming inspection for main office and energy inspection for battery complex please-JC Phone #: ###-#### main office ok to cover pending plm. c/n isued for envlope of produce area.
|
BLD-Conference | 5/14/2009 | 5/15/2009 | 5/15/2009 | A | PASS |
Jim Storey
|
|
|
10:00 am meetting w/strata to review bolting. waked the job with si rep.
|
FIRE-Conference | 5/13/2009 | 5/13/2009 | 5/13/2009 | A | DONE |
Forrest France
|
|
|
On site conference regarding project schedule.
|
BLD-Energy code compliance | 5/12/2009 | 5/13/2009 | 5/13/2009 | P | PASS |
Jim Storey
|
|
|
J.C. Phone #: ###-#### office ok to cover walls and hard lids in produce area.
|
BLD-Framing/Rough-in | 5/11/2009 | 5/12/2009 | 5/12/2009 | A | PART |
Jim Storey
|
|
|
JC- call 30 mins prior to going Phone #: ###-#### ok to insulate
|
BLD-Energy code compliance | 4/15/2009 | 4/16/2009 | 4/16/2009 | A | PASS |
Jim Storey
|
|
|
j.c. - first thing in the morning please Phone #: ###-#### dry goods office ok
|
BLD-Framing/Rough-in | 4/14/2009 | 4/15/2009 | 4/15/2009 | A | PASS |
Jim Storey
|
|
|
j.c. Phone #: ###-####
|