BLD-Final | 6/29/2009 | 6/29/2009 | 6/29/2009 | P | CANC |
Mike Jordan
|
|
|
christine Phone #: ###-####. ok for perm occ.
|
FIRE-Final Inspection | 6/29/2009 | 6/29/2009 | 6/29/2009 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
FIRE-Final Inspection | 6/25/2009 | 6/26/2009 | 6/26/2009 | P | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm and fire sprinkler permits need finaled and two exit discharge lights on the east side did not work.
|
BLD-Framing/Rough-in | 6/9/2009 | 6/10/2009 | 6/10/2009 | A | PASS |
Mike Jordan
|
|
|
christine - ceiling grid Phone #: ###-####
|
BLD-Other | 5/15/2009 | 5/15/2009 | 5/15/2009 | P | PASS |
Mike Jordan
|
|
|
Chistine Phone #: ###-####. 1hr. const. for fire riser room.
|
BLD-Other | 5/13/2009 | 5/14/2009 | 5/14/2009 | A | CANC |
Mike Jordan
|
|
|
christine - 1 hr construction on a fire riser Phone #: ###-####
|
BLD-Energy code compliance | 5/11/2009 | 5/11/2009 | 5/11/2009 | P | PASS |
Mike Jordan
|
|
|
Christine Phone #: ###-####
|
BLD-Final | 5/7/2009 | 5/8/2009 | 5/8/2009 | A | CANC |
Mike Jordan
|
|
|
christine Phone #: ###-####
|
BLD-Framing/Rough-in | 5/8/2009 | 5/8/2009 | 5/8/2009 | A | PASS |
Mike Jordan
|
|
|
christine Phone #: ###-####
|
BLD-Framing/Rough-in | 4/28/2009 | 4/29/2009 | 4/29/2009 | A | NR |
Mike Jordan
|
|
|
Christine Phone #: ###-####. Needs ri. imsp. from other trades first.
|
BLD-Other | 3/31/2009 | 4/1/2009 | 4/1/2009 | A | PART |
Mike Jordan
|
|
|
Christine- roof nailing Phone #: ###-####. Nailing for roof ok.
|
BLD-Framing/Rough-in | 3/26/2009 | 3/26/2009 | 3/26/2009 | P | PART |
Mike Jordan
|
|
|
Shear Inspection -christine Phone #: ###-####. Exterior shear nailing only, ok. Also gave contactor c/n noting to resubmit mezzanine drawing and all applicable engineering showing use of bonus trusses in leiu of TJI and additional square footage.
|
BLD-Foundation | 3/2/2009 | 3/3/2009 | 3/3/2009 | A | PASS |
Mike Jordan
|
|
|
ian Phone #: ###-####. Perimeter stemwalls and pedestals on column pad footings. ok.
|
BLD-Footing | 3/2/2009 | 3/2/2009 | 3/2/2009 | P | PASS |
Mike Jordan
|
|
|
Ian Phone #: ###-####. Exterior column pad footings.
|
BLD-Footing | 2/25/2009 | 2/26/2009 | 2/26/2009 | P | PASS |
Mike Jordan
|
|
|
ian Phone #: ###-####. Perimeter footings ok.
|