Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD09-01863
StatusFinaled
Name FLYNNER HOMES
Site Address 4859 W WILLOW LN
Project Name 
Customer Number 
ePlanReviewNo
Description
To construct a new 1910s.f. 2-story single family dwelling with a 576s.f. detached 2-car garage. The dwelling is f to have 1337s.f. on the main level and 573s.f. on the upper level and a 576s.f. 2-car gagare that is attached to the dwelling by a breezeway. R-1C setbacks approved per Section 11-04-04.01A. per planning director by Todd Tucker. All per the approved plans as marked REScheck; letters from the Engineer of Rcord (Scott Soule) validating the non-typical use of engineered floor joists ( LP SOLIDSTART I-JOISTS WITH SAWN LUMBER FLANGES); (SEE ESR-1305) in a vertical manor.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/18/20105/20/20105/25/2010PPASS
DetailsTony Young
jonathan Phone #: ###-####
DOC - Permit Finaled5/25/20105/25/20105/25/2010PPASS
DetailsTony Young
c of o issues
BLD-Final5/17/20105/18/20105/18/2010PNR
DetailsTony Young
jonathan Phone #: ###-####,, need trades
BLD-Final5/14/20105/17/20105/17/2010APART
DetailsTony Young
jonathan Phone #: ###-####,, conf only,, need trades 1st
BLD-Conference3/1/20103/2/20103/4/2010APEND
DetailsTony Young
Johnathon Phone #: ###-####, meet energy consultant for blower test,, 9:30am,,
BLD-Conference2/26/20103/1/20103/1/2010ANR
DetailsTony Young
Johnathon Phone #: ###-####, meet energy consultant for blower test,, 9:30am
BLD-Energy code compliance2/25/20102/25/20103/1/2010PPASS
DetailsTony Young
Johnathon Phone #: ###-####
BLD-Conference2/25/20102/25/20102/26/2010PPASS
DetailsTony Young
Johnathon Phone #: ###-####,, other ?s
BLD-Conference2/25/20102/25/20102/26/2010APASS
DetailsTony Young
Johnathon Phone #: ###-####,, Feb 25, 2010
met with contractor Jonathon and energy consultant John Coldiron to look at job, video some,,, invited others from our department but too short of notice for them,, this is the 1st with in our State of this type of house,, net zero and also a St. Judes raffle house.. also on site was the insulation person
BLD-Energy code compliance2/24/20102/24/20102/25/2010PNR
DetailsTony Young
Johnathon Phone #: ###-####
BLD-Energy code compliance2/23/20102/24/20102/24/2010ANR
DetailsTony Young
Johnathon Phone #: ###-####
BLD-Energy code compliance2/23/20102/23/20102/23/2010PNR
DetailsTony Young
Johnathon Phone #: ###-####
BLD-Framing/Rough-in2/11/20102/12/20102/12/2010APASS
DetailsTony Young
Johnathan Phone #: ###-####
BLD-Conference2/2/20102/3/20102/3/2010ADONE
DetailsTony Young
jonathan Phone #: ###-#### Met on site with Tony Young and framing contractor to inspect prior to the placement of exterior blown in insulation. pep 2-2-2010
BLD-Footing1/12/20101/13/20101/13/2010APASS
DetailsMike Jordan
Jonathan Phone #: ###-####. Interior slab on grade and interior footings (thickend slab areas ok.) All rigid foam insulation in place.
BLD-Other11/30/200911/30/200911/30/2009PPART
DetailsJim Storey
Sabastian Phone #: ###-####- stem wall
BLD-Footing11/25/200911/25/200911/25/2009PPEND
DetailsTony Young
SABASTIAN Phone #: ###-####
BLD-Conference11/25/200911/25/200911/25/2009PPASS
DetailsTony Young
SABASTIAN Phone #: ###-####
SOIL ENGINEER REINSPECTED AND PASSED SOIL AFTER NOON
BLD-Footing11/23/200911/24/200911/24/2009ANR
DetailsTony Young
Sabatian Phone #: ###-####
BLD-Conference11/23/200911/24/200911/24/2009ANR
DetailsTony Young
Jonathan Phone #: ###-####
check on soil report
BLD-Footing11/23/200911/23/200911/23/2009PNR
DetailsTony Young
Jonathan Phone #: ###-####
on site conf,, need soil compaction test