Eberlestock Distribution Center - (Fire Rebuild - Cold Shell) - To reconstruct the cold shell for a 13,150 square foot, two story warehouse and office building destroyed by fire. The building was completely destroyed and demolished with the exception of a couple of exterior walls. The first floor is a 9,100 square foot, warehouse; the 4,050 square foot second floor contains storage and office areas. There is also a proposed 360 square foot occupied roof area above the first floor at the southeast corner of the building. This is a cold shell permit only; no plumbing, mechanical or electrical plans were submitted and no plumbing, mechanical or electrical work is approved under this permit. A separate tenant improvement permit will be required to finish this building for occupancy. The tenant improvement plans must include all items not approved under this permit. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/5/20115/5/20115/5/2011PPASS
DetailsDave Hannah
Dave Phone #: ###-####
DOC - Permit Finaled5/5/20115/5/20115/5/2011PPASS
DetailsDave Hannah
FIRE-Final Inspection4/26/20114/26/20114/26/2011PPASS
DetailsForrest France
Shell building fire life safety passed.
FIRE-Sprinkler Rough-in4/4/20114/4/20114/4/2011APART
DetailsForrest France
Ref. FIR10-00569 for activity notes to date.
FIRE-Sprinkler Rough-in3/7/20113/7/20113/8/2011PPART
DetailsForrest France
Regarding light fixtures at the east side first floor.
BLD-Framing/Rough-in1/14/20111/14/20111/17/2011PPART
DetailsDave Hannah
Dave Phone #: ###-#### ok to cover ext walls
BLD-Other1/11/20111/11/20111/11/2011PPART
DetailsDave Hannah
Dave Phone #: ###-#### shear wall ok to cover ext
BLD-Framing/Rough-in12/28/201012/29/201012/29/2010AFAIL
DetailsDave Hannah
dave Phone #: ###-#### shear needs to renail over shot and used stapels
BLD-Foundation12/16/201012/17/201012/17/2010APART
DetailsDave Hannah
Dave Phone #: ###-#### bottom of elev pit ok to pour
BLD-Energy code compliance12/16/201012/17/201012/17/2010APART
DetailsDave Hannah
dave Phone #: ###-#### roof/deck ok to cover
BLD-Foundation11/4/201011/5/201011/5/2010APASS
DetailsDave Hannah
Dave Phone #: ###-#### slabs over column pads base plates grouted
BLD-Footing9/30/201010/1/201010/1/2010APART
DetailsDave Hannah
dave Phone #: ###-#### ok to pour 10 int ftgs/ column pads and 2 ftgs for cmu walls