FIRE-Final Inspection | 7/21/2010 | 7/21/2010 | 7/21/2010 | P | PASS |
Forrest France
|
|
|
Correction items verified for completion, fire life safety passed.
|
BLD-Final | 7/19/2010 | 7/21/2010 | 7/21/2010 | P | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
FIRE-Conference | 7/1/2010 | 7/1/2010 | 7/1/2010 | A | DONE |
Forrest France
|
|
|
Regarding project related fire alarm permit work.
|
FIRE-Final Inspection | 6/3/2010 | 6/4/2010 | 6/3/2010 | A | FAIL |
Forrest France
|
|
|
Inspection completed early, 6/3/10- see activity notes for details.
|
FIRE-Final Inspection | 6/3/2010 | 6/3/2010 | 6/3/2010 | P | FAIL |
Forrest France
|
|
|
A fire alarm permit will be necessary for modifications made to the existing system due to remodel work within the scope of BLD permit. Also noted one exit sign/EM light at the south exit to be repaired.
|
BLD-Framing/Rough-in | 5/3/2010 | 5/4/2010 | 5/4/2010 | A | PASS |
Dave Hannah
|
|
|
Perry Phone #: ###-####
|
BLD-Foundation | 4/14/2010 | 4/14/2010 | 4/14/2010 | P | PASS |
Dave Hannah
|
|
|
john Phone #: ###-#### ok to pour wall for chair lift
|
BLD-Concrete | 4/9/2010 | 4/12/2010 | 4/12/2010 | A | PART |
Dave Hannah
|
|
|
Dave Mortenson Phone #: ###-####-after 10 if possible please ok to pour ftg for chair lift
|
BLD-Framing/Rough-in | 3/26/2010 | 3/29/2010 | 3/29/2010 | A | PASS |
Dave Hannah
|
|
|
Perry Phone #: ###-####
|
BLD-Framing/Rough-in | 3/16/2010 | 3/17/2010 | 3/17/2010 | A | PART |
Dave Hannah
|
|
|
perry Phone #: ###-#### ok to cover demis wall
|
BLD-Framing/Rough-in | 3/10/2010 | 3/10/2010 | 3/10/2010 | P | PART |
Jim Sly
|
|
|
perry Phone #: ###-#### OK to cover walls in room 102
|