BLD-Final | 2/3/2010 | 2/3/2010 | 2/3/2010 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 1/29/2010 | 1/29/2010 | 1/29/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety passed, ceiling tile to be replaced prior to structural final.
|
BLD-Final | 1/28/2010 | 1/29/2010 | 1/29/2010 | P | PART |
Jim Storey
|
|
|
Craig Phone #: ###-#### final occ ok pending plm perm sign off.
|
FIRE-Final Inspection | 1/27/2010 | 1/28/2010 | 1/28/2010 | P | DEFR |
Forrest France
|
|
|
Pending project related fire alarm permit final.
|
BLD-Final | 1/27/2010 | 1/28/2010 | 1/28/2010 | P | DEFR |
Jim Storey
|
|
|
Craig Phone #: ###-####
|
FIRE-Conference | 1/5/2010 | 1/5/2010 | 1/7/2010 | P | DONE |
Forrest France
|
|
|
Regarding items needed for final including project related fire alarm work, door hardware, fire life safety issues.
|
BLD-Wall cover | 12/7/2009 | 12/7/2009 | 12/7/2009 | P | PASS |
Jim Storey
|
|
|
ceilling firestop ok
|
FIRE-Conference | 12/3/2009 | 12/3/2009 | 12/3/2009 | A | DONE |
Forrest France
|
|
|
Regarding exit sign location at the new vestibule.
|
BLD-Energy code compliance | 12/1/2009 | 12/2/2009 | 12/2/2009 | P | PASS |
Jim Storey
|
|
|
craig Phone #: ###-####
|
BLD-Framing/Rough-in | 11/30/2009 | 12/1/2009 | 12/1/2009 | P | PASS |
Jim Storey
|
|
|
Graig Phone #: ###-####
|
BLD-Framing/Rough-in | 11/24/2009 | 11/25/2009 | 11/25/2009 | P | CANC |
Jim Storey
|
|
|
CRAIG Phone #: ###-####
|
BLD-Conference | 11/12/2009 | 11/13/2009 | 11/13/2009 | A | PASS |
Jim Storey
|
|
|
CRAIG Phone #: ###-#### steel support beams ok si ok for epoxy holddowns and ab's in plate interior bearing wall.
|
BLD-Framing/Rough-in | 10/28/2009 | 10/29/2009 | 10/29/2009 | P | PASS |
Jim Storey
|
|
|
Craig Phone #: ###-#### exterior and roof ok to apply gyp and rooffing materials.
|
BLD-Conference | 10/28/2009 | 10/28/2009 | 10/28/2009 | P | PASS |
Jim Storey
|
|
|
Craig Phone #: ###-####
|
BLD-Framing/Rough-in | 10/20/2009 | 10/21/2009 | 10/21/2009 | P | PART |
Jim Storey
|
|
|
craig Phone #: ###-#### ok to gyp coridor walls pending achor bolt/plate rfi to engineer.
|
BLD-Foundation | 10/12/2009 | 10/13/2009 | 10/13/2009 | A | PASS |
Jim Storey
|
|
|
craig Phone #: ###-####
|
BLD-Conference | 10/8/2009 | 10/9/2009 | 10/9/2009 | A | PASS |
Jim Storey
|
|
|
craig Phone #: ###-####
|
BLD-Footing | 10/9/2009 | 10/9/2009 | 10/9/2009 | A | PASS |
Jim Storey
|
|
|
craig Phone #: ###-#### ft and rebar ok
|