Permit Information
Permit NumberBLD10-00109
StatusFinaled
Name DATUM CONSTRUCTION MANAGEMENT INC
Site Address 5100 W OVERLAND RD
Project NameHILLCREST SHOPPING CENTER
Customer Number 
ePlanReviewNo
Description
(HILLCREST SHOPPING CENTER - NEW COVERED WALKWAY AND FACADE) (6-28-10 PLAN MODIFICATION TO REPLACE PREVIOUSLY APPROVED STOREFRONT WINDOW AND DOOR SYSTEMS WITH OPAQUE WALLS AND TO REALIGN VEHICULAR ACCESS TO PHILLIPPI STREET.) This building is fully fire sprinklered for unlimited area. To construct about 3,200 square feet of covered walkway with about 240 lineal feet of new façade where a demolished portion of the building (about 102,000 square feet) formerly connected to the remainder of the building on the South side. The demolished portion was formerly occupied by "Fred Meyer" and by "Honk's 99 Cents". The demolition was done under a separate permit. Work is to include concrete footings, concrete foundations, shear walls, concrete sidewalk, concrete curb ramps, steel columns, steel beams, steel roof joists, steel roof deck, brick veneer, 3-coat exterior stucco system, storefront glazing, exterior wall, metal roofing, single ply membrane roofing, and a suspended acoustical ceiling. Curb, gutter, sidewalk, asphalt paving, and a retaining wall will be constructed along Phillippi Street in conjunction with this permit. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final6/3/20116/6/20116/3/2011APASS
DetailsTom Arcoraci
shelby Phone #: ###-####
DOC - Permit Finaled6/3/20116/3/20116/3/2011PPASS
DetailsTom Arcoraci
BLD-Final6/3/20116/3/20116/3/2011PPASS
DetailsTom Arcoraci
shelby Phone #: ###-####
FIRE-Final Inspection5/20/20115/23/20115/23/2011APASS
DetailsTroy Cobbley
Life safety passed
BLD-Conference5/19/20115/20/20115/20/2011APASS
DetailsTom Arcoraci
shelby Phone #: ###-####
BLD-Aging Inspection3/30/20113/30/20113/30/2011 PASS
DetailsTom Arcoraci
BLD-Conference1/27/20111/28/20111/28/2011APASS
DetailsTom Arcoraci
Blair Phone #: ###-####
BLD-Framing/Rough-in12/10/201012/10/201012/10/2010PPASS
DetailsTom Arcoraci
Shear nail inspection-Blair Phone #: ###-####
BLD-Framing/Rough-in11/17/201011/18/201011/18/2010APASS
DetailsTom Arcoraci
Blair Phone #: ###-####
BLD-Conference10/6/201010/6/201010/6/2010PPASS
DetailsTom Arcoraci
blair Phone #: ###-#### needs letter from eng for ok of nail use on shear wall
BLD-Aging Inspection8/23/20108/23/20108/23/2010 PART
DetailsTom Arcoraci
BLD-Conference6/22/20106/23/20106/23/2010PPASS
DetailsTom Arcoraci
BLD-Conference6/22/20106/23/20106/22/2010ACANC
DetailsTom Arcoraci
BLD-Foundation6/22/20106/22/20106/22/2010PPASS
DetailsJim Storey
Barry ###-#### c/n made ok
BLD-Conference6/21/20106/22/20106/22/2010PCANC
DetailsTom Arcoraci
cw
BLD-Foundation6/21/20106/22/20106/22/2010AFAIL
DetailsJim Storey
Barry ###-#### hoop bar inside verts/ clearance to forms to close.
BLD-Footing6/21/20106/22/20106/22/2010APASS
DetailsJim Storey
Barry @ ###-####
BLD-Footing6/16/20106/16/20106/16/2010PPASS
DetailsTom Arcoraci
Roger Phone #: ###-####