BLD-Aging Inspection | 4/29/2011 | 4/29/2011 | 4/29/2011 | | PASS |
Dave Hannah
|
|
|
|
BLD-Final | 1/28/2011 | 1/28/2011 | 1/31/2011 | P | PART |
Tony Young
|
|
|
temp occ. ok,, needs final letter of okay from engineer and architect on changes and special inspection reports,, also need public works complete sign off
|
FIRE-Final Inspection | 1/27/2011 | 1/27/2011 | 1/27/2011 | P | PASS |
Forrest France
|
|
|
mike Phone #: ###-####
|
BLD-Framing/Rough-in | 12/13/2010 | 12/14/2010 | 12/14/2010 | A | NR |
Jim Storey
|
|
|
michael - ceiling grid Phone #: ###-####
|
BLD-Framing/Rough-in | 11/16/2010 | 11/19/2010 | 11/19/2010 | A | PART |
Dave Hannah
|
|
|
Michael Phone #: ###-#### office area ok but needs rfi from engineer plans call out wood studs contractor used steel also moved a door in mec room
|
BLD-Footing | 11/3/2010 | 11/3/2010 | 11/3/2010 | P | PASS |
Dave Hannah
|
|
|
Mike ###-#### wash station ftgs and column pads
|