BLD-Final | 8/27/2009 | 8/28/2009 | 8/28/2009 | A | PASS |
Jim Storey
|
|
|
kelly Phone #: ###-####
|
DOC - Permit Finaled | 8/28/2009 | 8/28/2009 | 8/28/2009 | P | PASS |
Jim Storey
|
|
|
|
BLD-Aging Inspection | 8/3/2009 | 8/3/2009 | 8/3/2009 | | PASS |
Jim Storey
|
|
|
p$z has bond posted until nov.
|
BLD-Conference | 6/3/2009 | 6/3/2009 | 6/3/2009 | P | PART |
Jim Storey
|
|
|
shell ok to the point of life saftey and bonded for completion of work with p&z. ec and bld finals to be performed on unleased area north of ti.
|
FIRE-Final Inspection | 6/2/2009 | 6/2/2009 | 6/2/2009 | P | PASS |
Forrest France
|
|
|
Building shell life safety inspection completed okay, hardware at the west exit doors to be made compliant prior to occupancy approvals.
|
BLD-Conference | 5/14/2009 | 5/14/2009 | 5/14/2009 | P | PASS |
Jim Storey
|
|
|
recieved si and engineers letter to resolve hold downs. ok to insulate.
|
BLD-Foundation | 3/24/2009 | 3/25/2009 | 3/25/2009 | A | PASS |
Jim Storey
|
|
|
Ian Phone #: ###-####
|
BLD-Footing | 3/24/2009 | 3/25/2009 | 3/25/2009 | A | PASS |
Jim Storey
|
|
|
dane Phone #: ###-####
|
BLD-Framing/Rough-in | 2/17/2009 | 2/17/2009 | 2/17/2009 | P | PART |
Jim Storey
|
|
|
Wall sheeting Phone #: ###-#### nailling ok missing hold downs 4 locations 2 east 2 west center of bldg. pending engineering to resolve.
|
BLD-Framing/Rough-in | 2/5/2009 | 2/6/2009 | 2/6/2009 | A | PART |
Jim Storey
|
|
|
kelly fisher Phone #: ###-#### roof perimitor nailling ok to build crickets.
|
BLD-Foundation | 1/14/2009 | 1/14/2009 | 1/14/2009 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/14/2009 at 11:22:25 AM. Contact: ###-####.walls ok pending center ft pads
|
BLD-Footing | 1/13/2009 | 1/13/2009 | 1/13/2009 | P | PASS |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 1/13/2009 at 9:41:32 AM. Contact: ###-####.
|