Information based on query as of Wednesday, August 14, 2024.
Permit Information
Permit NumberBLD09-00461
StatusFinaled
Name GOLIS CONSTRUCTION
Site Address 4420 N FIVE MILE RD
Project NamePriest Retirement House
Customer Number 
ePlanReviewNo
Description
Priest Retirement Home - To construct a new 16,377 square feet, one story, eight unit, apartment building with common areas and attached garages for retiring Catholic Priests. Each unit has two bedrooms, two bathrooms, a kitchen, and a 55 square feet patio. Each unit has a separate means of egress and also share a common path of egress into and through a 1/2-hour exit corridor with 20 minute fire-resistive, listed, labeled, self-closing door assemblies from the dwelling units into the corridor. All eight units are required to comply as Type 'B' accessible dwelling units. All construction shall be per the approved plans, engineering, and attached plan review report. NOTE: This building is required to be fully fire sprinklered per NFPA 13. CUP07-00171 **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/16/20102/17/20102/17/2010APASS
DetailsJim Sly
Chris Phone #: ###-####
OK for Perm Occ.
FIRE-Final Inspection2/12/20102/16/20102/16/2010APASS
DetailsTroy Cobbley
Life safety passed.
FIRE-Final Inspection2/11/20102/11/20102/11/2010PFAIL
DetailsTroy Cobbley
Per the approved drawings and documents the address is 4450. The address of 4420 has been installed on the building. I spoke to April with the addressing dept. and she believes that neither address is correct. I let the contractor know that he needs to speak to April to get the correct address. Also the exit discharge light out of the southeast exit did not work nor did the emergency light just inside of this same door. All other items appear ok.
Code Occupancy Approval  2/1/2010 DONE
BLD-Framing/Rough-in10/1/200910/2/200910/2/2009APASS
DetailsJim Sly
Frame and energy OK for core and South wing.
BLD-Energy code compliance9/30/200910/1/200910/1/2009APASS
DetailsJim Sly
Brandon Phone #: ###-####
North wing OK.
BLD-Energy code compliance9/28/20099/28/20099/28/2009PPART
DetailsJim Sly
Brandon Phone #: ###-####
North wing only ....OK
BLD-Framing/Rough-in9/16/20099/16/20099/17/2009PPART
DetailsJim Sly
Brandon Phone #: ###-####
All sleeping rooms OK.
BLD-Conference8/31/20099/1/20099/1/2009ADONE
DetailsJim Sly
Brandon Phone #: ###-####
Sm. Det placement.
BLD-Framing/Rough-in8/20/20098/21/20098/21/2009PNR
DetailsJim Sly
Brandon Phone #: ###-####
NR....Walked thru with Contr and Framer.
BLD-Framing/Rough-in8/14/20098/17/20098/17/2009PPART
DetailsJim Sly
brandon Phone #: ###-####
Roof strapping at South 1/2f OK
BLD-Conference8/13/20098/14/20098/14/2009ADONE
DetailsJim Sly
brandon Phone #: ###-####
Inspection of straps at roof deck.....OK. OK to roof.
BLD-Framing/Rough-in7/16/20097/17/20097/17/2009APART
DetailsJim Sly
kevin Phone #: ###-####
Went through plans with Brandon....Talked about ADA, Rated walls, firestopping, Shear inspections etc.......Looked at shear walls in crawl (pony walls).....located below entrances to hallways.....OK except for overshot nails, and a panel with missed nailing. Wants to cut a hole or two through pony shear walls.....contact Architect or Eng. for advise.
BLD-Footing7/9/20097/9/20097/9/2009PPART
DetailsJim Sly
brandon Phone #: ###-####
Int. foot ....MTI on site.
BLD-Foundation7/6/20097/7/20097/7/2009APART
DetailsJim Sly
Brandon Phone #: ###-####
OK Pend MTI insp, tests and appr.
BLD-Foundation7/2/20097/2/20097/2/2009PPART
DetailsJim Sly
Brandon Phone #: ###-####
S.W area .....OK pending MTI inspection, tests and approvals.
BLD-Foundation6/30/20097/1/20097/1/2009APART
DetailsJim Sly
stem wall-rebar inspection please-Brandon Phone #: ###-####
NW quarter.....Stem wall OK pending MTI special insp, tests and approvals.
BLD-Foundation6/29/20096/30/20096/30/2009APASS
DetailsJim Sly
Brandon Phone #: ###-####
BLD-Foundation6/25/20096/26/20096/26/2009APART
DetailsJim Sly
Brandon Phone #: ###-####
Footing......S 1/2 of bldg OK Pending MTI special insp, tests and approvals.
BLD-Footing6/23/20096/23/20096/23/2009PPART
DetailsJim Sly
brandon Phone #: ###-####
Rebar OK......MTI special insp, tests, and approvals pending.
BLD-Foundation6/22/20096/23/20096/23/2009ACANC
DetailsJim Sly
brandon Phone #: ###-####