BLD-Final | 9/16/2010 | 9/17/2010 | 9/17/2010 | A | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-#### final ok
|
FIRE-Final Inspection | 9/14/2010 | 9/15/2010 | 9/15/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection completed acceptable.
|
FIRE-Conference | 9/2/2010 | 9/2/2010 | 9/2/2010 | P | DONE |
Forrest France
|
|
|
Discussion with contractor regarding exit sign placement.
|
BLD-Framing/Rough-in | 8/26/2010 | 8/26/2010 | 8/26/2010 | P | PASS |
Jim Storey
|
|
|
Ceiling grid exterior please-Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 8/20/2010 | 8/20/2010 | 8/20/2010 | P | PART |
Jim Storey
|
|
|
Ceiling grid-Tom Phone #: ###-#### need ele c/n aproved/ need perimiter wires with in 8 inched.
|
BLD-Framing/Rough-in | 8/19/2010 | 8/20/2010 | 8/20/2010 | A | NR |
Jim Storey
|
|
|
Ceiling grid-Tom Phone #: ###-#### need ele insp.
|
BLD-Energy code compliance | 7/1/2010 | 7/6/2010 | 7/6/2010 | A | PART |
Jim Storey
|
|
|
Tom Phone #: ###-#### need to check soffit drops at ceilling insp.
|
BLD-Framing/Rough-in | 6/30/2010 | 7/1/2010 | 7/1/2010 | P | PASS |
Jim Storey
|
|
|
Tom Phone #: ###-####
|
BLD-Framing/Rough-in | 6/14/2010 | 6/15/2010 | 6/15/2010 | A | PASS |
Jim Storey
|
|
|
Wall nailing on the exterior shear inspection please ###-#### Tom ok for cover.
|
BLD-Framing/Rough-in | 6/8/2010 | 6/8/2010 | 6/8/2010 | A | PART |
Jim Storey
|
|
|
reviewed roof nailling with struc. engineer ok to instal roof insulation.
|
BLD-Footing | 4/12/2010 | 4/13/2010 | 4/13/2010 | P | PART |
Jim Storey
|
|
|
Column footings--pouring at 2 Phone #: ###-#### si sch / rebar ok
|
BLD-Foundation | 4/8/2010 | 4/9/2010 | 4/9/2010 | A | PART |
Jim Storey
|
|
|
Tom Phone #: ###-#### walls ok placed with si oversite pending report/ interior pads ok pending si reports
|
BLD-Footing | 4/1/2010 | 4/2/2010 | 4/2/2010 | P | PART |
Jim Storey
|
|
|
tom Phone #: ###-#### rebar ok si pending report ok
|