Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD09-00965
StatusFinaled
Name SAGE CONSTRUCTION
Site Address 11405 W FAIRVIEW AVE
Project NameEckhardt Company Inc
Customer Number 
ePlanReviewNo
Description
Eckhardt Company - Pawn One - To construct a new 8,510 square foot, two story retail and storage building. This building is constructed of masonry exterior walls and wood framed second floor and roof construction. This building was reviewed as nonseparated uses. This permit also includes related site improvements. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final11/24/200911/24/200911/24/2009PPASS
DetailsMike Jordan
Jarod Phone #: ###-####. Fixtures ok. ok for perm occ.
BLD-Final11/16/200911/16/200911/16/2009PPART
DetailsMike Jordan
Jared Phone #: ###-####. Ok for temp occ. Still need to check fixtures for ada compliance.
BLD-Final11/12/200911/13/200911/16/2009PNR
DetailsMike Jordan
Jarod Phone #: ###-####
FIRE-Final Inspection11/12/200911/12/200911/12/2009PPASS
DetailsTroy Cobbley
Life safety passed.
BLD-Framing/Rough-in10/30/200911/2/200911/2/2009APASS
DetailsTom Arcoraci
jared - ceiling grid Phone #: ###-####
BLD-Framing/Rough-in10/29/200910/30/200910/30/2009APART
DetailsMike Jordan
jared - ceiling grid Phone #: 412-288. Needs to install wires for diffusers.
BLD-Other10/26/200910/27/200910/27/2009ANR
DetailsMike Jordan
ceiling grid insp//Jared Phone #: ###-####. Needs elec. ri insp. first.
BLD-Framing/Rough-in10/8/200910/9/200910/9/2009APART
DetailsMike Jordan
Jared-dry wall inspection please Phone #: ###-####. 5/8 type x rock for vertical exit enclosure.
FIRE-Conference10/7/200910/8/200910/8/2009ADONE
DetailsTroy Cobbley
Went over life safety requirements with contractor. Requiring emergency lights and exit signs in mezzanine.
BLD-Energy code compliance10/8/200910/8/200910/8/2009PPASS
DetailsMike Jordan
BLD-Framing/Rough-in10/6/200910/6/200910/6/2009PPASS
DetailsMike Jordan
Jared Phone #: ###-####. Interior framed walls under mezz, mezz framing and roof framing ok.
BLD-Framing/Rough-in9/29/20099/29/20099/29/2009PPART
DetailsMike Jordan
jared Phone #: ###-####. ok to insulate ceiling. Verified all straps and blocking for roof.
BLD-Framing/Rough-in9/23/20099/24/20099/24/2009APART
DetailsMike Jordan
jared Phone #: ###-####. 4" nailing on blocking for roof diaphragm completed. Also visually inspected nailing on interior shearwall ok.
BLD-Framing/Rough-in9/21/20099/22/20099/22/2009PPART
DetailsMike Jordan
Jared Phone #: ###-####. Nailing for roof diaphragm only. Still needs to nail at 4"oc at blocking.
BLD-Concrete9/11/20099/14/20099/15/2009PDONE
DetailsMike Jordan
masonary wall insp. Phone #: ###-####
BLD-Other9/10/20099/11/20099/11/2009PPART
DetailsMike Jordan
Jared-Masonry inspection please Phone #: ###-####
BLD-Other9/9/20099/10/20099/10/2009APART
DetailsMike Jordan
jared - masonary wall Phone #: ###-####. wip on masonry wall construction, southwall tow, 17ft. 4in. elev. on remaining walls. special inspector was on site. Also reviewed all special insp. reports to date. No deficiencies were noted.
BLD-Other9/4/20099/8/20099/8/2009PDONE
DetailsMike Jordan
Jared- wall Phone #: ###-####. Masonry grout placement already completed when on site. Did have special insp.
BLD-Concrete9/2/20099/3/20099/3/2009PPART
DetailsMike Jordan
Jared Phone #: ###-####. Masonry walls from 4ft. to 8ft. elev. work in progress. Perimeter walls. oft. to 4ft. ele. for interio masonry walls.
BLD-Other8/31/20099/1/20099/1/2009PPART
DetailsMike Jordan
Masonary wall inspection please-Jared Phone #: ###-####. Perimeter wall, 0 to4ft. elev. wip. Will have special inspection.
BLD-Concrete8/27/20098/27/20098/27/2009PPASS
DetailsMike Jordan
slab inspection ready this morning if possible. Phone #: ###-####. Interior footings.
BLD-Footing8/21/20098/24/20098/24/2009APART
DetailsMike Jordan
Jared Phone #: ###-####. wip on interior column pad footings. Will have special insp.
BLD-Foundation8/14/20098/17/20098/17/2009PPASS
DetailsMike Jordan
jared Phone #: ###-####
BLD-Footing8/11/20098/12/20098/12/2009PPART
DetailsMike Jordan
jared Phone #: ###-####. Perimeter footings. Noted special inspection.
BLD-Conference8/4/20098/5/20098/5/2009PDONE
DetailsMike Jordan
Jarod Phone #: ###-####. Went over special inspection requirements with contractor as per special inspection start up sheet on approved plans.