BLD-Final | 6/14/2010 | 6/14/2010 | 6/14/2010 | P | PASS |
Mike Jordan
|
|
|
please call 1/2 hr before. Thanks Jim Inspection requested from web by: James Larkin Phone #: ###-####
|
DOC - Permit Finaled | 6/14/2010 | 6/14/2010 | 6/14/2010 | P | PASS |
Mike Jordan
|
|
|
Certificate of occupancy was issued.
|
BLD-Final | 6/10/2010 | 6/11/2010 | 6/11/2010 | P | NR |
Mike Jordan
|
|
|
please call 1/2 hr before.thanks Jim Inspection requested from web by: James Larkin Phone #: ###-####. Needs zoning.
|
BLD-Energy code compliance | 5/7/2010 | 5/7/2010 | 5/7/2010 | P | PASS |
Mike Jordan
|
|
|
please call 1/2 hour before. Thanks! Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 5/6/2010 | 5/6/2010 | 5/6/2010 | P | PASS |
Mike Jordan
|
|
|
jim Phone #: ###-####. ok to insulate.
|
BLD-Framing/Rough-in | 4/21/2010 | 4/21/2010 | 4/21/2010 | P | PASS |
Mike Jordan
|
|
|
Firewall construction "Overbuilds" Inspection requested from web by: James Larkin Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. fire wall at ceiling to underside of roof deck and at overbuilds.
|
BLD-Framing/Rough-in | 4/20/2010 | 4/20/2010 | 4/20/2010 | P | PASS |
Mike Jordan
|
|
|
Firewall construction-Jim Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. firewall at overbuild.
|
BLD-Framing/Rough-in | 4/19/2010 | 4/19/2010 | 4/19/2010 | P | PASS |
Mike Jordan
|
|
|
JIM\\FIRE WALL CONSTRUSTION Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. firewalls, 2nd. floor both sides.
|
BLD-Framing/Rough-in | 4/15/2010 | 4/15/2010 | 4/15/2010 | P | NR |
Mike Jordan
|
|
|
firewall construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/14/2010 | 4/14/2010 | 4/14/2010 | P | NR |
Mike Jordan
|
|
|
Jim-Fire wall inspection please Phone #: ###-####
|
BLD-Framing/Rough-in | 4/13/2010 | 4/13/2010 | 4/13/2010 | P | NR |
Mike Jordan
|
|
|
firewall Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/8/2010 | 4/8/2010 | 4/8/2010 | P | PASS |
Mike Jordan
|
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. firewall, remaining side, 1st. floor.
|
BLD-Framing/Rough-in | 4/7/2010 | 4/7/2010 | 4/7/2010 | P | PASS |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####. BAse and face layers of 5/8 type x rock for 2hr. fire wall, one side only, 1st. floor.
|
BLD-Framing/Rough-in | 4/6/2010 | 4/6/2010 | 4/6/2010 | P | NR |
Mike Jordan
|
|
|
firewall Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/2/2010 | 4/5/2010 | 4/5/2010 | A | NR |
Mike Jordan
|
|
|
Firewall Construction Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Footing | 3/19/2010 | 3/19/2010 | 3/19/2010 | P | PASS |
Mike Jordan
|
|
|
Jim Phone #: ###-####. Interior footings
|
BLD-Energy code compliance | 3/16/2010 | 3/16/2010 | 3/16/2010 | A | PASS |
Mike Jordan
|
|
|
Foundation Insulation Inspection requested from web by: James Larkin Phone #: ###-####. Rigid insulation at interior side of stemwall.
|
BLD-Foundation | 3/12/2010 | 3/12/2010 | 3/12/2010 | P | PASS |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####
|
BLD-Footing | 3/12/2010 | 3/12/2010 | 3/12/2010 | P | PASS |
Mike Jordan
|
|
|
Inspection requested from web by: James Larkin Phone #: ###-####
|