BLD-Final | 6/17/2009 | 6/17/2009 | 6/17/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 6/17/2009 at 9:24:29 AM.
|
DOC - Permit Finaled | 6/17/2009 | 6/17/2009 | 6/17/2009 | P | PASS |
Mike Jordan
|
|
|
Cert. of occ issued.
|
BLD-Final | 4/29/2009 | 4/29/2009 | 4/29/2009 | P | NR |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Needs elec. ri first.
|
BLD-Other | 4/9/2009 | 4/9/2009 | 4/9/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/9/2009 at 8:03:58 AM. Verified installation of exterior weather barrier.
|
BLD-Framing/Rough-in | 4/3/2009 | 4/3/2009 | 4/3/2009 | A | CANC |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/3/2009 at 6:08:08 AM.
|
BLD-Energy code compliance | 4/3/2009 | 4/3/2009 | 4/3/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/3/2009 at 6:08:08 AM. ok to cover.
|
BLD-Energy code compliance | 4/2/2009 | 4/2/2009 | 4/2/2009 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/2/2009 at 6:04:09 AM.
|
BLD-Framing/Rough-in | 4/1/2009 | 4/1/2009 | 4/1/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/1/2009 at 5:31:09 AM.
|
BLD-Framing/Rough-in | 4/1/2009 | 4/1/2009 | 4/1/2009 | A | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 4/1/2009 at 5:28:55 AM. Scheduled for pm.
|
BLD-Framing/Rough-in | 3/17/2009 | 3/17/2009 | 3/17/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Nailing for both layers of 5/8 type x rock from ceiling to underside of roof deck, both sides.
|
BLD-Framing/Rough-in | 3/16/2009 | 3/16/2009 | 3/16/2009 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/16/2009 at 11:17:49 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/5/2009 | 3/5/2009 | 3/5/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. 2nd flooe, 2nd. layer, remaining side of 5/8 type x rock for 2hr. wall.
|
BLD-Framing/Rough-in | 3/4/2009 | 3/4/2009 | 3/4/2009 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/4/2009 at 7:10:23 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/3/2009 | 3/3/2009 | 3/3/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/3/2009 at 7:39:13 AM. Contact: ###-####.. 2nd floor, 2nd. layer, one side only. ok.
|
BLD-Framing/Rough-in | 3/2/2009 | 3/2/2009 | 3/2/2009 | P | PART |
Mike Jordan
|
|
|
jim Phone #: ###-####. 2nd. floor, 1st. layer, both sides type x rock for 2hr. fire wall.
|
BLD-Framing/Rough-in | 2/27/2009 | 2/27/2009 | 2/27/2009 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/27/2009 at 8:27:05 AM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/26/2009 | 2/26/2009 | 2/26/2009 | P | NR |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 2/11/2009 | 2/12/2009 | 2/12/2009 | P | PASS |
Mike Jordan
|
|
|
jim - fire wall Phone #: ###-####. 1st. floor, 2nd. layer of type x rock for 2hr. wall, both sides.
|
BLD-Framing/Rough-in | 2/12/2009 | 2/12/2009 | 2/12/2009 | A | PART |
Mike Jordan
|
|
|
jim - fire wall Phone #: ###-####. 1st. floor, 1st. layer, type x rock for 2hr. wall, both sides.
|
BLD-Footing | 2/6/2009 | 2/9/2009 | 2/9/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/6/2009 at 4:14:32 PM. Contact: ###-####. Interior fotings and column pad footings.
|
BLD-Energy code compliance | 1/29/2009 | 1/29/2009 | 1/29/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Rigid foam insul. on interior side of stemwall.
|
BLD-Foundation | 1/27/2009 | 1/27/2009 | 1/27/2009 | P | PASS |
Mike Jordan
|
|
|
bill Phone #: ###-####
|
BLD-Footing | 1/23/2009 | 1/23/2009 | 1/23/2009 | P | PASS |
Mike Jordan
|
|
|
bill Phone #: ###-####. Perimeter footings.
|