BLD-Final | 6/28/2011 | 7/1/2011 | 7/1/2011 | A | PASS |
Mike Jordan
|
|
|
JULIO Phone #: ###-####All issues have been resolved. Ok for perm occ.
|
FIRE-Final Inspection | 5/2/2011 | 5/3/2011 | 5/3/2011 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
BLD-Final | 4/5/2011 | 4/5/2011 | 4/5/2011 | P | PART |
Mike Jordan
|
|
|
herb Phone #: ###-####. Temp. occ. granted.
|
FIRE-Final Inspection | 4/5/2011 | 4/5/2011 | 4/5/2011 | P | PART |
Troy Cobbley
|
|
|
A temporary was given with Scott's permission until the as-built building drawings have been approved. A follow up inspection will be required to verify the new approved plans have been complied with.
|
FIRE-Final Inspection | 4/1/2011 | 4/4/2011 | 4/4/2011 | A | FAIL |
Troy Cobbley
|
|
|
Plans need to be resubmitted showing the wall and door changes in the shop and parts areas which may be increasing the occupant load. Emergency lights need to be installed in the missing locations in the shop and in the oil pit. The project related fire alarm permit needs to be finaled. The changes in the new fire hydrant location is approved by Scott.
|
BLD-Final | 4/1/2011 | 4/4/2011 | 4/1/2011 | A | NR |
Tom Arcoraci
|
|
|
Later pending Life/Safety--Herb Phone #: ###-####
|
BLD-Conference | 3/24/2011 | 3/25/2011 | 3/25/2011 | A | DONE |
Mike Jordan
|
|
|
herb Phone #: ###-####
|
BLD-Framing/Rough-in | 2/22/2011 | 2/22/2011 | 2/22/2011 | P | PART |
Mike Jordan
|
|
|
herb Phone #: ###-####. Interior wood framed walls for restoom/lockeroom and breakroom. Pending plumbing rough in.
|
BLD-Framing/Rough-in | 1/24/2011 | 1/25/2011 | 1/25/2011 | A | PART |
Jim Sly
|
|
|
Herb Phone #: ###-#### OK to cover....Service manager, tire storage rooms including (2) shear walls (A) adjacent to these rooms.
|
BLD-Conference | 12/27/2010 | 12/27/2010 | 12/27/2010 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 12/27/2010 | 12/27/2010 | 12/27/2010 | P | PASS |
Mike Jordan
|
|
|
Interior and exterior shear nailing on parts department existing and new portions of biulding.
|
BLD-Framing/Rough-in | 11/15/2010 | 11/15/2010 | 11/15/2010 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 10/25/2010 | 10/26/2010 | 10/26/2010 | P | PASS |
Mike Jordan
|
|
|
herb Phone #: ###-####. Inspected added hdu-2 and hdu-4 simpson holdwns and added anchor bolts for shear on existing buiklding, also noted added trimmer studs as neded. Reviewed special inspection reports as well.
|
BLD-Conference | 10/21/2010 | 10/21/2010 | 10/21/2010 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Conference | 10/20/2010 | 10/21/2010 | 10/21/2010 | A | CANC |
Mike Jordan
|
|
|
Herb Phone #: ###-####. Moved to pm.
|