Permit Information
Permit NumberBLD09-02069
StatusFinaled
Name KREIZENBECK CONSTRUCTORS
Site Address 1055 N CURTIS RD
Project NameST ALPHONSUS
Customer Number 
ePlanReviewNo
Description
(ST ALPHONSUS - CLINICAL LABORATORY RENOVATION) Renovation of existing Clinical Laboratory Department to accommodate the installation of an automatic testing line and relocation of the Histology and Cytology Departments. Work will include selective interior demolition in five different phases in conjunction with five phases of tenant remodel to allow Lab functions to continue. In order to maintain operation requirements of the Lab some existing rooms in the immediate Lab Clinic area will receive minimum modifications to facility maintaining use of equipment and work stations for lab activities while their portion of the clinic is demolished and remodeled. At the conclusion of the remodel all activities and support functions will be within the existing Clinical Lab and expanded Histology and Cytology Departments in the SE corner of the 1st floor of SARMC. Work includes construction of new non-bearing walls to create work / testing areas, relocation of existing walk-in cooler; relocation / construction of existing 2-hour fire barrier wall on west and north sides of new Cytology Dept.; structural modification for new door opening in concrete wall between Histology 101 & Cytology 103 (see 8-1/2" xx 11" structural design and details); and upgrades of electrical, mechanical, plumbing, sprinkler and alarm systems to meet tenant needs and provide / maintain code compliance. drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final2/1/20112/1/20112/1/2011PPASS
DetailsTom Arcoraci
cecil Phone #: ###-####
DOC - Permit Finaled2/1/20112/1/20112/1/2011PPASS
DetailsTom Arcoraci
FIRE-Final Inspection2/1/20112/1/20112/1/2011PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection12/16/201012/16/201012/16/2010PFAIL
DetailsTroy Cobbley
Life safety will be ok to pass when the project related fire alarm permit has been addressed.
BLD-Framing/Rough-in11/15/201011/15/201011/15/2010PPASS
DetailsTom Arcoraci
cecil Phone #: ###-####
BLD-Conference9/21/20109/22/20109/22/2010APASS
DetailsTom Arcoraci
BLD-Aging Inspection9/21/20109/21/20109/21/2010 PASS
DetailsTom Arcoraci
BLD-Aging Inspection7/19/20107/19/20107/20/2010 PART
DetailsTom Arcoraci
work in progress ok
BLD-Final5/19/20105/19/20105/19/2010PPART
DetailsTom Arcoraci
Cecil Phone #: ###-#### phase 2 ok
FIRE-Final Inspection5/18/20105/18/20105/18/2010PPART
DetailsTroy Cobbley
The life safety for phase two passed.
BLD-Final4/8/20104/9/20104/9/2010APART
DetailsTom Arcoraci
cecil Phone #: ###-####
FIRE-Final Inspection4/7/20104/8/20104/8/2010APART
DetailsTroy Cobbley
The phase 1 fire life safety is passed.