BLD-Final | 6/12/2009 | 6/12/2009 | 6/12/2009 | P | PASS |
Dave Hannah
|
|
|
Jim Phone #: ###-####
|
DOC - Permit Finaled | 6/12/2009 | 6/12/2009 | 6/12/2009 | P | PASS |
Dave Hannah
|
|
|
|
BLD-Other | 4/3/2009 | 4/3/2009 | 4/3/2009 | P | CANC |
Mike Jordan
|
|
|
Jim- building wrap Phone #: ###-####
|
BLD-Framing/Rough-in | 3/18/2009 | 3/18/2009 | 3/18/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/18/2009 at 6:20:39 AM. Contact: ###-####. Inspected remaining layer of 5/8 type x rock in garages for 2hr. fire walls. Also verified installation of exterior water resistive barrier.
|
BLD-Energy code compliance | 3/12/2009 | 3/13/2009 | 3/13/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/12/2009 at 8:36:12 PM. Contact: ###-####. ok to rock.
|
BLD-Framing/Rough-in | 3/11/2009 | 3/11/2009 | 3/11/2009 | P | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 3/11/2009 at 7:16:09 AM. Contact: ###-####. ok to insul.
|
BLD-Energy code compliance | 3/10/2009 | 3/11/2009 | 3/11/2009 | P | CANC |
Mike Jordan
|
|
|
Jim Phone #: ###-####
|
BLD-Framing/Rough-in | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. 1st. layer type x rock from ceiling to bottom of roof deck, both sides.
|
BLD-Framing/Rough-in | 2/19/2009 | 2/20/2009 | 2/20/2009 | P | NR |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/19/2009 at 9:59:09 PM. Contact: ###-####.
|
BLD-Framing/Rough-in | 2/19/2009 | 2/19/2009 | 2/19/2009 | P | PASS |
Mike Jordan
|
|
|
jim - firewalls Phone #: ###-####.. Verified fire rated plywood at 4ft. laydown parapet at overbuild areas.
|
BLD-Framing/Rough-in | 2/18/2009 | 2/19/2009 | 2/19/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/18/2009 at 5:07:07 PM. type x rock at overbuild areas ok.
|
BLD-Framing/Rough-in | 2/18/2009 | 2/18/2009 | 2/18/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 2nd. floor, 2nd. layer, both sides type x rock for 2hr. wall.
|
BLD-Framing/Rough-in | 2/17/2009 | 2/17/2009 | 2/17/2009 | P | PART |
Mike Jordan
|
|
|
Jim- Fire wall Phone #: ###-####. 2nd. floor, 1st. layer 5/8 type x rock for 2hr. wall, both sides.
|
BLD-Framing/Rough-in | 2/11/2009 | 2/13/2009 | 2/13/2009 | P | NR |
Mike Jordan
|
|
|
jim - fire wall Phone #: ###-####
|
BLD-Framing/Rough-in | 2/10/2009 | 2/11/2009 | 2/11/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st. floor, 2nd. layer 5/8 type x rock for 2hr. wall, both sides.
|
BLD-Framing/Rough-in | 2/10/2009 | 2/11/2009 | 2/11/2009 | A | PART |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st.floor, 5/8 type x rock for 2hr. wall, remaining side.
|
BLD-Framing/Rough-in | 2/10/2009 | 2/10/2009 | 2/10/2009 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. 1st. floor, 5/8 type x rock for 2hr. wall, one side only.
|
BLD-Conference | 2/5/2009 | 2/5/2009 | 2/5/2009 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Footing | 2/4/2009 | 2/5/2009 | 2/5/2009 | A | PASS |
Mike Jordan
|
|
|
Scheduled by a contractor via Hello! on 2/4/2009 at 2:51:43 PM. Contact: ###-####. Interior footings.
|
BLD-Energy code compliance | 1/23/2009 | 1/23/2009 | 1/23/2009 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. rigid insul. on interior side of stemwall.
|
BLD-Foundation | 1/22/2009 | 1/22/2009 | 1/22/2009 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Foundation | 1/21/2009 | 1/22/2009 | 1/22/2009 | A | NR |
Mike Jordan
|
|
|
bill Phone #: ###-####. REscheduled for pm.
|
BLD-Footing | 1/20/2009 | 1/21/2009 | 1/21/2009 | A | PASS |
Mike Jordan
|
|
|
Jim-###-####. Exterior perimeter footings.
|