BLD-Final | 10/18/2011 | 10/18/2011 | 10/18/2011 | P | PASS |
Dave Hannah
|
|
|
rick - lowered a sink Phone #: ###-#### ok for perm occ
|
FIRE-Final Inspection | 10/3/2011 | 10/4/2011 | 10/4/2011 | A | PASS |
Forrest France
|
|
|
Adjustments at two exit signs and one EM light repaired while on site. Remainder of fire life safety inspection passed.
|
BLD-Final | 10/3/2011 | 10/4/2011 | 10/4/2011 | A | PART |
Dave Hannah
|
|
|
RICK Phone #: ###-#### ok for temp occ ok for perm occ after they lower the sink on seond floor
|
BLD-Final | 9/9/2011 | 9/12/2011 | 9/12/2011 | A | NR |
Dave Hannah
|
|
|
ron hill - 10:00 Phone #: ###-####
|
FIRE-Final Inspection | 9/9/2011 | 9/12/2011 | 9/12/2011 | A | PART |
Forrest France
|
|
|
ron hill - 10:00 Phone #: ###-####
|
BLD-Final | 8/30/2011 | 8/30/2011 | 9/12/2011 | P | CANC |
Dave Hannah
|
|
|
rick Phone #: ###-####
|
BLD-Final | 8/26/2011 | 8/26/2011 | 9/12/2011 | P | CANC |
Dave Hannah
|
|
|
rick Phone #: ###-####
|
DOC - Permit Finaled | 9/7/2011 | 9/7/2011 | 9/7/2011 | P | PASS |
Dave Hannah
|
|
|
|
FIRE-Conference | 9/6/2011 | 9/6/2011 | 9/6/2011 | A | DONE |
Forrest France
|
|
|
|
FIRE-Final Inspection | 8/18/2011 | 8/19/2011 | 8/19/2011 | A | NR |
Forrest France
|
|
|
Final pending project related fire alarm and sprinkler permit finals. Also noted missing exit signs at the 2nd and 3rd floors, need to add discharge lighting at the south exit, discussed project schedule.
|
BLD-Final | 8/11/2011 | 8/12/2011 | 8/12/2011 | A | NR |
Dave Hannah
|
|
|
rick Phone #: ###-#### walked project with rick he will keep working to get everything finished
|
BLD-Other | 7/21/2011 | 7/22/2011 | 7/22/2011 | P | PASS |
Dave Hannah
|
|
|
partial ceiling insp (stairwells)//Steve Phone #: ###-####
|
BLD-Other | 7/21/2011 | 7/21/2011 | 7/22/2011 | P | PASS |
Dave Hannah
|
|
|
ceiling insp//Rick Phone #: ###-#### ok to cover third floor
|
BLD-Other | 7/14/2011 | 7/15/2011 | 7/15/2011 | P | PART |
Dave Hannah
|
|
|
celing inspection//Rick ###-#### Third floor offices ok to cover
|
BLD-Other | 7/1/2011 | 7/5/2011 | 7/5/2011 | A | PASS |
Tom Arcoraci
|
|
|
Ceiling Grid---Steve Phone #: ###-#### 2nd floor patch stair tower grid ok
|
BLD-Other | 6/6/2011 | 6/6/2011 | 6/7/2011 | P | PART |
Dave Hannah
|
|
|
Steve Phone #: ###-#### ok to cover ceiling in the two lecture rooms first floor
|
FIRE-Sprinkler Rough-in | 5/9/2011 | 5/9/2011 | 5/9/2011 | A | PART |
Forrest France
|
|
|
Overhead fire sprinkler work approved for ceiling cover at the 2nd floor computer room.
|
BLD-Framing/Rough-in | 4/12/2011 | 4/13/2011 | 4/14/2011 | A | PASS |
Dave Hannah
|
|
|
2nd floor-Rick Phone #: ###-#### ok to cover second and thrid floors walls but plumbing to firestop floors
|
FIRE-Conference | 4/13/2011 | 4/13/2011 | 4/13/2011 | P | DONE |
Forrest France
|
|
|
Regarding new SW head locations at the covered entry east side.
|
BLD-Framing/Rough-in | 3/31/2011 | 3/31/2011 | 4/1/2011 | P | PART |
Dave Hannah
|
|
|
Steve Phone #: ###-#### ok to cover first floor
|
BLD-Other | 3/23/2011 | 3/24/2011 | 3/31/2011 | A | PART |
Dave Hannah
|
|
|
shaft insp//Rick Phone #: ###-####
|
FIRE-Sprinkler Rough-in | 3/30/2011 | 3/30/2011 | 3/30/2011 | A | PART |
Forrest France
|
|
|
Supply line flush okayed
|
BLD-Framing/Rough-in | 3/9/2011 | 3/10/2011 | 3/11/2011 | A | PART |
Dave Hannah
|
|
|
exterior insulation and framing insp--Rick Phone #: ###-#### ok to cover ext and int on ext bldg
|
FIRE-Sprinkler Rough-in | 3/7/2011 | 3/7/2011 | 3/8/2011 | A | PART |
Forrest France
|
|
|
Beam clamps and retainers at the 2nd floor okayed.
|
BLD-Framing/Rough-in | 2/23/2011 | 2/24/2011 | 2/24/2011 | A | PART |
Dave Hannah
|
|
|
exterior framing and sheathing insp South side//Rick Phone #: ###-#### ok to cover south ext
|
BLD-Framing/Rough-in | 2/17/2011 | 2/18/2011 | 2/18/2011 | A | PART |
Dave Hannah
|
|
|
rick Phone #: ###-#### ok to cover east ext end of bldg
|
BLD-Framing/Rough-in | 2/15/2011 | 2/16/2011 | 2/16/2011 | A | PART |
Dave Hannah
|
|
|
Rick Phone #: ###-#### east ext wall ok to cover ext
|
FIRE-Sprinkler Rough-in | 2/14/2011 | 2/14/2011 | 2/14/2011 | P | PART |
Forrest France
|
|
|
Inspection for beam clamps/retainers and seismic brace attatchments at the 3rd floor okayed pre fireproof coating application.
|
BLD-Concrete | 1/21/2011 | 1/24/2011 | 1/24/2011 | A | PART |
Dave Hannah
|
|
|
rick Phone #: ###-#### mti on site doing concrete and slab reinfocement for the third floor pour
|
FIRE-Sprinkler Rough-in | 1/12/2011 | 1/12/2011 | 1/12/2011 | A | PART |
Forrest France
|
|
|
Beam clamps and seismic straps at overhead sprinkler main line hangers on the first floor okayed.
|
BLD-Concrete | 1/4/2011 | 1/5/2011 | 1/5/2011 | P | PART |
Dave Hannah
|
|
|
Reinforcing inspection please-Rick Phone #: ###-#### second floor deck ok to pour
|