Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD09-01808
StatusFinaled
Name RB SCHWEIGERT
Site Address 7250 W POPLAR ST
Project NameCHATEAU DE'BOISE
Customer Number 
ePlanReviewNo
Description
(FIRE REPAIR - CHATEAU DE'BOISE RETIREMENT RESIDENCE) To demo and repair Fire damage areas on the South facing wing of an existing retirement apartment building to the condition prior to the fire including: Rooms 118, 119, 120, the vertical exit stair enclosure, and the common corridor on the first floor; Rooms 215, 216, 217, the vertical exit stair enclosure, and the common corridor on the Second floor; Rooms 313 where the Fire started, 314, the vertical exit stair enclosure, and the common corridor on the Third floor. Work to include: demo all fire damaged areas; demo all water damaged areas; replace all sheetrock, carpeting, particle board, flooring in bathrooms, and flooring in hallways to original; Replace (2) decks; demo room #313 deck completely and replace to original; demo room #216 2x6 deck top and replace to original; Remove water damaged insulation throughout, dry affected area's and remediate any mold issues; remove and replace charred wood in deck areas and replace to original; remove hallway ceiling tiles and replace with new tiles; Install new insulation, install new sheetrock at ceilings and walls with same materials as original; install new subfloor on floors; Install new windows and doors that were damaged as original; repair water damaged bathrooms back to original; repair exterior to original condition; remediate any/all mold and miscellaneous finish work. All construction shall be per chapter 39 of the 2006 IBC, the approved plans, engineering, attached plan review report, and the structural inspector's approval. NOTE: No structural damage or repair was declared as part of this permit. Separate permits are required for the installation of electrical, plumbing and mechanical. 2006 IBC, sections 3403. This building is fully Fire sprinklered. No work is proposed to the existing Fire Sprinkler system. All penetrations and/or openings of any Fire-resistant-rated assemblies shall comply with the 2006 IBC. (See plan review report) **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection1/25/20101/27/20101/27/2010APASS
DetailsTroy Cobbley
Life safety passed
BLD-Final1/25/20101/27/20101/27/2010APEND
DetailsTom Arcoraci
jerry Phone #: ###-####
DOC - Permit Finaled1/27/20101/27/20101/27/2010PPASS
DetailsTom Arcoraci
FIRE-Final Inspection1/22/20101/25/20101/25/2010ACANC
DetailsTroy Cobbley
Cancelled by Jerry and rescheduled for wednesday.
BLD-Final1/22/20101/25/20101/25/2010ANR
DetailsTom Arcoraci
Randy Phone #: ###-####
BLD-Final1/19/20101/20/20101/20/2010PNR
DetailsTom Arcoraci
randy Phone #: ###-####
FIRE-Final Inspection1/19/20101/20/20101/20/2010AFAIL
DetailsTroy Cobbley
This project is not ready for inspection. Will be rescheduled for monday.
BLD-Final1/6/20101/7/20101/7/2010PNR
DetailsTom Arcoraci
Randy Phone #: ###-####
FIRE-Final Inspection1/6/20101/7/20101/7/2010ACANC
DetailsTroy Cobbley
Per the owner this project is not ready for a final inspection yet.
BLD-Conference1/5/20101/5/20101/5/2010APASS
DetailsTom Arcoraci
conf on final
FIRE-Final Inspection12/17/200912/17/200912/17/2009PCANC
DetailsTroy Cobbley
Randy Phone #: ###-#### Per Randy one of the residence rooms is not complete so the inspection is to be rescheduled.
BLD-Framing/Rough-in11/13/200911/16/200911/16/2009APASS
DetailsTom Arcoraci
Randy Phone #: ###-####
FIRE-Final Inspection11/3/200911/3/200911/3/2009PFAIL
DetailsTroy Cobbley
Todays inspection was actually a conference about cover. Sheet rock is ok to be installed by Fire pending the other inspectors approvals.
BLD-Other10/30/200911/2/200911/2/2009APASS
DetailsTom Arcoraci
randy - first thing in the morning if possible Phone #: ###-#### wip ok