Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD09-01496
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 618 N ALLUMBAUGH ST
Project NameDarigold
Customer Number 
ePlanReviewNo
Description
Darigold Addition - (Footing and Foundation Only) - To Demolish approximately 11,150 square feet of the existing building; a 765 sq. ft. office at the east end of the building and a 10,385 sq. ft. Cooler #3. To install the footing and foundation for a 20,635 sq. ft., one story addition on the east end of the existing building. To install the footing and foundation for a a 990 sq. ft., one story Receiving West and an 825 sq. ft. one story Receiving East additions at the exisitng Receiving Bay. To install a concrete foundation to support three 60,000 gallon silos at the north side of the building. This permit also includes related site improvements. This is a footing and foundation permit only and no occupancy is permitted under this permit. Separate permits will be required to finish this building for occupancy. This building is fully fire sprinkled. This building was reviewed as an unlimited area building. All construction per the approved plans. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/21/20104/23/20104/23/2010APASS
DetailsJim Storey
DOC - Permit Finaled4/23/20104/23/20104/23/2010PPASS
DetailsJim Storey
BLD-Conference4/19/20104/20/20104/21/2010ACANC
DetailsJim Storey
BLD-Aging Inspection2/19/20102/19/20102/19/2010 PASS
DetailsTom Arcoraci
BLD-Footing12/4/200912/4/200912/4/2009ACANC
DetailsJim Storey
time test
BLD-Footing12/4/200912/4/200912/4/2009APASS
DetailsJim Storey
last of interior ft at east addition shell. 1 hr
BLD-Footing11/23/200911/23/200911/23/2009APASS
DetailsJim Storey
interior bearing strip ft rebar ok.
BLD-Foundation11/16/200911/16/200911/16/2009PPASS
DetailsJim Storey
north interior ft and wall rebar ok of shell bld.
FIRE-Conference11/13/200911/13/200911/13/2009ADONE
DetailsForrest France
On site meeting with general and subcontractors regarding facility program guidelines.
BLD-Wall cover11/13/200911/13/200911/13/2009PPASS
DetailsJim Storey
1:00 grout pour
BLD-Conference11/12/200911/13/200911/13/2009APASS
DetailsJim Storey
10:00 am appointment meeting of trades and inspectors to go over facilitity insp. protacall .
BLD-Footing11/12/200911/12/200911/12/2009PPASS
DetailsJim Storey
interior ft appointmet 2:30 north and south sides
BLD-Conference11/10/200911/10/200911/10/2009ACANC
DetailsJim Storey
time test
BLD-Foundation11/10/200911/10/200911/10/2009APASS
DetailsJim Storey
east loading dock wall. rebar ok 1 hr sch. for meetting on fri at 10:00 am with facilitys group and contrators to go over job and protacall.
BLD-Foundation11/5/200911/6/200911/6/2009APASS
DetailsJim Storey
10:30 or 11:00 appointment for dock wall. southeast wall ok 45min.
BLD-Foundation11/5/200911/5/200911/5/2009PCANC
DetailsJim Storey
2:00 appointment.
BLD-Wall cover11/5/200911/5/200911/5/2009APASS
DetailsJim Storey
1 st course cmu tank and exitway from plant northwest corner of plant. ok
BLD-Footing11/4/200911/4/200911/4/2009PPASS
DetailsJim Storey
south side to complet exterior of addition ok/ rebar ok
BLD-Footing11/2/200911/2/200911/2/2009PPASS
DetailsJim Storey
west tank pad ft for rebar insp. 3:30 apointment w/ron ab and weld plats set with rebar double mat ok for cover west tank pad.
BLD-Foundation10/29/200910/29/200910/29/2009PPASS
DetailsJim Storey
3:00 pm appt. east wall insp. center srction of wall east end of addition rebar ok si onsite/ weld plates set.
BLD-Footing10/28/200910/28/200910/28/2009PPASS
DetailsJim Storey
2:30 appointment east ft and rebar of main building ok to place concrete/ compaction ok
BLD-Wall cover10/26/200910/26/200910/26/2009PPASS
DetailsJim Storey
grout placement north dock 5th lift rebar ok
BLD-Footing10/26/200910/26/200910/26/2009PPASS
DetailsJim Storey
wall northside main addition rebar and weld plates inplace ok
BLD-Other10/23/200910/23/200910/23/2009APASS
DetailsJim Storey
north dock 4th lift of cmu wall bond beam rebar ok for 4th lift at north dock area ie over door opening.
BLD-Footing10/23/200910/23/200910/23/2009APASS
DetailsJim Storey
ft insp for main building appt:11:30 301 ft for main addition north side rebar inplace and ok to place concrete/ ft at tank pad for building wall north west area ok to place concrete/
BLD-Other10/21/200910/22/200910/22/2009APASS
DetailsJim Storey
3rd lift north dock around 11:00 am
BLD-Wall cover10/20/200910/21/200910/21/2009APASS
DetailsJim Storey
2nd lift recieving dock north side late insp. rebar ok si to test grout on sch.
BLD-Footing10/20/200910/20/200910/20/2009PPASS
DetailsJim Storey
northwest 60000 tank rebar as perplan si to be on site at placment.
BLD-Wall cover10/20/200910/20/200910/20/2009PPART
DetailsJim Storey
cmu first lift receiving dock north side
BLD-Foundation10/15/200910/15/200910/15/2009PPASS
DetailsJim Storey
rebar ok nw area si pending
BLD-Footing10/14/200910/14/200910/14/2009PPART
DetailsJim Storey
ron Phone #: ###-#### ft for bld. northwest corner of building rebar ok si onsite taking concrete samples.