Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD08-01871
StatusFinaled
Name IRONHEAD CONSTRUCTION
Site Address 6776 W VICTORY RD
Project NameHORTON FLUID POWER
Customer Number 
ePlanReviewNo
Description
Horton Fluid Power - To construct a new 11,525 square foot, one story with 760 square foot mezzanine, pre-engineered steel building and related site improvements. This building is for a 9,075 square foot Maintenance and Repair shop and a 2,450office first floor office with 760 square foot mezzanine office and storage area. This building is fully fire sprinkled. The sprinklers are used for area increase. All construction per the approved plans and attached comment list. DRH08-00159 JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final7/1/20097/2/20097/2/2009PPASS
DetailsTom Arcoraci
Mike Phone #: ###-####
FIRE-Final Inspection7/1/20097/2/20097/2/2009APASS
DetailsTroy Cobbley
Life safety passed. The racks will be limited to no more than 8'-0" in height.
BLD-Other6/15/20096/15/20096/15/2009PPASS
DetailsTom Arcoraci
BLD-Other6/12/20096/15/20096/15/2009APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 6/12/2009 at 2:00:52 PM. Contact: ###-####.
BLD-Other5/7/20095/7/20095/7/2009PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 5/7/2009 at 10:19:27 AM. Contact: ###-####.
BLD-Energy code compliance4/30/20095/1/20095/1/2009PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 4/30/2009 at 5:08:40 PM. Contact: ###-####.
BLD-Conference4/22/20094/22/20094/22/2009PPASS
DetailsTom Arcoraci
Mike Phone #: ###-####
BLD-Other3/20/20093/20/20093/20/2009PPASS
DetailsTom Arcoraci
BLD-Other3/18/20093/19/20093/19/2009APASS
DetailsTom Arcoraci
Mike- roof drain Phone #: ###-####
BLD-Concrete3/13/20093/16/20093/16/2009PPASS
DetailsTom Arcoraci
mike - rebar Phone #: ###-####
BLD-Foundation1/14/20091/15/20091/15/2009APASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 1/14/2009 at 4:58:42 PM. Contact: ###-####.
BLD-Footing1/9/20091/12/20091/12/2009PPASS
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 1/9/2009 at 4:53:01 PM. Contact: ###-####. wip ok
BLD-Footing1/5/20091/5/20091/5/2009PPASS
DetailsTom Arcoraci
mike Note: rebar Phone #: ###-####
BLD-Footing12/22/200812/23/200812/22/2008ACANC
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/22/2008 at 4:55:01 PM. Contact: ###-####. Disp set to [CANC] by a contractor via Hello! on Dec 22 2008 5:04PM.
BLD-Footing12/19/200812/22/200812/22/2008PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/19/2008 at 4:58:16 PM. Contact: ###-####. wip footings ok
BLD-Footing12/16/200812/17/200812/17/2008PPART
DetailsTom Arcoraci
Scheduled by a contractor via Hello! on 12/16/2008 at 4:45:25 PM. Contact: ###-####.