BLD-Final | 6/1/2009 | 6/2/2009 | 6/2/2009 | P | PART |
Mike Jordan
|
|
|
christine Phone #: ###-####. ok for temp occ. Needs to install remaing glazing in doors, provide hc signs and complete firecaulking in riser room.
|
FIRE-Final Inspection | 6/1/2009 | 6/2/2009 | 6/2/2009 | A | PASS |
Troy Cobbley
|
|
|
Life Safety Passed
|
FIRE-Final Inspection | 6/1/2009 | 6/1/2009 | 6/1/2009 | P | FAIL |
Troy Cobbley
|
|
|
The northwest exit discharge light failed to operate.
|
BLD-Other | 5/20/2009 | 5/21/2009 | 5/21/2009 | A | PASS |
Mike Jordan
|
|
|
Christine- grid Phone #: ###-####. Grid ok.
|
BLD-Other | 5/19/2009 | 5/20/2009 | 5/20/2009 | P | FAIL |
Mike Jordan
|
|
|
Christine- grid Phone #: ###-####. Installed grid not per approved plan.
|
BLD-Framing/Rough-in | 4/24/2009 | 4/24/2009 | 4/24/2009 | P | PASS |
Mike Jordan
|
|
|
christine Phone #: ###-####. All issues resolved. Received engineering noting that 2x6 with double top plate is adequate for piont loads. Will have scanned into permit.
|
BLD-Energy code compliance | 4/24/2009 | 4/24/2009 | 4/24/2009 | P | PASS |
Mike Jordan
|
|
|
christine Phone #: ###-####
|
BLD-Framing/Rough-in | 4/22/2009 | 4/23/2009 | 4/23/2009 | A | PART |
Mike Jordan
|
|
|
christine Phone #: ###-####. Needs to add lateral bracing on bottom chords, provide letter from engineer regarding point loads on 2x6 walls. Also needs to provide tbh on truss eg1 and 2.
|
BLD-Framing/Rough-in | 4/22/2009 | 4/22/2009 | 4/22/2009 | P | PART |
Mike Jordan
|
|
|
christine Phone #: ###-####. ok to insul. exterior walls and one side only. Needs to provide new truss engineering and sprinkler ri insp.
|
BLD-Framing/Rough-in | 3/26/2009 | 3/26/2009 | 3/26/2009 | P | PART |
Mike Jordan
|
|
|
roof inspection-christine Phone #: ###-####. Nailing on roof diaphragm ok. Also gave contractor c/n noting to resubmit mezzanine drawings and all applicable engineering showing bonus truss in leiu of TJI and additional square footage added.
|
BLD-Framing/Rough-in | 3/20/2009 | 3/23/2009 | 3/23/2009 | A | PART |
Mike Jordan
|
|
|
building a only please--shear nail christine Phone #: ###-####. Shear nailing on exterior walls only. ok.
|
FIRE-Conference | 3/17/2009 | 3/17/2009 | 3/17/2009 | P | DONE |
Troy Cobbley
|
|
|
I spoke to Brian Johnson with Shilo Automatic Sprinkler about the sizing of the piping from the FDC to the floating main. I gave my interpretation of NFPA 13-8.17.2 but defered him to Tim Frost. The entry is being made under this permit due to the overhead sprinkler permit not being issued at this time.
|
BLD-Foundation | 3/3/2009 | 3/4/2009 | 3/4/2009 | A | PASS |
Mike Jordan
|
|
|
Ian Phone #: ###-####. Stemwall for dumpster enclosure ok.
|
BLD-Foundation | 3/2/2009 | 3/3/2009 | 3/3/2009 | A | PASS |
Mike Jordan
|
|
|
ian Phone #: ###-####. Perimeter stemwalls and column pad pdestals. ok.
|
BLD-Footing | 2/27/2009 | 2/27/2009 | 2/27/2009 | P | PASS |
Mike Jordan
|
|
|
Ian Phone #: ###-####. Perimeter footings and column pad footings ok.
|
BLD-Footing | 2/27/2009 | 2/27/2009 | 2/27/2009 | P | CANC |
Mike Jordan
|
|
|
ian Phone #: ###-####
|
BLD-Footing | 2/25/2009 | 2/26/2009 | 2/26/2009 | P | NR |
Mike Jordan
|
|
|
ian Phone #: ###-####. Contractor will reschedule insp.
|