BLD-Final | 3/5/2009 | 3/6/2009 | 3/6/2009 | A | PASS |
Tom Arcoraci
|
|
|
Daryl Phone #: ###-####
|
FIRE-Final Inspection | 3/5/2009 | 3/6/2009 | 3/6/2009 | A | PASS |
Troy Cobbley
|
|
|
life safety passed;
Note: sprinklers were installed and finaled under FIR08-00541. Fire alarm monitoring was installed and finaled under FIR08-00593. SLR 3-6-09
|
FIRE-Final Inspection | 2/27/2009 | 3/2/2009 | 3/2/2009 | A | PART |
Troy Cobbley
|
|
|
LIfe safety will be ok to final when the shell permit is finaled.
|
FIRE-Final Inspection | 2/24/2009 | 2/25/2009 | 2/25/2009 | A | FAIL |
Troy Cobbley
|
|
|
See the correction notice left at the job site for items needing addressed.. Per a conversation with Scott the remote FDC and PIV arer not required. I measured the distance from the existing fire hydrant to the now wall mounted PIV and FDC and the distance is roughly 250'-0" which is ok with Scott.
|
BLD-Final | 1/22/2009 | 1/23/2009 | 1/23/2009 | A | PART |
Jim Storey
|
|
|
darrell Note: 9:00 am Phone #: ###-#### need fire life saftey sign off/ ada signage/ mirriors/ tp despencers/ all other bld insp. ok.
|
BLD-Energy code compliance | 12/16/2008 | 12/17/2008 | 12/18/2008 | P | PASS |
Jim Storey
|
|
|
Steve Phone #: ###-####
|
BLD-Energy code compliance | 10/29/2008 | 10/30/2008 | 10/30/2008 | A | PASS |
Jim Storey
|
|
|
steve Phone #: ###-#### frame and insulation ok for cover.
|
BLD-Energy code compliance | 10/17/2008 | 10/17/2008 | 10/17/2008 | P | NR |
Jim Storey
|
|
|
steve Phone #: ###-#### need plm permit.
|
BLD-Energy code compliance | 10/3/2008 | 10/7/2008 | 10/7/2008 | P | FAIL |
Jim Storey
|
|
|
steve Phone #: ###-#### need shell framing and trades as well as ti framing and trades/ stoped work bldg. insulated w/o aproval.
|