BLD-Conference | 9/13/2012 | 9/14/2012 | 9/14/2012 | A | CANC |
Mike Jordan
|
|
|
Final Inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Final | 9/14/2012 | 9/14/2012 | 9/14/2012 | A | PASS |
Mike Jordan
|
|
|
Final Inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. Ok for perm occ.
|
BLD-Conference | 9/12/2012 | 9/12/2012 | 9/12/2012 | P | PART |
Mike Jordan
|
|
|
Final Building Inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. HAndrail has been repaired. Ok for temp occ. Waiting on letter from engineer of record to accomidate final letter from special inspection agency.
|
BLD-Conference | 9/10/2012 | 9/10/2012 | 9/10/2012 | P | NR |
Mike Jordan
|
|
|
Final building inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. Needs to repair handrail in shop.
|
FIRE-Alarm Testing | 9/6/2012 | 9/6/2012 | 9/6/2012 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Final Inspection | 9/4/2012 | 9/5/2012 | 9/5/2012 | A | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to sign off when the project related fire alarm permit is addressed.
|
FIRE-Conference | 9/4/2012 | 9/4/2012 | 9/4/2012 | A | CANC |
Troy Cobbley
|
|
|
Life Safety inspection rescheduled for tomorrow when the fire alarm and fire sprinkler permits are addressed.
|
BLD-Conference | 8/24/2012 | 8/24/2012 | 8/24/2012 | A | DONE |
Mike Jordan
|
|
|
Final Building inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. Walk through with contractor. Noted that not all glazing is in place or door hardware. Needs to repair handrails in shop, provide guard at chiller. ADA unisex restroom has been made compliant. A letter has been sent to building official regarding the non compliant restroom. Also need as built drawings for review.
|
FIRE-Conference | 8/21/2012 | 8/22/2012 | 8/23/2012 | P | DONE |
Troy Cobbley
|
|
|
Scott and I went over life safety requirements for the project.
|
BLD-Conference | 8/18/2012 | 8/21/2012 | 8/21/2012 | A | CANC |
Mike Jordan
|
|
|
Life Safety Preliminary inspection with Troy Cobbley Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Conference | 8/7/2012 | 8/8/2012 | 8/8/2012 | A | DONE |
Mike Jordan
|
|
|
8:30 AM walk through of handrails etc. Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Conference | 8/2/2012 | 8/2/2012 | 8/2/2012 | A | PASS |
Tom Arcoraci
|
|
|
Lower Level Ceiling inspection. Phone #: ###-#### >> Inspection requested via web by Scott Greer ok 408
|
BLD-Conference | 7/26/2012 | 7/26/2012 | 7/26/2012 | A | PASS |
Mike Jordan
|
|
|
Suspended ceiling re inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. grid ceiling, main level ok to cover. additional support has been added per cicsca0-2 standard.
|
BLD-Conference | 7/16/2012 | 7/17/2012 | 7/20/2012 | A | PART |
Mike Jordan
|
|
|
Ceiling inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. Adminstrative office and changing rooms. Need letter from engineer for alternate on hanger wires for diffusers.
|
BLD-Framing/Rough-in | 7/13/2012 | 7/16/2012 | 7/16/2012 | A | DONE |
Mike Jordan
|
|
|
Ceiling inspections rooms 159, 177, 149, 136, 145, 142, 140, 141, 143. Phone #: ###-#### >> Inspection requested via web by Scott Greer. Went over CISCA requirements with contractor, no inspections.
|
BLD-Conference | 7/13/2012 | 7/13/2012 | 7/13/2012 | A | PART |
Mike Jordan
|
|
|
Ceiling inspections rooms 159, 177, 149, 136, 145, 142, 140, 141, 143. Phone #: ###-#### >> Inspection requested via web by Scott Greer. Grid inspection at locker rooms, Need wires on diffusers.
|
BLD-Conference | 5/4/2012 | 5/4/2012 | 5/4/2012 | P | PASS |
Mike Jordan
|
|
|
Framing inspection Maintenance shop Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Conference | 4/27/2012 | 4/30/2012 | 4/30/2012 | A | PASS |
Mike Jordan
|
|
|
Framing re inspection area E Phone #: ###-#### >> Inspection requested via web by Scott Greer. Vapor barrier material in area E has been removed and replaced with compliant vapor barrier.
|
BLD-Conference | 4/24/2012 | 4/24/2012 | 4/24/2012 | P | PART |
Mike Jordan
|
|
|
Framing inspection in area E Phone #: ###-#### >> Inspection requested via web by Scott Greer. Interior steel stud framed walls and hardlids At area E and basement, Pending other trades rough in inspections. Also received tech data for spray foam insulation that has been used in area E. Flame and smoke spread indexes o. Will also remove some non compliant visquin in concelled areas and provide the correct visquin.
|
BLD-Conference | 3/20/2012 | 3/20/2012 | 3/20/2012 | A | PASS |
Mike Jordan
|
|
|
Framing inspection in area D Inclusive grid lined 6 to 11. Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Conference | 2/16/2012 | 2/23/2012 | 2/24/2012 | A | CANC |
Jim Sly
|
|
|
Went to job site.....they didn't call this in.
|
BLD-Framing/Rough-in | 2/16/2012 | 2/16/2012 | 2/16/2012 | P | PASS |
Mike Jordan
|
|
|
roof framing and sheathing for overbuild at south enterance.
|
FIRE-Conference | 2/14/2012 | 2/14/2012 | 2/14/2012 | P | DONE |
Troy Cobbley
|
|
|
Carl Westfall and I performed a job site review of the exit signs in areas A and B. I let the superintendant Scott know that they need to be installed as per approved plans and the two that are blocked by the low soffits will need to be viewable from the far end of the corridor.
|
BLD-Conference | 2/14/2012 | 2/14/2012 | 2/14/2012 | A | CANC |
Mike Jordan
|
|
|
Site sewer inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Conference | 2/2/2012 | 2/9/2012 | 2/9/2012 | A | PASS |
Mike Jordan
|
|
|
Interior steel stud framed walls and hardlids for area C. Also walk through mech. room and reviewed special inspection reports.
|
BLD-Other | 2/3/2012 | 2/3/2012 | 2/3/2012 | P | CANC |
Mike Jordan
|
|
|
|
BLD-Other | 2/3/2012 | 2/3/2012 | 2/3/2012 | A | PASS |
Mike Jordan
|
|
|
witness epxoy bolting for tw holddowns on shearwalls at gridline 2.
|
BLD-Conference | 1/25/2012 | 2/2/2012 | 2/2/2012 | A | DONE |
Mike Jordan
|
|
|
reviewed special inspection reports via email and spoke to scott about exit light issues and exiting issues.
|
BLD-Conference | 1/27/2012 | 1/27/2012 | 1/27/2012 | P | DEFR |
Mike Jordan
|
|
|
Footing rebar inspection for plan mod # 4 Phone #: ###-#### >> Inspection requested via web by Scott Greer. Special inspector on site.
|
BLD-Conference | 1/25/2012 | 1/25/2012 | 1/26/2012 | P | PASS |
Mike Jordan
|
|
|
Reviewed special inspection reports and walked jobsite.
|
BLD-Conference | 1/5/2012 | 1/5/2012 | 1/5/2012 | A | PASS |
Mike Jordan
|
|
|
Framing inspection between grid lines 13 - 17 and D - L Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Framing/Rough-in | 1/5/2012 | 1/5/2012 | 1/5/2012 | P | PASS |
Mike Jordan
|
|
|
Framing inspection between grid lines 13 - 17 and D - L Phone #: ###-#### >> Inspection requested via web by Scott Greer. Interior steel sted framed walls and hardlids ok. Pending fire sprinkler rough in inspection.
|
BLD-Other | 12/27/2011 | 12/27/2011 | 12/27/2011 | P | PASS |
Tom Arcoraci
|
|
|
scott - shear nail Phone #: ###-#### hall 166 ok
|
BLD-Conference | 12/22/2011 | 12/22/2011 | 12/22/2011 | A | PASS |
Tom Arcoraci
|
|
|
Framing inspection area A Rooms 181 - 205 Phone #: ###-#### >> Inspection requested via web by Scott Greer a area ok
|
BLD-Conference | 12/1/2011 | 12/22/2011 | 12/21/2011 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 12/14/2011 | 12/15/2011 | 12/15/2011 | P | DONE |
Mike Jordan
|
|
|
Gypsum nailing inspection. any time Concrete wall rebar inspection at chiller building. Special inspector at 1:00 PM. Concrete scheduled at 1:30 PM Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Foundation | 12/15/2011 | 12/15/2011 | 12/15/2011 | P | PASS |
Mike Jordan
|
|
|
Gypsum nailing inspection. any time Concrete wall rebar inspection at chiller building. Special inspector at 1:00 PM. Concrete scheduled at 1:30 PM Phone #: ###-#### >> Inspection requested via web by Scott Greer. Vertical and horizontal reinforcement for W1 type walls at grids X12 and and grid Xc per RFI#282.1(These walls are to be architectual concrete. Previously they were to be masonry walls). Noted that vertical reinforcement at these walls was already placed at 12" o.c.
|
BLD-Conference | 12/1/2011 | 12/15/2011 | 12/15/2011 | A | DONE |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 12/15/2011 | 12/15/2011 | 12/15/2011 | A | PASS |
Mike Jordan
|
|
|
Shear wall holdowns at rooms 164 and 175 (mens and womens restroom) per ASI #5. ok to place plywood after electrical rough in inspection passes.
|
BLD-Conference | 12/1/2011 | 12/8/2011 | 12/8/2011 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Framing/Rough-in | 12/8/2011 | 12/8/2011 | 12/8/2011 | A | PASS |
Mike Jordan
|
|
|
Interior Steel stud construction for walls, soffits and catwalks for rooms 192, 193, 194, 195 and 182. Also inspected guards for noted catwalks.
|
FIRE-Conference | 12/6/2011 | 12/6/2011 | 12/6/2011 | P | DONE |
Troy Cobbley
|
|
|
I requested Tim Frost to accompany me to this project to verify possible issues with combustible concealed spaces that I had found on the previous days courtesy inspection. We found many areas which have not been provided upright sprinkler protection and when protection is provided will require many additional sprinkler heads. Per the city approved plans only pendant protection below the ceilings has been provided in these areas. I spoke to the sprinkler fitter and let him know that Plan Modifications will be required. I also spoke to Frank and Ricardo with Jacobsen Construction about a possible stop work order if any more piping is covered and the possibility of removing ceilings just to inspect what has already been installed and covered. No sprinkler rough-in inspections have been performed to this point. I notified Scott and Romeo of the situation.
|
BLD-Conference | 11/30/2011 | 12/1/2011 | 12/1/2011 | P | PASS |
Mike Jordan
|
|
|
Rebar inspection in the north west garden retaining wall. Concrete scheduled for 2:00PM. Special inspector scheduled for 1:00
Epoxy hold down inspections for interior shear walls. Any time in PM Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Foundation | 12/1/2011 | 12/1/2011 | 12/1/2011 | P | PASS |
Mike Jordan
|
|
|
Exterior northwest garden retaining wall. Will have special inspection.
|
BLD-Framing/Rough-in | 12/1/2011 | 12/1/2011 | 12/1/2011 | P | PASS |
Mike Jordan
|
|
|
Simpson htt14 tie downs at interior shearwall on grid 15.8. Also reviewed special inspection reports.
|
BLD-Conference | 11/14/2011 | 11/15/2011 | 11/15/2011 | A | PASS |
Mike Jordan
|
|
|
Chiller shop footing and rebar inspection east end. Concrete scheduled for 1:00 ans special inspector at 12:00 Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Conference | 10/10/2011 | 11/2/2011 | 11/2/2011 | A | PASS |
Mike Jordan
|
|
|
Reviewed special inspector reports. Aslo noted backfilling operations for water feature and at chiller room.
|
BLD-Foundation | 11/2/2011 | 11/2/2011 | 11/2/2011 | P | PART |
Mike Jordan
|
|
|
Stemwall for pump house and trash enclosure. Work in progress on installing vertical reinforcement. All per approved plans and RFI from engineer.
|
BLD-Conference | 10/26/2011 | 10/28/2011 | 10/28/2011 | A | PASS |
Mike Jordan
|
|
|
Chiller room walls. Formwork and rebar. Concrete scheduled for 1:00 Friday. Rebar is ready to inspect any time Thursday all doay or Friday morning. Special inspector scheduled for Thursday to look at rebar. Special inspector scheduled for Friday at 1:00 to cast 2 sets of cylinders during pour Phone #: ###-#### >> Inspection requested via web by Scott GreerW3 and W5 type walls ok. as per plans and RFI's.
|
BLD-Conference | 10/26/2011 | 10/26/2011 | 10/26/2011 | P | PASS |
Mike Jordan
|
|
|
Reviewed special inspection reports. Also noted RFI #219, from structural engineer, repairing the omition of #6 bar at wall type W3. Additional #5 will be placed at 32" o.c. at inside face of wall at areas not integral with drilled piers. Also noted work in progress on interior moment frames on south end of building. Noted that their will be an additional plan modification for west vestibule to be submitted by architect.
|
BLD-Conference | 10/10/2011 | 10/26/2011 | 10/26/2011 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Conference | 10/24/2011 | 10/25/2011 | 10/25/2011 | A | DEFR |
Mike Jordan
|
|
|
Partial footing inspection for the chiller building. Concrete cheduled for 10:00 AM Special inspector scheduled for 9:00 AM Phone #: ###-#### >> Inspection requested via web by Scott Greer
|
BLD-Footing | 10/20/2011 | 10/21/2011 | 10/21/2011 | A | PART |
Jim Storey
|
|
|
scott - rebar footing and wall Phone #: ###-#### west 1/2 of south wall wip mti to be on site at pm placment time. vert descrepincy for #6 bar to be addressed by engineer for next wall section.
|
BLD-Conference | 10/10/2011 | 10/19/2011 | 10/19/2011 | A | PASS |
Mike Jordan
|
|
|
|
BLD-Conference | 10/15/2011 | 10/17/2011 | 10/17/2011 | A | PART |
Mike Jordan
|
|
|
Interior Stair rebar. Shop wall rebar. Special inspector scheduled at 12:00 noon. Concrete scheduled for 1:00 PM >> Inspection requested via web by Scott Greer
|
BLD-Conference | 10/13/2011 | 10/14/2011 | 10/14/2011 | P | PART |
Jim Sly
|
|
|
Rebar in foundation wall concrete scheduled for 3:00 PM Special inspection. >> Inspection requested via web by Scott Greer small section of 8' high wall at South side of bldg. MTI has inspected.
|
BLD-Conference | 10/10/2011 | 10/12/2011 | 10/12/2011 | A | PASS |
Mike Jordan
|
|
|
Reviewed special inspection reports, Work in progress on south retaining wall, and on catwalk on interior of building.
|
BLD-Conference | 10/8/2011 | 10/10/2011 | 10/10/2011 | P | CANC |
Mike Jordan
|
|
|
Rebar inspection fro Shop and chiller building walls. Special inspection scheduled for Monday afernoon. Pour on Tuesday >> Inspection requested via web by Scott Greer
|
BLD-Foundation | 10/10/2011 | 10/10/2011 | 10/10/2011 | P | PART |
Mike Jordan
|
|
|
South retaining aloong piers. Work is in progress. Will have special inspection prior to concrete placement.
|
BLD-Conference | 10/7/2011 | 10/7/2011 | 10/7/2011 | P | PART |
Mike Jordan
|
|
|
Inspection on rebar prior to form placement at new chiller, boiler area.
|
BLD-Conference | 10/6/2011 | 10/7/2011 | 10/7/2011 | A | PASS |
Mike Jordan
|
|
|
Shear wall inspection Grid line 23 Phone #: ###-#### >> Inspection requested via web by Scott Greer. Shearwall at gridline 23 ok, as per ASI#23, will need to submit plan mod.
|
BLD-Conference | 9/20/2011 | 9/21/2011 | 9/21/2011 | P | PASS |
Mike Jordan
|
|
|
Foundation inspection Concrete scheduled for 2:30 Special inspection scheduled at 2:00 Phone #: ###-#### x801 >> Inspection requested via web by Scott Greer. Stemwall and column pad pedestals at annex addition. Special inspector on site. Also work in progress on interior piers at shear wall locations.
|
BLD-Footing | 9/19/2011 | 9/20/2011 | 9/20/2011 | A | PART |
Mike Jordan
|
|
|
Scott Phone #: ###-####. Footings for annex addition. Special inspector also on site.
|
BLD-Footing | 9/16/2011 | 9/16/2011 | 9/16/2011 | A | DEFR |
Mike Jordan
|
|
|
scott - ###-#### - pouring at 9:00 am
|
BLD-Other | 8/26/2011 | 8/26/2011 | 8/26/2011 | P | PART |
Mike Jordan
|
|
|
Drill ---Richardo Phone #: ###-####. REmainder of drilled piers on south side of building, special inspectors were on site observing the drilling adn will inspect rebar and test concrete.
|
BLD-Footing | 8/26/2011 | 8/26/2011 | 8/26/2011 | A | PART |
Mike Jordan
|
|
|
Richardo Phone #: 801-577-971. RFeinforcement for concrete stairs, went over noising requirements with contractor. Willl have special inspection.
|
BLD-Concrete | 8/25/2011 | 8/25/2011 | 8/25/2011 | P | PART |
Mike Jordan
|
|
|
ricardo - ###-####. Work in progress on drilled piers south end, special inspector on site. Aslo inspected the nearly completed interior footings for existing columns that were moved to gridline 15.6 and remainder of column footing work on grid 25.5.
|
BLD-Concrete | 8/24/2011 | 8/24/2011 | 8/24/2011 | P | PASS |
Mike Jordan
|
|
|
Drilling piers inspection please-Ricardo Phone #: ###-####. Noted special inspector on site during the drilliong of the drilled piers and rebar and concrete.
|
BLD-Concrete | 8/23/2011 | 8/23/2011 | 8/23/2011 | P | PART |
Mike Jordan
|
|
|
Ricardo Donoso Phone #: ###-####. Drilled piers. south side of bldg. Noted special inspector on site. Noted to jacobsen construction that special inspection is required o n drilled concrete for drilled piers as per approved plans, specs and chapter 17 if the IBC, continous special inspection is also required while piers ore being drilled.
|
BLD-Footing | 8/19/2011 | 8/22/2011 | 8/22/2011 | P | PASS |
Mike Jordan
|
|
|
Ricado this is for the out side footings only Phone #: ###-####. Drilled piers # 27.30,32.
|
BLD-Footing | 8/18/2011 | 8/19/2011 | 8/19/2011 | A | PART |
Tom Arcoraci
|
|
|
scott - ###-#### - exterior footing spec insp on site
|
BLD-Footing | 8/18/2011 | 8/18/2011 | 8/18/2011 | A | PART |
Mike Jordan
|
|
|
Scott Greer ###-#### per Scott this inspection has nothing to do with the plan mod in review. Drilled piers south side, work in progress.
|
BLD-Footing | 8/17/2011 | 8/17/2011 | 8/17/2011 | P | NR |
Mike Jordan
|
|
|
Soils issues with driiled piers, wating for geo-tech and engineering response.
|
BLD-Footing | 8/12/2011 | 8/15/2011 | 8/15/2011 | P | PART |
Mike Jordan
|
|
|
Rebar & epoxy by special inspector at 9:00 AM Rebar and footing inspection needed at 1:00 if possible Concrete scheduled at 2:00 PM Phone #: ###-#### >> Inspection requested via web by Ricardo Donosso. Grade beam footings on grid line 23, North portion of building (ordinance room). Noted that their has been a structural change to footings from city set of approved plans, a plan mod needs to be sumbitted to cty for approval.
|