Permit Information
Permit NumberBLD10-01604
StatusFinaled
Name VAN AUKER CONSTRUCTION
Site Address 3491 S TK AVE
Project NameB and D Foods
Customer Number 
ePlanReviewNo
Description
B and D Foods - Warehouse and Freezer Addition - To construct a 12,585 square foot, one story, pre-engineered metal building warehouse and freezer addition on the east side of an existing 26,000 square foot, one story office and warehouse building. The addition will have within it a 4,340 square foot freezer warehouse and an 895 square foot, wood framed mezzanine above the breakroom/restroom area. This permit also includes related site improvements. All construction per the approved plans and attached comment list. JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final4/11/20114/11/20114/11/2011PPASS
DetailsJim Storey
DOC - Permit Finaled4/11/20114/11/20114/11/2011PPASS
DetailsJim Storey
BLD-Aging Inspection3/23/20113/23/20113/23/2011 PASS
DetailsJim Storey
building ok pending permit sign off p$z and esc.
BLD-Final1/20/20111/21/20111/21/2011PPART
DetailsJim Storey
jim Phone #: ###-#### building ok pending bld racking permit sign off as well sa p$z and esc.
FIRE-Final Inspection1/20/20111/21/20111/21/2011APASS
DetailsForrest France
Fire life safety inspection passed after corrections made while on site.
FIRE-Final Inspection1/18/20111/19/20111/19/2011APEND
DetailsForrest France
Fire life safety final pending project related fire sprinkler permit work. Some items incomplete at this time.
FIRE-Sprinkler Rough-in1/12/20111/12/20111/13/2011PPART
DetailsForrest France
Overhead fire sprinkler work okay for cover at the grid ceiling areas.
BLD-Other1/12/20111/12/20111/12/2011PPASS
DetailsJim Storey
ceilling grid
BLD-Grading Inspection1/11/20111/12/20111/12/2011PDEFR
DetailsJim Storey
Jim Phone #: ###-####
BLD-Energy code compliance12/22/201012/27/201012/27/2010APASS
DetailsJim Storey
late am please//Jim Phone #: ###-####
BLD-Framing/Rough-in12/22/201012/23/201012/23/2010PPASS
DetailsJim Storey
Jim Phone #: ###-#### ceilling ok pending ele aproval.
BLD-Footing11/2/201011/3/201011/3/2010APASS
DetailsJim Storey
footing/rebar insp--wants late am--Jim Phone #: ###-#### center peirs as per engineering submited ot frost protection.
BLD-Footing11/2/201011/2/201011/3/2010PPASS
DetailsJim Storey
Jim Phone #: ###-####
BLD-Energy code compliance10/22/201010/25/201010/25/2010APART
DetailsJim Storey
jim Phone #: ###-####
BLD-Foundation10/22/201010/25/201010/25/2010APASS
DetailsJim Storey
jim - rebar Phone #: ###-####
BLD-Footing10/18/201010/19/201010/19/2010APASS
DetailsJim Storey
Footing & Re-bar inspection please-Jim Phone #: ###-#### 1/2 north east walls ok.
BLD-Footing10/12/201010/13/201010/13/2010APASS
DetailsJim Storey
request late am//Dan Phone #: ###-####