Information based on query as of Saturday, June 29, 2024.
Permit Information
Permit NumberBLD10-02069
StatusFinaled
Name JACOBSEN CONSTRUCTION COMPANY INC
Site Address 1211 S COLE RD
Project NameLDS TEMPLE
Customer Number 
ePlanReviewNo
Description
(LDS TEMPLE REMODEL AND ADDITION) (1-19-12 PLAN MODIFICATION #4. SEE NOTE IN COMMNETS FIELD.) (11-9-11 PLAN MODIFICATION TO VERIFY THE ACTUAL OCCUPANT LOAD OF THE BUILDING. THE OCCUPANT LOAD OF THE MAIN TEMPLE BUILDING WAS CHANGED FROM 1,070 TO 995. IN ADDITION TO REVISED OCCUPANT LOADS FOR SOME ROOMS, THE CENTER ASSEMBLY ROOM HAVING AN OCCUPANT LOAD OF 48 IN THE GROUP OF FIVE ASSEMBLY ROOMS WAS CONSIDERED TO BE ACCESSORY FOR OCCUPANT LOAD) (9-16-11 PLAN MODIFICATION TO RELOCATED THE FIRE DEPARTMENT CONNECTION AND THE POST INDICATOR VALVE AND TO REPLACE MUCH OF THE HANGING CATWALK WITH NON-HANGING CATWALK) (8-24-11 PLAN MODIFICATION SUBMITTED ON AUGUST 15, 2011 FOR EAST MOMENT FRAME AT GRID 23 WAS APPROVED.) The fire sprinkler system is used for building area increase and for fire area. A 2,000 square foot maintenance shop and storage basement located on the South side of the main Temple Building was demolished under permit BLD11-01606. Interior nonstructural demolition within the main Temple Building was also covered under that permit. The pump house and dumpster enclosure was constructed under permit BLD11-01333. To construct a 5,050 square foot Grounds Shop, Engineering/Maintenance, Boiler Room, and Chiller Room basement addition in the place of the demolished maintenance shop and storage basement (i.e. on the South side of the main Temple Building). Work is to include concrete footings, 24” diameter concrete piers 10 feet long, concrete foundations, masonry walls, concrete stairways, interior frame walls, interior wall furring, steel columns, steel beams, steel roof deck, steel grate floor and stairs, roof insulation installed on top of the roof deck, single ply roof membrane, roof drains and secondary roof drains, roll-up over head door, exterior and interior doors, an exterior window, and a restroom/shower room accessible to the disabled. The Temple grounds will also be altered. Work is to include new concrete sidewalks, new concrete stairways, new concrete retaining walls and planters, new landscaping, a new decorative water fountain, benches, stepping stones to define egress paths through plant areas, and drinking fountains. The perimeter fence will also be modified in some locations. Concrete piers, concrete foundations, and steel fence sections will be installed. To also remodel the interior of the main Temple Building and to construct a 400 square foot 1 story addition (Northwest corner). Work is to include suspended gypsum board ceilings, remodeled restrooms, and interior finishes. Structural work includes concrete footings, concrete foundations, a concrete slab on grade, columns, beams, roof joists, steel moment frames, shear walls, and a new concrete and steel main stairway. Much of the existing mechanical mezzanine located in the center of the building will be re-constructed. Work is to include new shear walls, new steel beams, new floor joists, and new floor sheathing. Mechanical access platforms, including some suspended catwalks, will also be constructed above hallways. This building will be fire sprinklered throughout in conjunction with this permit. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. The fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Conference9/13/20129/14/20129/14/2012ACANC
DetailsMike Jordan
Final Inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Final9/14/20129/14/20129/14/2012APASS
DetailsMike Jordan
Final Inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. Ok for perm occ.
BLD-Conference9/12/20129/12/20129/12/2012PPART
DetailsMike Jordan
Final Building Inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. HAndrail has been repaired. Ok for temp occ. Waiting on letter from engineer of record to accomidate final letter from special inspection agency.
BLD-Conference9/10/20129/10/20129/10/2012PNR
DetailsMike Jordan
Final building inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. Needs to repair handrail in shop.
FIRE-Alarm Testing9/6/20129/6/20129/6/2012PPASS
DetailsTroy Cobbley
Life safety passed
FIRE-Final Inspection9/4/20129/5/20129/5/2012AFAIL
DetailsTroy Cobbley
Life safety will be ok to sign off when the project related fire alarm permit is addressed.
FIRE-Conference9/4/20129/4/20129/4/2012ACANC
DetailsTroy Cobbley
Life Safety inspection rescheduled for tomorrow when the fire alarm and fire sprinkler permits are addressed.
BLD-Conference8/24/20128/24/20128/24/2012ADONE
DetailsMike Jordan
Final Building inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. Walk through with contractor. Noted that not all glazing is in place or door hardware. Needs to repair handrails in shop, provide guard at chiller. ADA unisex restroom has been made compliant. A letter has been sent to building official regarding the non compliant restroom. Also need as built drawings for review.
FIRE-Conference8/21/20128/22/20128/23/2012PDONE
DetailsTroy Cobbley
Scott and I went over life safety requirements for the project.
BLD-Conference8/18/20128/21/20128/21/2012ACANC
DetailsMike Jordan
Life Safety Preliminary inspection with Troy Cobbley Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Conference8/7/20128/8/20128/8/2012ADONE
DetailsMike Jordan
8:30 AM walk through of handrails etc. Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Conference8/2/20128/2/20128/2/2012APASS
DetailsTom Arcoraci
Lower Level Ceiling inspection. Phone #: ###-#### >> Inspection requested via web by Scott Greer ok 408
BLD-Conference7/26/20127/26/20127/26/2012APASS
DetailsMike Jordan
Suspended ceiling re inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. grid ceiling, main level ok to cover. additional support has been added per cicsca0-2 standard.
BLD-Conference7/16/20127/17/20127/20/2012APART
DetailsMike Jordan
Ceiling inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer. Adminstrative office and changing rooms. Need letter from engineer for alternate on hanger wires for diffusers.
BLD-Framing/Rough-in7/13/20127/16/20127/16/2012ADONE
DetailsMike Jordan
Ceiling inspections rooms 159, 177, 149, 136, 145, 142, 140, 141, 143. Phone #: ###-#### >> Inspection requested via web by Scott Greer. Went over CISCA requirements with contractor, no inspections.
BLD-Conference7/13/20127/13/20127/13/2012APART
DetailsMike Jordan
Ceiling inspections rooms 159, 177, 149, 136, 145, 142, 140, 141, 143. Phone #: ###-#### >> Inspection requested via web by Scott Greer. Grid inspection at locker rooms, Need wires on diffusers.
BLD-Conference5/4/20125/4/20125/4/2012PPASS
DetailsMike Jordan
Framing inspection Maintenance shop Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Conference4/27/20124/30/20124/30/2012APASS
DetailsMike Jordan
Framing re inspection area E Phone #: ###-#### >> Inspection requested via web by Scott Greer. Vapor barrier material in area E has been removed and replaced with compliant vapor barrier.
BLD-Conference4/24/20124/24/20124/24/2012PPART
DetailsMike Jordan
Framing inspection in area E Phone #: ###-#### >> Inspection requested via web by Scott Greer. Interior steel stud framed walls and hardlids At area E and basement, Pending other trades rough in inspections. Also received tech data for spray foam insulation that has been used in area E. Flame and smoke spread indexes o. Will also remove some non compliant visquin in concelled areas and provide the correct visquin.
BLD-Conference3/20/20123/20/20123/20/2012APASS
DetailsMike Jordan
Framing inspection in area D Inclusive grid lined 6 to 11. Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Conference2/16/20122/23/20122/24/2012ACANC
DetailsJim Sly
Went to job site.....they didn't call this in.
BLD-Framing/Rough-in2/16/20122/16/20122/16/2012PPASS
DetailsMike Jordan
roof framing and sheathing for overbuild at south enterance.
FIRE-Conference2/14/20122/14/20122/14/2012PDONE
DetailsTroy Cobbley
Carl Westfall and I performed a job site review of the exit signs in areas A and B. I let the superintendant Scott know that they need to be installed as per approved plans and the two that are blocked by the low soffits will need to be viewable from the far end of the corridor.
BLD-Conference2/14/20122/14/20122/14/2012ACANC
DetailsMike Jordan
Site sewer inspection Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Conference2/2/20122/9/20122/9/2012APASS
DetailsMike Jordan
Interior steel stud framed walls and hardlids for area C. Also walk through mech. room and reviewed special inspection reports.
BLD-Other2/3/20122/3/20122/3/2012PCANC
DetailsMike Jordan
BLD-Other2/3/20122/3/20122/3/2012APASS
DetailsMike Jordan
witness epxoy bolting for tw holddowns on shearwalls at gridline 2.
BLD-Conference1/25/20122/2/20122/2/2012ADONE
DetailsMike Jordan
reviewed special inspection reports via email and spoke to scott about exit light issues and exiting issues.
BLD-Conference1/27/20121/27/20121/27/2012PDEFR
DetailsMike Jordan
Footing rebar inspection for plan mod # 4 Phone #: ###-#### >> Inspection requested via web by Scott Greer. Special inspector on site.
BLD-Conference1/25/20121/25/20121/26/2012PPASS
DetailsMike Jordan
Reviewed special inspection reports and walked jobsite.
BLD-Conference1/5/20121/5/20121/5/2012APASS
DetailsMike Jordan
Framing inspection between grid lines 13 - 17 and D - L Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Framing/Rough-in1/5/20121/5/20121/5/2012PPASS
DetailsMike Jordan
Framing inspection between grid lines 13 - 17 and D - L Phone #: ###-#### >> Inspection requested via web by Scott Greer. Interior steel sted framed walls and hardlids ok. Pending fire sprinkler rough in inspection.
BLD-Other12/27/201112/27/201112/27/2011PPASS
DetailsTom Arcoraci
scott - shear nail Phone #: ###-#### hall 166 ok
BLD-Conference12/22/201112/22/201112/22/2011APASS
DetailsTom Arcoraci
Framing inspection area A Rooms 181 - 205 Phone #: ###-#### >> Inspection requested via web by Scott Greer a area ok
BLD-Conference12/1/201112/22/201112/21/2011ACANC
DetailsMike Jordan
BLD-Conference12/14/201112/15/201112/15/2011PDONE
DetailsMike Jordan
Gypsum nailing inspection. any time
Concrete wall rebar inspection at chiller building. Special inspector at 1:00 PM. Concrete scheduled at 1:30 PM Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Foundation12/15/201112/15/201112/15/2011PPASS
DetailsMike Jordan
Gypsum nailing inspection. any time
Concrete wall rebar inspection at chiller building. Special inspector at 1:00 PM. Concrete scheduled at 1:30 PM Phone #: ###-#### >> Inspection requested via web by Scott Greer. Vertical and horizontal reinforcement for W1 type walls at grids X12 and and grid Xc per RFI#282.1(These walls are to be architectual concrete. Previously they were to be masonry walls). Noted that vertical reinforcement at these walls was already placed at 12" o.c.
BLD-Conference12/1/201112/15/201112/15/2011ADONE
DetailsMike Jordan
BLD-Framing/Rough-in12/15/201112/15/201112/15/2011APASS
DetailsMike Jordan
Shear wall holdowns at rooms 164 and 175 (mens and womens restroom) per ASI #5. ok to place plywood after electrical rough in inspection passes.
BLD-Conference12/1/201112/8/201112/8/2011APASS
DetailsMike Jordan
BLD-Framing/Rough-in12/8/201112/8/201112/8/2011APASS
DetailsMike Jordan
Interior Steel stud construction for walls, soffits and catwalks for rooms 192, 193, 194, 195 and 182. Also inspected guards for noted catwalks.
FIRE-Conference12/6/201112/6/201112/6/2011PDONE
DetailsTroy Cobbley
I requested Tim Frost to accompany me to this project to verify possible issues with combustible concealed spaces that I had found on the previous days courtesy inspection. We found many areas which have not been provided upright sprinkler protection and when protection is provided will require many additional sprinkler heads. Per the city approved plans only pendant protection below the ceilings has been provided in these areas. I spoke to the sprinkler fitter and let him know that Plan Modifications will be required. I also spoke to Frank and Ricardo with Jacobsen Construction about a possible stop work order if any more piping is covered and the possibility of removing ceilings just to inspect what has already been installed and covered. No sprinkler rough-in inspections have been performed to this point. I notified Scott and Romeo of the situation.
BLD-Conference11/30/201112/1/201112/1/2011PPASS
DetailsMike Jordan
Rebar inspection in the north west garden retaining wall. Concrete scheduled for 2:00PM. Special inspector scheduled for 1:00

Epoxy hold down inspections for interior shear walls. Any time in PM Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Foundation12/1/201112/1/201112/1/2011PPASS
DetailsMike Jordan
Exterior northwest garden retaining wall. Will have special inspection.
BLD-Framing/Rough-in12/1/201112/1/201112/1/2011PPASS
DetailsMike Jordan
Simpson htt14 tie downs at interior shearwall on grid 15.8. Also reviewed special inspection reports.
BLD-Conference11/14/201111/15/201111/15/2011APASS
DetailsMike Jordan
Chiller shop footing and rebar inspection east end. Concrete scheduled for 1:00 ans special inspector at 12:00 Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Conference10/10/201111/2/201111/2/2011APASS
DetailsMike Jordan
Reviewed special inspector reports. Aslo noted backfilling operations for water feature and at chiller room.
BLD-Foundation11/2/201111/2/201111/2/2011PPART
DetailsMike Jordan
Stemwall for pump house and trash enclosure. Work in progress on installing vertical reinforcement. All per approved plans and RFI from engineer.
BLD-Conference10/26/201110/28/201110/28/2011APASS
DetailsMike Jordan
Chiller room walls. Formwork and rebar. Concrete scheduled for 1:00 Friday. Rebar is ready to inspect any time Thursday all doay or Friday morning. Special inspector scheduled for Thursday to look at rebar. Special inspector scheduled for Friday at 1:00 to cast 2 sets of cylinders during pour Phone #: ###-#### >> Inspection requested via web by Scott GreerW3 and W5 type walls ok. as per plans and RFI's.
BLD-Conference10/26/201110/26/201110/26/2011PPASS
DetailsMike Jordan
Reviewed special inspection reports. Also noted RFI #219, from structural engineer, repairing the omition of #6 bar at wall type W3. Additional #5 will be placed at 32" o.c. at inside face of wall at areas not integral with drilled piers. Also noted work in progress on interior moment frames on south end of building. Noted that their will be an additional plan modification for west vestibule to be submitted by architect.
BLD-Conference10/10/201110/26/201110/26/2011ACANC
DetailsMike Jordan
BLD-Conference10/24/201110/25/201110/25/2011ADEFR
DetailsMike Jordan
Partial footing inspection for the chiller building. Concrete cheduled for 10:00 AM Special inspector scheduled for 9:00 AM Phone #: ###-#### >> Inspection requested via web by Scott Greer
BLD-Footing10/20/201110/21/201110/21/2011APART
DetailsJim Storey
scott - rebar footing and wall Phone #: ###-#### west 1/2 of south wall wip mti to be on site at pm placment time. vert descrepincy for #6 bar to be addressed by engineer for next wall section.
BLD-Conference10/10/201110/19/201110/19/2011APASS
DetailsMike Jordan
BLD-Conference10/15/201110/17/201110/17/2011APART
DetailsMike Jordan
Interior Stair rebar. Shop wall rebar. Special inspector scheduled at 12:00 noon. Concrete scheduled for 1:00 PM >> Inspection requested via web by Scott Greer
BLD-Conference10/13/201110/14/201110/14/2011PPART
DetailsJim Sly
Rebar in foundation wall concrete scheduled for 3:00 PM Special inspection. >> Inspection requested via web by Scott Greer
small section of 8' high wall at South side of bldg. MTI has inspected.
BLD-Conference10/10/201110/12/201110/12/2011APASS
DetailsMike Jordan
Reviewed special inspection reports, Work in progress on south retaining wall, and on catwalk on interior of building.
BLD-Conference10/8/201110/10/201110/10/2011PCANC
DetailsMike Jordan
Rebar inspection fro Shop and chiller building walls. Special inspection scheduled for Monday afernoon. Pour on Tuesday >> Inspection requested via web by Scott Greer
BLD-Foundation10/10/201110/10/201110/10/2011PPART
DetailsMike Jordan
South retaining aloong piers. Work is in progress. Will have special inspection prior to concrete placement.
BLD-Conference10/7/201110/7/201110/7/2011PPART
DetailsMike Jordan
Inspection on rebar prior to form placement at new chiller, boiler area.
BLD-Conference10/6/201110/7/201110/7/2011APASS
DetailsMike Jordan
Shear wall inspection Grid line 23 Phone #: ###-#### >> Inspection requested via web by Scott Greer. Shearwall at gridline 23 ok, as per ASI#23, will need to submit plan mod.
BLD-Conference9/20/20119/21/20119/21/2011PPASS
DetailsMike Jordan
Foundation inspection
Concrete scheduled for 2:30
Special inspection scheduled at 2:00 Phone #: ###-#### x801 >> Inspection requested via web by Scott Greer. Stemwall and column pad pedestals at annex addition. Special inspector on site. Also work in progress on interior piers at shear wall locations.
BLD-Footing9/19/20119/20/20119/20/2011APART
DetailsMike Jordan
Scott Phone #: ###-####. Footings for annex addition. Special inspector also on site.
BLD-Footing9/16/20119/16/20119/16/2011ADEFR
DetailsMike Jordan
scott - ###-#### - pouring at 9:00 am
BLD-Other8/26/20118/26/20118/26/2011PPART
DetailsMike Jordan
Drill ---Richardo Phone #: ###-####. REmainder of drilled piers on south side of building, special inspectors were on site observing the drilling adn will inspect rebar and test concrete.
BLD-Footing8/26/20118/26/20118/26/2011APART
DetailsMike Jordan
Richardo Phone #: 801-577-971. RFeinforcement for concrete stairs, went over noising requirements with contractor. Willl have special inspection.
BLD-Concrete8/25/20118/25/20118/25/2011PPART
DetailsMike Jordan
ricardo - ###-####. Work in progress on drilled piers south end, special inspector on site. Aslo inspected the nearly completed interior footings for existing columns that were moved to gridline 15.6 and remainder of column footing work on grid 25.5.
BLD-Concrete8/24/20118/24/20118/24/2011PPASS
DetailsMike Jordan
Drilling piers inspection please-Ricardo Phone #: ###-####. Noted special inspector on site during the drilliong of the drilled piers and rebar and concrete.
BLD-Concrete8/23/20118/23/20118/23/2011PPART
DetailsMike Jordan
Ricardo Donoso Phone #: ###-####. Drilled piers. south side of bldg. Noted special inspector on site. Noted to jacobsen construction that special inspection is required o n drilled concrete for drilled piers as per approved plans, specs and chapter 17 if the IBC, continous special inspection is also required while piers ore being drilled.
BLD-Footing8/19/20118/22/20118/22/2011PPASS
DetailsMike Jordan
Ricado this is for the out side footings only Phone #: ###-####. Drilled piers # 27.30,32.
BLD-Footing8/18/20118/19/20118/19/2011APART
DetailsTom Arcoraci
scott - ###-#### - exterior footing spec insp on site
BLD-Footing8/18/20118/18/20118/18/2011APART
DetailsMike Jordan
Scott Greer ###-#### per Scott this inspection has nothing to do with the plan mod in review. Drilled piers south side, work in progress.
BLD-Footing8/17/20118/17/20118/17/2011PNR
DetailsMike Jordan
Soils issues with driiled piers, wating for geo-tech and engineering response.
BLD-Footing8/12/20118/15/20118/15/2011PPART
DetailsMike Jordan
Rebar & epoxy by special inspector at 9:00 AM
Rebar and footing inspection needed at 1:00 if possible
Concrete scheduled at 2:00 PM Phone #: ###-#### >> Inspection requested via web by Ricardo Donosso. Grade beam footings on grid line 23, North portion of building (ordinance room). Noted that their has been a structural change to footings from city set of approved plans, a plan mod needs to be sumbitted to cty for approval.