FIRE-Final Inspection | 5/25/2010 | 5/26/2010 | 5/26/2010 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 5/25/2010 | 5/26/2010 | 5/26/2010 | P | PASS |
Tom Arcoraci
|
|
|
Brandon-PLease call at least 30 mins prior to inspection Phone #: ###-####
|
BLD-Conference | 4/28/2010 | 4/28/2010 | 4/28/2010 | P | PASS |
Tom Arcoraci
|
|
|
on temp occ
|
BLD-Aging Inspection | 4/28/2010 | 4/28/2010 | 4/28/2010 | | PASS |
Tom Arcoraci
|
|
|
|
BLD-Final | 2/25/2010 | 2/25/2010 | 2/25/2010 | P | PART |
Tom Arcoraci
|
|
|
dale Phone #: ###-#### some accessible issues, fire proofing and glass items . ok for temp
|
FIRE-Final Inspection | 2/24/2010 | 2/24/2010 | 2/24/2010 | P | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Scott's permission until the privacy curtains have been installed and it is verified that they meet NFPA 13 requirements for obstructions.
|
FIRE-Final Inspection | 2/19/2010 | 2/22/2010 | 2/22/2010 | P | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm inspection was cancelled and the project related fire sprinkler permit had not been called in so I performed a conference with Dale and went over life safety items. Along with needing the project related fire permits satified an exit discharge light needs repaired out of the north exit, fire dept access signage provided and provide a copy of the missing fire life safety plan review notes.
|
BLD-Framing/Rough-in | 2/5/2010 | 2/8/2010 | 2/8/2010 | A | PASS |
Tom Arcoraci
|
|
|
Ceiling grid inspection please-Dale Phone #: ###-####
|
BLD-Other | 1/26/2010 | 1/26/2010 | 1/26/2010 | P | PASS |
Tom Arcoraci
|
|
|
Dale Phone #: ###-#### wip ok
|
BLD-Other | 1/13/2010 | 1/20/2010 | 1/20/2010 | A | PASS |
Tom Arcoraci
|
|
|
wip
|
BLD-Wall cover | 1/5/2010 | 1/13/2010 | 1/13/2010 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 1/4/2010 | 1/5/2010 | 1/5/2010 | A | PASS |
Tom Arcoraci
|
|
|
ceiling cover/Dale Phone #: ###-####
|
BLD-Wall cover | 12/9/2009 | 12/16/2009 | 12/16/2009 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 12/15/2009 | 12/15/2009 | 12/15/2009 | P | PASS |
Tom Arcoraci
|
|
|
dale Phone #: ###-#### wip ok to cover grid fire stop 1 hr walls
|
BLD-Wall cover | 12/1/2009 | 12/9/2009 | 12/9/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Framing/Rough-in | 12/1/2009 | 12/1/2009 | 12/1/2009 | P | PASS |
Tom Arcoraci
|
|
|
Dale Phone #: ###-#### wip ok
|
BLD-Wall cover | 11/19/2009 | 11/24/2009 | 11/24/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Other | 11/19/2009 | 11/19/2009 | 11/19/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 11/18/2009 | 11/18/2009 | 11/18/2009 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 11/13/2009 | 11/18/2009 | 11/18/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Energy code compliance | 11/12/2009 | 11/13/2009 | 11/13/2009 | A | PASS |
Tom Arcoraci
|
|
|
Dale Phone #: ###-####
|
BLD-Wall cover | 11/12/2009 | 11/12/2009 | 11/12/2009 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 11/12/2009 | 11/12/2009 | 11/12/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 11/10/2009 | 11/11/2009 | 11/12/2009 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 11/4/2009 | 11/11/2009 | 11/12/2009 | A | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Wall cover | 11/4/2009 | 11/4/2009 | 11/4/2009 | P | PASS |
Tom Arcoraci
|
|
|
roof cover ok wip ok checked misc hardware wip ok
|
BLD-Wall cover | 11/3/2009 | 11/4/2009 | 11/4/2009 | A | PART |
Tom Arcoraci
|
|
|
|
BLD-Wall cover | 10/28/2009 | 11/4/2009 | 11/3/2009 | A | PASS |
Tom Arcoraci
|
|
|
|
BLD-Other | 10/28/2009 | 10/28/2009 | 10/28/2009 | P | PASS |
Tom Arcoraci
|
|
|
wip ok
|
BLD-Other | 10/23/2009 | 10/23/2009 | 10/23/2009 | P | PASS |
Tom Arcoraci
|
|
|
|
BLD-Framing/Rough-in | 10/20/2009 | 10/21/2009 | 10/21/2009 | A | PART |
Tom Arcoraci
|
|
|
dale Phone #: ###-####
|
BLD-Other | 10/6/2009 | 10/7/2009 | 10/7/2009 | A | PASS |
Tom Arcoraci
|
|
|
dale - roof sheating Phone #: ###-####
|
BLD-Foundation | 8/25/2009 | 8/26/2009 | 8/26/2009 | P | PASS |
Mike Jordan
|
|
|
Dale Phone #: ###-####. Interior footings ok.
|
BLD-Foundation | 7/8/2009 | 7/9/2009 | 7/9/2009 | A | PART |
Tom Arcoraci
|
|
|
Dale Phone #: ###-####
|
BLD-Footing | 7/2/2009 | 7/6/2009 | 7/6/2009 | P | PART |
Dave Hannah
|
|
|