BLD-Final | 1/27/2009 | 1/28/2009 | 1/28/2009 | A | PASS |
Dave Hannah
|
|
|
dean Phone #: ###-#### ok for perm occ
|
BLD-Final | 1/22/2009 | 1/23/2009 | 1/23/2009 | A | PART |
Dave Hannah
|
|
|
dean Phone #: ###-#### everything ok but needs a plumbing final
|
FIRE-Final Inspection | 1/22/2009 | 1/22/2009 | 1/22/2009 | P | PASS |
Forrest France
|
|
|
Life safety inspection passed, contractor to replace one lamp at the EM light fixture in the stairway to the mezzanine as discussed.
|
BLD-Other | 12/16/2008 | 12/17/2008 | 12/17/2008 | A | PART |
Dave Hannah
|
|
|
dean Note: ceiling grid Phone #: ###-#### ok to cover ceiling also I have a letter from the engineer oking structal on clouds I also talked with Roy McGlothin on 12/16 at around 10:00am about framing changes on clouds he told me that he was ok with everything
|
BLD-Framing/Rough-in | 12/11/2008 | 12/12/2008 | 12/12/2008 | A | FAIL |
Dave Hannah
|
|
|
dean Phone #: ###-#### letter from engineer dont ok clouds
|
BLD-Framing/Rough-in | 11/26/2008 | 12/1/2008 | 12/1/2008 | A | PART |
Dave Hannah
|
|
|
Scheduled by a contractor via Hello! on 11/26/2008 at 2:57:22 PM. ok to cover walls but need the engineer to ok the constrution of the lighing clouds hanging down from ceiling not per plans
|
BLD-Framing/Rough-in | 11/3/2008 | 11/3/2008 | 11/4/2008 | P | PASS |
Dave Hannah
|
|
|
dean Phone #: ###-#### ok to sheet floor under safe
|