Permit Information
Permit NumberBLD09-01754
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 618 N ALLUMBAUGH ST
Project NameDarigold
Customer Number 
ePlanReviewNo
Description
Darigold - Production Plant Addition Shell- Darigold Addition - To construct a 20,635 sq. ft., concrete tilt-up, one story shell building addition on the east end of the existing building. To construct a 990 sq. ft., one story shell Receiving West and an 825 sq. ft. one story shell Receiving East additions at the existing Receiving Bay. This is a shell permit only and no occupancy is permitted under this permit. Separate permits will be required to finish this building for occupancy. This building is fully fire sprinkled. This building was reviewed as an unlimited area building. The footing and foundation for this shell building is be installed under building permit BLD09-01496. All construction per the approved plans. JCM (PLAN MODIFICATION - 01-12-10) Minor field modification to drive through opening at the west receiving area, work included removing 2' 8" of CMU to enlarge the opening to 14' 8" and install new lintel per attached engineering dated 12-04-09 this was field evalutated by Jim Storey, (RmH)
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection6/23/20106/23/20107/1/2010 PASS
DetailsJim Storey
BLD-Final6/30/20106/30/20106/30/2010APASS
DetailsJim Storey
l/c
DOC - Permit Finaled6/30/20106/30/20106/30/2010PPASS
DetailsJim Storey
FIRE-Final Inspection4/19/20104/20/20104/26/2010PPASS
DetailsForrest France
Shell permit fire life safety passed.
BLD-Final4/21/20104/23/20104/23/2010APART
DetailsJim Storey
si report archived ok pending zoning final.
BLD-Conference4/19/20104/20/20104/21/2010ACANC
DetailsJim Storey
BLD-Concrete3/15/20103/15/20103/15/2010PPASS
DetailsJim Storey
slab on grade. north side truck pad/ exit door landing. ok rebar ok
BLD-Concrete3/2/20103/2/20103/2/2010PPASS
DetailsJim Storey
BLD-Footing2/10/20102/10/20102/10/2010PPASS
DetailsJim Storey
3:00 appt. for truck pand and retaining wall.
BLD-Wall cover1/28/20101/28/20101/28/2010APASS
DetailsJim Storey
BLD-Concrete1/14/20101/14/20101/14/2010PPASS
DetailsJim Storey
floor rebar insp. culture rm rebar ok on floor.
BLD-Other1/12/20101/13/20101/13/2010APASS
DetailsJim Storey
se 2nd lift ok
BLD-Other1/12/20101/12/20101/12/2010APASS
DetailsJim Storey
southeast corner 1 st lift rebar ok si onsite for grout sampling. top out of northeast door infil ok rebar ok si on site to test grout.
BLD-Other1/11/20101/11/20101/11/2010APART
DetailsJim Storey
3dr lift grout header of drygoods door cmu. rebar ok si on site for samplling. need base conection in cultural rn missed for welding detail/ still pending engineered panel conection in production area door to culture hallway.
BLD-Other1/8/20101/8/20101/8/2010APASS
DetailsJim Storey
2nd lift dry storage area door infil rebar ok si on site.
BLD-Other1/7/20101/7/20101/7/2010APASS
DetailsJim Storey
1 st lift of cmu at overhead doorway ne bay rebar ok to cover. walked tilt slab walls to review weld conections and shrink grouting in progress. si reports are continuing and in complance. duscused nw interior cut out pannel for door and window as to retro weld plate conections that were missed at precast plant.
BLD-Concrete12/2/200912/2/200912/2/2009APASS
DetailsJim Storey
north third of slab si on site/ rebar ok
BLD-Wall cover11/12/200911/12/200911/12/2009PPASS
DetailsJim Storey
grout pour for third lift north west area of building 12:30 appointment.
BLD-Conference11/9/200911/9/200911/9/2009PPASS
DetailsJim Storey
time tracking test
BLD-Wall cover11/9/200911/9/200911/9/2009PPASS
DetailsJim Storey
2nd lift of cmu north west area 3:30 appointment. 35 min