BLD-Final | 9/14/2010 | 9/16/2010 | 9/16/2010 | A | PASS |
Tony Young
|
|
|
joe Phone #: ###-#### - please call 1/2 hr prior
|
DOC - Permit Finaled | 9/16/2010 | 9/16/2010 | 9/16/2010 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Grading Inspection | 9/16/2010 | 9/16/2010 | 9/16/2010 | P | DONE |
Terry Records
|
|
|
Final grading and drainage aproved.
|
BLD-Energy code compliance | 6/4/2010 | 6/8/2010 | 6/8/2010 | A | PASS |
Tony Young
|
|
|
joe - please call 1/2 hr prior so he can meet you there Phone #: ###-####
|
BLD-Framing/Rough-in | 6/2/2010 | 6/4/2010 | 6/4/2010 | A | PART |
Tony Young
|
|
|
joe - please call 1/2 hr prior so he can meet you there Phone #: ###-####,, will need a letter of compliance from structural engineer at final,,, need seal in all holes,, fire blocks,, straps on beams/plates etc.,, fill all nail holes in all hangers,, interior stairs will be done at final,, ok to insulate
|
BLD-Framing/Rough-in | 5/11/2010 | 5/12/2010 | 5/12/2010 | A | PART |
Tony Young
|
|
|
Joe Harris-Shear Nail inspection-ask for Odie if questions Phone #: ###-####,, exterior shear ok
|
BLD-Framing/Rough-in | 5/11/2010 | 5/11/2010 | 5/11/2010 | P | FAIL |
Tony Young
|
|
|
Joe Harris-Shear Nail inspection-ask for Odie if questions Phone #: ###-####,, need to nail per plan
|
BLD-Foundation | 4/6/2010 | 4/6/2010 | 4/6/2010 | A | PART |
Tony Young
|
|
|
ian Phone #: ###-####,, ok to pour when ready,, conference on sill bolts,, double plates, ,, some bolts are 8" on center
|
BLD-Foundation | 4/5/2010 | 4/5/2010 | 4/6/2010 | P | PART |
Tony Young
|
|
|
ian Phone #: ###-####,, work in progress
|
BLD-Foundation | 4/2/2010 | 4/5/2010 | 4/5/2010 | A | NR |
Tony Young
|
|
|
ian Phone #: ###-####,, too much ice on scaffolding to see,,
|
BLD-Footing | 3/23/2010 | 3/24/2010 | 3/24/2010 | A | PASS |
Tony Young
|
|
|
ian Phone #: ###-####
|
BLD-Footing | 3/22/2010 | 3/23/2010 | 3/23/2010 | P | PART |
Tony Young
|
|
|
ian Phone #: ###-####
|