BLD-Final | 5/26/2010 | 5/27/2010 | 5/27/2010 | A | PASS |
Mike Jordan
|
|
|
ok for perm occ.
|
FIRE-Final Inspection | 5/7/2010 | 5/10/2010 | 5/10/2010 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
|
BLD-Final | 5/6/2010 | 5/7/2010 | 5/7/2010 | A | PASS |
Mike Jordan
|
|
|
Rod Phone #: ###-####. ok for temp. occ. Open plumbing permit should be stand alone permit. Needs to complete firecaulking at riser room and repair the doorhardware at the pet salon.
|
FIRE-Final Inspection | 5/5/2010 | 5/6/2010 | 5/6/2010 | A | PART |
Troy Cobbley
|
|
|
A temporary occupancy was given with Scott and Marks approval until the fire alarm permit for the new tamper switch on the anti-freeze loop has been finaled. The work has been scheduled for monday morning at 8:00am.
|
FIRE-Conference | 5/6/2010 | 5/6/2010 | 5/6/2010 | A | DONE |
Troy Cobbley
|
|
|
The property manager, Linda, contacted me about a temporary occupancy for this project until Monday due to SimpleGrinnell not being able to perform their work until that I deferred her to Mark Senteno for a decision.
|
FIRE-Final Inspection | 5/3/2010 | 5/4/2010 | 5/4/2010 | P | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm permit needs to be finaled, verification of factory installed duct smoke detectors and the indicators installed on the main exit doors as discussed. The previous items have been corrected.
|
BLD-Final | 4/29/2010 | 4/30/2010 | 4/30/2010 | A | NR |
Mike Jordan
|
|
|
rod Phone #: ###-####. Also spoke to contractor about shell and core permit.
|
FIRE-Final Inspection | 4/28/2010 | 4/29/2010 | 4/29/2010 | P | FAIL |
Troy Cobbley
|
|
|
The project related fire alarm permit needs to be finaled. Also indicators and stickers need to be installed at the two sets of double main entry doors. The exit discharge light on the northwest exit door did not function.
|
FIRE-Conference | 4/14/2010 | 4/14/2010 | 4/14/2010 | P | DONE |
Troy Cobbley
|
|
|
I spoke with the job superintendant for CNI Construction about the need for an additional fire alarm permit for the connection of the canopy anti-freeze system control valve into the existing fire alarm system located at 104 Milwaukee. This fire alarm work is not covered under the new PetsMart fire alarm system. I let him know that I could not sign off on the building until this additional permit has atleast been submitted for review. He said he would let the associated parties know.
|
BLD-Other | 4/7/2010 | 4/8/2010 | 4/8/2010 | A | PASS |
Mike Jordan
|
|
|
rob - ceiling grid Phone #: ###-####. Reinspected grid ceiling. grid as installed per cisca 0-2 ok. Received letter from CASCO (architect of record) noting that CISCA 0-2 system is approved to be installed in leiu of the CICSCA3-4. Will have letter scanned into project.
|
BLD-Conference | 4/5/2010 | 4/5/2010 | 4/5/2010 | P | DONE |
Mike Jordan
|
|
|
Met on site with contractor to discuss ceiling grid issues. Will discuss with plan reviewer before proceeding further.
|
BLD-Framing/Rough-in | 3/31/2010 | 3/31/2010 | 3/31/2010 | P | FAIL |
Mike Jordan
|
|
|
Ceiling grid inspection please-Rod- Phone #: ###-####. Installed grid not per plan.
|
BLD-Energy code compliance | 3/1/2010 | 3/2/2010 | 3/2/2010 | A | PASS |
Mike Jordan
|
|
|
Rod Phone #: ###-####
|
BLD-Framing/Rough-in | 2/25/2010 | 3/1/2010 | 3/1/2010 | A | PASS |
Mike Jordan
|
|
|
ROD Phone #: ###-####. All interior steel stud framed walls and backing for ada elements, no grid. Also spoke to rod about 1hr. consttruction requirements for fire riser room.
|
BLD-Aging Inspection | 2/24/2010 | 2/24/2010 | 2/24/2010 | | PASS |
Mike Jordan
|
|
|
work is in progress on interior steel stud walls. Visited job site last week. Should be ready for framing inspection by early next week as per contractor.
|