Permit Information
Permit NumberBLD10-00831
StatusFinaled
Name ROCKY MOUNTAIN MANAGEMENT
Site Address 805 W IDAHO ST
Project NameBOISE CITY NATL BANK BLDG
Customer Number 
ePlanReviewNo
Description
(BOISE CITY NATIONAL BANK BUILDING - CORE REMODEL) (8-18-10 PLAN MODIFICATION TO INSTALL AN EXTERIOR ENTRANCE DOOR FROM THE 1ST STORY MAIN ENTRANCE COMMON LOBBY TO THE OUTSIDE AT IDAHO STREET. THE DOOR WILL BE RECESSED SO THAT IT WILL NOT SWING INTO THE PUBLIC WAY. WORK INCLUDES EXTERIOR WALLS WITH R-13 INSULATION AND AN EXTERIOR STUCCO SYSTEM. THE EXTERIOR CANOPY IS NOT COVERED UNDER THIS PERMIT.) The fire sprinkler system substitutes for the 1-hr fire-resistance-rating of the building structure. To remodel the core areas within an existing 5 story building (basement, 4 stories above grade plane, and enclosed mezzanine above the 4th story). Work is to include an interior non-fire-resistance-rated exit discharge on the ground floor to serve an existing stairway enclosure, a non-fire-resistance-rated corridor on the 2nd story to connect stairway enclosures, new suspended ceilings within some core areas, and new finishes in existing restrooms. Two new doorways will be created in existing masonry walls. Steel headers and trimmers will be provided. Common restrooms on the 1st story, 2nd story, 3rd story, and 4th story are required to be accessible to the disabled as defined by current standards, unless technically infeasible. Upgrades will be done where necessary to ensure compliance to the maximum extent possible. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. Some of the trade-offs permitted because this building is fully fire sprinklered are (1) egress from an enclosed stairway is allowed through an interior non-fire-resistance-rated lobby on the ground floor and (2) non-fire-resistance-rated corridors are allowed on all levels. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. Existing fire sprinkler heads will be replaced with quick-response sprinklers in the future on a floor by floor basis as allowed by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection12/22/201112/23/201112/29/2011APASS
DetailsDave Hannah
FIRE-Final Inspection11/22/201111/22/201111/22/2011PPASS
DetailsForrest France
Noted correction items verified for completion. Fire life safety finaled.
BLD-Aging Inspection3/17/20113/17/20113/21/2011 PASS
DetailsDave Hannah
BLD-Conference1/6/20111/6/20111/6/2011PPASS
DetailsDave Hannah
BLD-Aging Inspection1/6/20111/6/20111/6/2011 PASS
DetailsDave Hannah
BLD-Framing/Rough-in11/1/201011/1/201011/1/2010PPASS
DetailsDave Hannah
Brocl Nelson-Steel Stud framing inspection please Phone #: ###-####
BLD-Other10/21/201010/21/201010/21/2010APASS
DetailsDave Hannah
crew working on new section of hallway talked about walls and how to sheetrock
BLD-Aging Inspection10/21/201010/21/201010/21/2010 PASS
DetailsDave Hannah
BLD-Final8/6/20108/6/20108/7/2010PNR
DetailsDave Hannah
scott Phone #: ###-####
FIRE-Final Inspection8/6/20108/6/20108/6/2010PFAIL
DetailsForrest France
Corrections items include; repair one exit sign, one EM light and provide directional arrow at one exit sign per plan on the third floor. Repair one exit/EM light at the second floor. Scope of work per the permit description for the new exit discharge at the ground floor SW corner has not been done, item #15 per the fire code review is not yet provided.
FIRE-Final Inspection8/3/20108/4/20108/5/2010PNR
DetailsForrest France
Scott - life safety Phone #: ###-####
BLD-Final8/5/20108/5/20108/5/2010PNR
DetailsDave Hannah
BLD-Final8/4/20108/5/20108/5/2010ANR
DetailsDave Hannah
Scott Phone #: ###-####
BLD-Other7/28/20107/29/20107/29/2010APASS
DetailsJim Storey
scott - 1st floor - ok to cover Phone #: ###-#### 1st floor ok
BLD-Other7/15/20107/19/20107/19/2010APART
DetailsDave Hannah
Scott - ceiling Phone #: ###-#### ok to cover ceiling on second floor
FIRE-Conference6/22/20106/23/20106/23/2010PDONE
DetailsForrest France
On site visit regarding fire life safety requirements. Noted fire alarm and sprinkler contractors have commenced work without issued permits- double fees will apply. A stop work order may be applied if work continues without authorization.
BLD-Framing/Rough-in6/22/20106/22/20106/22/2010PPASS
DetailsDave Hannah
ok to cover front lobby
BLD-Footing6/21/20106/22/20106/22/2010ACANC
DetailsDave Hannah
Scott Phone #: ###-####