BLD-Final | 10/15/2009 | 10/15/2009 | 10/15/2009 | P | PASS |
Tony Young
|
|
|
jerry Phone #: ###-####
|
BLD-Final | 10/2/2009 | 10/5/2009 | 10/5/2009 | A | PART |
Tony Young
|
|
|
Patrick Phone #: ###-####
|
BLD-Final | 10/5/2009 | 10/5/2009 | 10/5/2009 | P | PART |
Tony Young
|
|
|
Jerry; Phone #: ###-#### recieved letter from engineer,, need zoning still,, temp guard rails and handrails on rebuilt steps on exterior,, TEMP occ. still ok
|
BLD-Final | 10/2/2009 | 10/2/2009 | 10/2/2009 | P | PART |
Tony Young
|
|
|
Patrick Phone #: ###-#### temp occ ok
|
FIRE-Final Inspection | 10/2/2009 | 10/2/2009 | 10/2/2009 | A | PASS |
Forrest France
|
|
|
Fire life safety correction items and project related FIR permits verified for compliance, inspection passed.
|
BLD-Final | 9/30/2009 | 10/1/2009 | 10/2/2009 | P | PART |
Tony Young
|
|
|
patrick Phone #: ###-#### on site conf on final
|
FIRE-Final Inspection | 9/29/2009 | 9/30/2009 | 9/30/2009 | P | PART |
Forrest France
|
|
|
Items on correction notice verified for completion, final pending project related FIR permit final.
|
FIRE-Final Inspection | 9/24/2009 | 9/25/2009 | 9/28/2009 | P | FAIL |
Forrest France
|
|
|
See fire code review note items numbers 1, 15, 17 for details, door hardware at some locations is not approved, gates at FD access road are incomplete, thresholds at the gym are not finished, noted one missing exit sign at the new gym per red-line plan annotations, discussed items needed for finals.
|
FIRE-Final Inspection | 9/23/2009 | 9/24/2009 | 9/24/2009 | A | NR |
Forrest France
|
|
|
Project related FIR permits must be finaled prior to building fire life safety approvals.
|
BLD-Framing/Rough-in | 9/11/2009 | 9/11/2009 | 9/14/2009 | P | PASS |
Tony Young
|
|
|
jerry - ceiling grid Phone #: ###-####
|
BLD-Conference | 9/4/2009 | 9/8/2009 | 9/8/2009 | A | PART |
Tony Young
|
|
|
Jerry Phone #: ###-#### ok to move some eqmt into basement room
|
FIRE-Conference | 8/28/2009 | 8/28/2009 | 8/28/2009 | P | DONE |
Troy Cobbley
|
|
|
Per Scott Arlenno and Mark Sentenno a job site meeting with the general contractor was held and the general contractor was notified which areas of the school were ok to occupy and which areas are not ok to occupy.
|
BLD-Framing/Rough-in | 8/21/2009 | 8/21/2009 | 8/21/2009 | P | PART |
Tony Young
|
|
|
Jerry-ceiling grid inspection please Phone #: ###-#### misc grid work,, most ok,, pending trades,, general walk through of project
|
BLD-Framing/Rough-in | 7/10/2009 | 7/10/2009 | 7/10/2009 | P | CANC |
Tony Young
|
|
|
Jerry Phone #: ###-####
|
BLD-Framing/Rough-in | 7/9/2009 | 7/10/2009 | 7/10/2009 | A | PART |
Tony Young
|
|
|
Jerry Phone #: ###-#### misc walls ,, ok
|
BLD-Framing/Rough-in | 6/26/2009 | 6/26/2009 | 6/26/2009 | P | PART |
Tony Young
|
|
|
jerry Phone #: ###-#### partial wall on north,, interior walls main level bathrooms,, ceiling grids in basement on east side ok pending trades
|
BLD-Framing/Rough-in | 6/25/2009 | 6/26/2009 | 6/26/2009 | A | CANC |
Tony Young
|
|
|
jerry Phone #: ###-####
|
BLD-Wall cover | 6/16/2009 | 6/17/2009 | 6/17/2009 | A | PART |
Tony Young
|
|
|
Jerry Phone #: ###-#### soth side exterior shear ok
|
BLD-Wall cover | 6/10/2009 | 6/11/2009 | 6/11/2009 | A | PART |
Tony Young
|
|
|
jerry Phone #: ###-####, shear west side on north ok,, walls in basement ok to cover pending trades
|
BLD-Framing/Rough-in | 6/9/2009 | 6/10/2009 | 6/10/2009 | A | PART |
Tony Young
|
|
|
jerry Phone #: ###-#### west side,, wip shear
|
BLD-Framing/Rough-in | 6/4/2009 | 6/4/2009 | 6/4/2009 | P | PART |
Tony Young
|
|
|
Shear inspection please-Jerry Phone #: ###-#### north ext shear ok
|
BLD-Framing/Rough-in | 5/28/2009 | 5/29/2009 | 5/29/2009 | A | PART |
Tony Young
|
|
|
Jerry Phone #: ###-#### studs ok to start covering on exterior for shear,, will add screws as needed,, add shots in plate as needed
|
BLD-Conference | 5/27/2009 | 5/28/2009 | 5/28/2009 | A | PART |
Tony Young
|
|
|
Jerry Phone #: ###-#### wip on fixes
|
BLD-Framing/Rough-in | 5/26/2009 | 5/27/2009 | 5/27/2009 | A | PART |
Tony Young
|
|
|
Jerry Phone #: ###-#### part,, need struct ok on as built on screw connection on double studs,, and on track connection,, ok to one side basement area pending trade ok's,,
|
BLD-Conference | 4/28/2009 | 4/29/2009 | 4/29/2009 | A | PART |
Tony Young
|
|
|
jerry Phone #: ###-#### walk about on job,, ok to put some sheet rock on upper wall line B for ducting
|
BLD-Concrete | 3/10/2009 | 3/11/2009 | 3/11/2009 | A | PART |
Tony Young
|
|
|
jerry - wall Phone #: ###-#### pending s i
|
BLD-Other | 3/2/2009 | 3/3/2009 | 3/3/2009 | A | PEND |
Tony Young
|
|
|
Jerry- rebar Phone #: ###-#### pending S.I.
|
BLD-Foundation | 2/24/2009 | 2/25/2009 | 2/25/2009 | A | PART |
Tony Young
|
|
|
jerry Phone #: ###-####,, elevator pit wall ok pending special inspection report
|
BLD-Footing | 2/23/2009 | 2/24/2009 | 2/24/2009 | A | PART |
Tony Young
|
|
|
jerry Phone #: ###-#### wip,, pending special inspection report,, interior column ftgs
|
BLD-Footing | 2/19/2009 | 2/20/2009 | 2/23/2009 | A | PART |
Tony Young
|
|
|
jerry Phone #: ###-#### pending special inspection
|
BLD-Footing | 2/17/2009 | 2/17/2009 | 2/17/2009 | A | PART |
Tony Young
|
|
|
jerry - rebar - around 11:00 if possible Phone #: ###-#### pending s. i. report
|
BLD-Other | 2/5/2009 | 2/6/2009 | 2/6/2009 | A | PART |
Jim Storey
|
|
|
jerry Note: rebar Phone #: ###-####placed w si pending report.
|
BLD-Other | 1/15/2009 | 1/16/2009 | 1/16/2009 | A | PASS |
Tony Young
|
|
|
jerry Note: rebar massonary Phone #: ###-#### ok pending s. i. report
|
BLD-Framing/Rough-in | 12/30/2008 | 12/31/2008 | 12/31/2008 | P | PART |
Tony Young
|
|
|
Jerry,, temporary ramp,, ok,, ramp on north side
|
BLD-Other | 12/29/2008 | 12/30/2008 | 12/30/2008 | A | PART |
Tony Young
|
|
|
jerry Note: rebar Phone #: ###-#### 10 interior ftgs for temp bracing in basement pending special inspection report
|
BLD-Framing/Rough-in | 12/26/2008 | 12/29/2008 | 12/29/2008 | A | PART |
Tony Young
|
|
|
jerry Phone #: ###-####,, ramp framing frame ok on temp ramp,, needs hand rails etc.
|
BLD-Framing/Rough-in | 12/24/2008 | 12/26/2008 | 12/26/2008 | A | CANC |
Tony Young
|
|
|
jerry Phone #: ###-####,, ramp framing will do on Monday
|
BLD-Framing/Rough-in | 12/24/2008 | 12/24/2008 | 12/26/2008 | P | CANC |
Tony Young
|
|
|
jerry Phone #: ###-####,, ramp framing
|
BLD-Framing/Rough-in | 12/23/2008 | 12/24/2008 | 12/24/2008 | A | CANC |
Tony Young
|
|
|
jerry Phone #: ###-####
|
BLD-Footing | 12/15/2008 | 12/16/2008 | 12/16/2008 | P | PART |
Tony Young
|
|
|
jerry Note: rebar Phone #: ###-#### ftgs for trash encloser,, pending SI report
|
BLD-Conference | 12/10/2008 | 12/11/2008 | 12/12/2008 | A | PASS |
Tony Young
|
|
|
jerry Phone #: ###-#### job conf,, ok
|
BLD-Footing | 12/11/2008 | 12/12/2008 | 12/12/2008 | A | PASS |
Tony Young
|
|
|
JERRY Phone #: ###-#### temp ftgs for wall bracing ok,, 2 upper outside ftgs5"x10" by 24"
|
BLD-Conference | 12/9/2008 | 12/10/2008 | 12/10/2008 | A | PART |
Tony Young
|
|
|
jerry Phone #: ###-#### pre construction meeting,, ok
|