BLD-Final | 2/16/2010 | 2/17/2010 | 2/17/2010 | P | PASS |
Dave Hannah
|
|
|
gene- call 30 mins prior to going Phone #: ###-#### dave bathroom hardware ok ada singage wrong side of the doors 301 ok for perm occ
|
BLD-Final | 2/16/2010 | 2/16/2010 | 2/16/2010 | P | DEFR |
Jim Storey
|
|
|
gene- call 30 mins prior to going Phone #: ###-#### to pm with 425
|
BLD-Final | 12/28/2009 | 12/28/2009 | 12/28/2009 | P | PART |
Dave Hannah
|
|
|
gene Phone #: ###-#### ok for temp occ
|
FIRE-Final Inspection | 12/28/2009 | 12/28/2009 | 12/28/2009 | A | PASS |
Forrest France
|
|
|
Fire life safety inspection passed, correction notice items completed.
|
FIRE-Final Inspection | 12/21/2009 | 12/22/2009 | 12/22/2009 | A | NR |
Forrest France
|
|
|
Project related fire alarm and sprinkler permit work must be finaled prior to life safety approvals. Preliminary check of EM lights and exit signs okayed with the exception of four locations.
|
BLD-Framing/Rough-in | 12/18/2009 | 12/18/2009 | 12/18/2009 | P | PART |
Dave Hannah
|
|
|
Ceiling grid for cover inspection please-Gene Phone #: ###-#### ok to cover ceiling
|
BLD-Framing/Rough-in | 12/16/2009 | 12/17/2009 | 12/17/2009 | A | PART |
Dave Hannah
|
|
|
Gene-Ceiling grid for cover inspection please Phone #: ###-#### ok to put border tiles in after other trades ok
|
BLD-Energy code compliance | 9/30/2009 | 9/30/2009 | 9/30/2009 | P | PART |
Dave Hannah
|
|
|
Gene-insulation on high ceiling area inspection please Phone #: ###-#### ok to cover
|
BLD-Energy code compliance | 9/18/2009 | 9/21/2009 | 9/21/2009 | A | PASS |
Dave Hannah
|
|
|
gene Phone #: ###-#### nw wing ok to cover
|
BLD-Energy code compliance | 9/15/2009 | 9/16/2009 | 9/16/2009 | A | PART |
Dave Hannah
|
|
|
gene Phone #: ###-#### se and sw wing insulation ok framing ok ok to cover
|
BLD-Framing/Rough-in | 9/9/2009 | 9/9/2009 | 9/10/2009 | P | PART |
Dave Hannah
|
|
|
Gene-bolting hold downs and exterior insulation please Phone #: ###-#### shear ok west wing ok to cover walls
|
BLD-Framing/Rough-in | 9/2/2009 | 9/3/2009 | 9/4/2009 | A | PART |
Dave Hannah
|
|
|
Gene Phone #: ###-#### ok to insulate ext walls ok to one side int walls but crew needs to bolt down hold downs also washers on sill plates for shear walls need engineer to reveiw size and type
|
BLD-Framing/Rough-in | 8/27/2009 | 8/27/2009 | 8/27/2009 | P | PART |
Dave Hannah
|
|
|
Gene Phone #: ###-#### high roof ok to cover
|
BLD-Framing/Rough-in | 8/17/2009 | 8/17/2009 | 8/18/2009 | P | PART |
Dave Hannah
|
|
|
Gene-roof nailing for cover inspection please Phone #: ###-#### ok to cover roof
|
BLD-Other | 7/22/2009 | 7/22/2009 | 7/22/2009 | P | DONE |
Dave Hannah
|
|
|
gene - please call 1/2 hr prior - nailing on the roof Phone #: ###-####
|
BLD-Framing/Rough-in | 6/30/2009 | 6/30/2009 | 7/1/2009 | P | DEFR |
Dave Hannah
|
|
|
Gene Phone #: ###-####
|
BLD-Footing | 6/19/2009 | 6/19/2009 | 6/19/2009 | A | PART |
Dave Hannah
|
|
|
Jim ###-####- pouring at 9
|
BLD-Concrete | 5/26/2009 | 5/27/2009 | 5/27/2009 | A | PART |
Dave Hannah
|
|
|
Clint Phone #: ###-#### crews still working on tilt up panels
|
BLD-Footing | 4/20/2009 | 4/21/2009 | 4/21/2009 | A | PART |
Dave Hannah
|
|
|
clint Phone #: ###-####
|
BLD-Footing | 4/14/2009 | 4/15/2009 | 4/15/2009 | A | PART |
Dave Hannah
|
|
|
Clint Phone #: ###-#### int ftgs for under slab mti also on site working on geo and conc and spec inspection
|