BLD-Final | 11/1/2010 | 11/3/2010 | 11/3/2010 | A | PASS |
Jim Sly
|
|
|
Jack please call 1 hr before going out Phone #: ###-#### OK for Perm Occ. C/C issued.
|
DOC - Permit Finaled | 11/3/2010 | 11/3/2010 | 11/3/2010 | P | PASS |
Jim Sly
|
|
|
|
BLD-Framing/Rough-in | 7/27/2010 | 7/27/2010 | 7/27/2010 | P | PART |
Jim Sly
|
|
|
trent Phone #: ###-#### Deans office OK
|
BLD-Framing/Rough-in | 7/15/2010 | 7/16/2010 | 7/16/2010 | A | PART |
Mike Jordan
|
|
|
trent Phone #: ###-####. HArdlid for lobby, grid at phase 3, Needs to extend to north bulkhead and remove old UBC portion so that entire grid is one single system.
|
BLD-Other | 6/29/2010 | 6/29/2010 | 6/29/2010 | P | PART |
Jim Sly
|
|
|
trent - ceiling grid Phone #: ###-####
|
BLD-Framing/Rough-in | 6/17/2010 | 6/18/2010 | 6/18/2010 | P | PART |
Jim Sly
|
|
|
trent Phone #: ###-#### North wall.....copy room OK
|
BLD-Framing/Rough-in | 6/14/2010 | 6/14/2010 | 6/14/2010 | P | PART |
Jim Sly
|
|
|
trent Phone #: ###-#### Theory rooms 120 ans 121.
|
BLD-Framing/Rough-in | 6/4/2010 | 6/7/2010 | 6/7/2010 | A | PASS |
Jim Sly
|
|
|
Ceiling grid inspection-Trent Green Phone #: ###-####
|
BLD-Framing/Rough-in | 5/26/2010 | 5/27/2010 | 5/27/2010 | A | PASS |
Jim Sly
|
|
|
trent Phone #: ###-####
|
BLD-Final | 5/20/2010 | 5/21/2010 | 5/21/2010 | P | CANC |
Jim Sly
|
|
|
Trent Green Phone #: ###-#### Canc by Contr....
|
FIRE-Final Inspection | 5/20/2010 | 5/21/2010 | 5/21/2010 | A | CANC |
Troy Cobbley
|
|
|
Trent - life safety Phone #: ###-####//cancelled per Trent 5/20/10 1:08pm /LEG
|
BLD-Final | 5/20/2010 | 5/20/2010 | 5/20/2010 | P | NR |
Jim Sly
|
|
|
Trent Green Phone #: ###-#### Need Fire OK for phased temp. occ.
|
FIRE-Conference | 5/17/2010 | 5/17/2010 | 5/18/2010 | P | DONE |
Troy Cobbley
|
|
|
I found that the existing fire alarm system had devices that had been removed by ADT for construction. No plans had been approved/issued for this work. I spoke to the general contractor and let him know that approved plans are required and that there would be no sign offs for final or for any phasing of the project until plans had been submitted, issued and the work completed.
|
BLD-Other | 5/13/2010 | 5/17/2010 | 5/17/2010 | A | PASS |
Jim Sly
|
|
|
trent - ceiling grid Phone #: ###-####
|
BLD-Framing/Rough-in | 5/5/2010 | 5/6/2010 | 5/6/2010 | P | PART |
Jim Sly
|
|
|
Trent please call 30 min before going out Phone #: ###-#### phase 1 ok
|