BLD-Final | 4/19/2011 | 4/19/2011 | 4/19/2011 | P | PASS |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 4/18/2011 | 4/19/2011 | 4/19/2011 | A | PASS |
Forrest France
|
|
|
Corrections and adjustments completed. Fire life safety finaled.
|
BLD-Final | 4/14/2011 | 4/15/2011 | 4/19/2011 | A | DEFR |
Jim Storey
|
|
|
|
FIRE-Final Inspection | 4/15/2011 | 4/15/2011 | 4/18/2011 | A | PART |
Forrest France
|
|
|
Reinspection scheduled 4/19 AM.
|
FIRE-Final Inspection | 4/13/2011 | 4/14/2011 | 4/14/2011 | A | FAIL |
Forrest France
|
|
|
Construction and use of exterior canopies must comply with the requirements of NFPA 13 2007 8.15.7 (8.15.7.2 & 8.15.7.5). Remainder of final inspection issues completed acceptable. Rooftop EM light repaired while on site.
|
BLD-Final | 4/13/2011 | 4/14/2011 | 4/14/2011 | P | CANC |
Jim Storey
|
|
|
todd Phone #: ###-####
|
BLD-Framing/Rough-in | 2/15/2011 | 2/15/2011 | 2/15/2011 | A | PASS |
Jim Storey
|
|
|
|
BLD-Framing/Rough-in | 2/11/2011 | 2/14/2011 | 2/14/2011 | A | PART |
Jim Storey
|
|
|
Bob or Sadie-Steel stud inspection Phone #: ###-#### clip welding nr atchment to studs pending.
|
BLD-Final | 12/29/2010 | 12/30/2010 | 12/30/2010 | A | PART |
Jim Storey
|
|
|
Todd Phone #: ###-#### ok for temp first floor only.
|
FIRE-Final Inspection | 12/29/2010 | 12/30/2010 | 12/30/2010 | A | PART |
Forrest France
|
|
|
Temporary Occupancy approved per conditions. See permit activity notes dated 12/7. Some aspects incomplete and not approved for occupancy at this time including rooftop dining, second level VIP room, exterior stairway. No storage allowed in attic spaces.
|
BLD-Conference | 12/27/2010 | 12/27/2010 | 12/27/2010 | P | PASS |
Jim Storey
|
|
|
recieved stair engineering for planreview.
|
BLD-Foundation | 12/20/2010 | 12/20/2010 | 12/20/2010 | P | PASS |
Jim Storey
|
|
|
Jay Phone #: ###-####
|
BLD-Footing | 12/17/2010 | 12/17/2010 | 12/17/2010 | P | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-####
|
BLD-Conference | 12/10/2010 | 12/10/2010 | 12/13/2010 | P | CANC |
Jim Storey
|
|
|
todd Phone #: ###-####
|
BLD-Conference | 12/10/2010 | 12/13/2010 | 12/13/2010 | A | PART |
Jim Storey
|
|
|
Kitchen ok to be used for training.
|
BLD-Framing/Rough-in | 12/7/2010 | 12/8/2010 | 12/8/2010 | A | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-#### 2 nd floor ok to cover.
|
BLD-Framing/Rough-in | 12/6/2010 | 12/7/2010 | 12/7/2010 | A | PART |
Jim Storey
|
|
|
Todd Phone #: ###-#### box out lid penatrations/ok to insulate
|
BLD-Concrete | 12/3/2010 | 12/3/2010 | 12/3/2010 | P | PART |
Jim Storey
|
|
|
Todd Phone #: ###-#### reviewed rated walls ok to continue assemblie. ft for outside stair from roof ok to form up pending submital if change is decieded.
|
BLD-Conference | 11/1/2010 | 11/1/2010 | 11/1/2010 | P | PART |
Jim Storey
|
|
|
call when go out//Todd ###-####
|
BLD-Framing/Rough-in | 9/3/2010 | 9/7/2010 | 9/7/2010 | A | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-#### orignial approval plan and pending resumital aprovals.
|
BLD-Energy code compliance | 9/7/2010 | 9/7/2010 | 9/7/2010 | A | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-####
|
FIRE-Conference | 9/3/2010 | 9/3/2010 | 9/3/2010 | P | DONE |
Forrest France
|
|
|
Discussion regarding project related fire alarm and sprinkler permit work.
|
BLD-Framing/Rough-in | 9/2/2010 | 9/3/2010 | 9/3/2010 | P | PART |
Jim Storey
|
|
|
Todd Phone #: ###-####
|
BLD-Energy code compliance | 8/27/2010 | 8/27/2010 | 8/27/2010 | P | PART |
Jim Storey
|
|
|
Todd Phone #: ###-#### air seal ok
|
FIRE-Conference | 8/4/2010 | 8/5/2010 | 8/5/2010 | A | DONE |
Forrest France
|
|
|
On site conference regarding project related fire alarm work, HVAC duct detectors, light fixture obstructions at the womens restroom, door hardware, fire code review notes, type one hood suppression, seismic clearance at the new UG fire sprinkler supply, project schedule, etc.
|
BLD-Conference | 7/19/2010 | 7/20/2010 | 7/20/2010 | A | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-#### sheer exterior ok to cover/ interior ele room ok to gyp.
|
BLD-Other | 7/13/2010 | 7/13/2010 | 7/13/2010 | P | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-#### paripets filled with blow in insulation full to comply with type of const. to not have to sprinkler the areas.
|
BLD-Conference | 7/12/2010 | 7/13/2010 | 7/13/2010 | A | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-#### roof deck insulated to 6 inches to meet ec report not 4 per drawring. ok
|
FIRE-Conference | 7/12/2010 | 7/13/2010 | 7/13/2010 | A | DONE |
Forrest France
|
|
|
Regarding insulation fill at concealed spaces.
|
BLD-Other | 7/7/2010 | 7/8/2010 | 7/8/2010 | P | PASS |
Jim Storey
|
|
|
nail inspection//Todd Martin Phone #: ###-#### roof nailling ok per plan.
|