BLD-Final | 4/15/2010 | 4/16/2010 | 4/16/2010 | A | PASS |
Jim Storey
|
|
|
John Phone #: ###-#### final ok
|
FIRE-Final Inspection | 4/15/2010 | 4/15/2010 | 4/15/2010 | P | PASS |
Forrest France
|
|
|
Fire life safety inspection passed, c/n items verified for completion.
|
FIRE-Final Inspection | 4/12/2010 | 4/12/2010 | 4/12/2010 | P | PART |
Forrest France
|
|
|
Final pending finishes, posting of occupant load sign per review note #5 as discussed. Remiander of fire life safety issues are complete.
|
FIRE-Conference | 4/9/2010 | 4/9/2010 | 4/9/2010 | A | DONE |
Forrest France
|
|
|
On site conference with contractor regarding fire code review notes and items needed for final fire life safety approvals. Discussed project completion date.
|
BLD-Final | 4/5/2010 | 4/6/2010 | 4/6/2010 | A | NR |
Jim Storey
|
|
|
john - suspended ceiling Phone #: ###-####
|
BLD-Other | 4/6/2010 | 4/6/2010 | 4/6/2010 | A | PASS |
Jim Storey
|
|
|
john - suspended ceiling Phone #: ###-#### ok to cover
|
BLD-Framing/Rough-in | 3/30/2010 | 3/31/2010 | 3/31/2010 | A | PASS |
Jim Storey
|
|
|
john Phone #: ###-####
|
FIRE-Final Inspection | 3/30/2010 | 3/30/2010 | 3/30/2010 | P | NR |
Forrest France
|
|
|
john Phone #: ###-#### Intended for structural inspection at the new rated wall.
|
BLD-Framing/Rough-in | 3/15/2010 | 3/16/2010 | 3/16/2010 | A | PASS |
Jim Storey
|
|
|
Fire stop inspection please-John Phone #: ###-#### fire stopping ok first layer interior ok to finsh.
|
BLD-Framing/Rough-in | 3/12/2010 | 3/12/2010 | 3/12/2010 | P | PART |
Jim Storey
|
|
|
john Phone #: ###-#### need listing for pipe penatrations.
|
BLD-Framing/Rough-in | 3/5/2010 | 3/8/2010 | 3/8/2010 | P | PART |
Jim Storey
|
|
|
John Phone #: ###-#### ok to cover inside of exterior walls/ two layers of 2 hr wall ok to finsh and frame for next layers. ok to one side partitions.
|