Permit Information
Permit NumberBLD08-02207
StatusFinaled
Name PARADIGM CONSTRUCTION COMPANY LLC
Site Address 8891 W EVENING STAR LN
Project NamePinetree Village
Customer Number 
ePlanReviewNo
Description
(Unit 1 Building 15) This permit is for the construction of a new townhouse with three attached units. This is unit 1 that has a total of 1401 square feet with an attached garage of 431 square feet. The main level is 627 square feet with one bathroom, a kitchen, and a covered front porch of 48 square feet. The second story is a total of 774 with three bedrooms and two bathrooms. The setback from the side property line is five feet for this building and will require the eaves to be fire rated to one hour on the underneath side per the detail on the approved plans. Epoxy anchors are being used on the interior walls and these will require a special inspector's sign off that will be provided to the City of Boise inspector on site. SEE COMMENTS FOR INFO. The furnace has been placed in the attic space and will require a walkway in the attic and a working platform, see attached plan review report for details. The separation wall is build to WP4136 as noted and detailed on the approved plans. This two hour wall may not have any penetrations, the columns in the garage must be placed inside the separation wall. R-2D zoning district, building setbacks, CUP07-000150, CUP08-00058, and DRH08-00043 per Planning and Zoning. Built per all approved plans, red lining, engineering and plan review report. (BSP)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final12/1/200912/2/200912/2/2009PPASS
DetailsMike Jordan
Phone #: ###-#### Internet Inspection Request from: James Larkin
DOC - Permit Finaled12/2/200912/2/200912/2/2009PPASS
DetailsMike Jordan
Cert. of occ. issued.
BLD-Other4/3/20094/3/20094/3/2009PPASS
DetailsMike Jordan
Jim- building wrap Phone #: ###-####.. Verified installation of weather resistive barrier.
BLD-Other3/20/20093/20/20093/20/2009PPASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 3/20/2009 at 7:01:46 AM. Contact: ###-####. double layer 5/8 type x rock under soffitt.
BLD-Framing/Rough-in3/9/20093/9/20093/10/2009PCANC
DetailsMike Jordan
Jim Phone #: ###-####
BLD-Energy code compliance3/6/20093/9/20093/9/2009APASS
DetailsMike Jordan
Jim Phone #: ###-####. ok to rock.
BLD-Energy code compliance3/5/20093/5/20093/5/2009PCANC
DetailsMike Jordan
jim Phone #: ###-####
BLD-Framing/Rough-in3/5/20093/5/20093/5/2009PPASS
DetailsMike Jordan
jim Phone #: ###-####. ok to insul.
BLD-Framing/Rough-in2/23/20092/23/20092/23/2009PCANC
DetailsMike Jordan
jim Phone #: ###-####
BLD-Framing/Rough-in2/19/20092/20/20092/20/2009PCANC
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/19/2009 at 10:03:02 PM. Contact: ###-####.
BLD-Framing/Rough-in2/19/20092/19/20092/19/2009PNR
DetailsMike Jordan
jim - firewalls Phone #: ###-####
BLD-Framing/Rough-in2/18/20092/19/20092/19/2009APASS
DetailsMike Jordan
Scheduled by a contractor via Hello! on 2/18/2009 at 5:14:42 PM. Contact: ###-####. 2nd layer type x rock from ceiling to roof deck, also verified nailing on type x rock for overbuilds and rated plywood for 4ft. parapet at overbuilds.
BLD-Framing/Rough-in2/18/20092/18/20092/18/2009PPASS
DetailsMike Jordan
Jim Phone #: ###-####. 2nd. floor, 2nd. layer, both sides, type x rock for 2hr. wall, also 1st. layer from ceiling to roof deck.
BLD-Framing/Rough-in2/17/20092/17/20092/17/2009PPASS
DetailsMike Jordan
Jim- Fire wall Phone #: ###-####. 2nd. floor, 5/8 type x rock, remaining side.
BLD-Framing/Rough-in2/11/20092/13/20092/17/2009PPART
DetailsMike Jordan
jim - fire wall Phone #: ###-####. 2nd. floor, 5/8type x rock one side only for 2hr. wall.
BLD-Framing/Rough-in2/10/20092/11/20092/11/2009PPASS
DetailsMike Jordan
Jim Phone #: ###-####. 1st. floor, 2nd. layer 5/8 typex rock for 2hr. wall both sides.
BLD-Framing/Rough-in2/10/20092/11/20092/11/2009APART
DetailsMike Jordan
Jim Phone #: ###-####. 1st floor, 5/8 type x rock for 2hr. wall, remaining side.
BLD-Framing/Rough-in2/10/20092/10/20092/10/2009PPART
DetailsMike Jordan
Jim Phone #: ###-####. 1st.floor, 5/8type x rock for 2hr. wall. one side only.
BLD-Energy code compliance1/23/20091/23/20091/23/2009PPASS
DetailsMike Jordan
jim Phone #: ###-####. Rigid insul. at interior side of stemwal.
BLD-Foundation1/22/20091/22/20091/22/2009PPASS
DetailsMike Jordan
BLD-Foundation1/21/20091/22/20091/22/2009ANR
DetailsMike Jordan
bill Phone #: ###-####. Rescheduled for pm.
BLD-Footing1/20/20091/21/20091/21/2009APASS
DetailsMike Jordan
Exterior perimeter footings.