BLD-Final | 5/5/2011 | 5/5/2011 | 5/5/2011 | P | PASS |
Dave Hannah
|
|
|
Dave Phone #: ###-####
|
DOC - Permit Finaled | 5/5/2011 | 5/5/2011 | 5/5/2011 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Final Inspection | 4/26/2011 | 4/26/2011 | 4/26/2011 | P | PASS |
Forrest France
|
|
|
Shell building fire life safety passed.
|
FIRE-Sprinkler Rough-in | 4/4/2011 | 4/4/2011 | 4/4/2011 | A | PART |
Forrest France
|
|
|
Ref. FIR10-00569 for activity notes to date.
|
FIRE-Sprinkler Rough-in | 3/7/2011 | 3/7/2011 | 3/8/2011 | P | PART |
Forrest France
|
|
|
Regarding light fixtures at the east side first floor.
|
BLD-Framing/Rough-in | 1/14/2011 | 1/14/2011 | 1/17/2011 | P | PART |
Dave Hannah
|
|
|
Dave Phone #: ###-#### ok to cover ext walls
|
BLD-Other | 1/11/2011 | 1/11/2011 | 1/11/2011 | P | PART |
Dave Hannah
|
|
|
Dave Phone #: ###-#### shear wall ok to cover ext
|
BLD-Framing/Rough-in | 12/28/2010 | 12/29/2010 | 12/29/2010 | A | FAIL |
Dave Hannah
|
|
|
dave Phone #: ###-#### shear needs to renail over shot and used stapels
|
BLD-Foundation | 12/16/2010 | 12/17/2010 | 12/17/2010 | A | PART |
Dave Hannah
|
|
|
Dave Phone #: ###-#### bottom of elev pit ok to pour
|
BLD-Energy code compliance | 12/16/2010 | 12/17/2010 | 12/17/2010 | A | PART |
Dave Hannah
|
|
|
dave Phone #: ###-#### roof/deck ok to cover
|
BLD-Foundation | 11/4/2010 | 11/5/2010 | 11/5/2010 | A | PASS |
Dave Hannah
|
|
|
Dave Phone #: ###-#### slabs over column pads base plates grouted
|
BLD-Footing | 9/30/2010 | 10/1/2010 | 10/1/2010 | A | PART |
Dave Hannah
|
|
|
dave Phone #: ###-#### ok to pour 10 int ftgs/ column pads and 2 ftgs for cmu walls
|