Permit Information
Permit NumberBLD10-02149
StatusFinaled
Name RAYMES INC
Site Address 3110 N CRESCENT DR Unit: 100
Project NamePARKVIEW CONDOS
Customer Number 
ePlanReviewNo
Description
(PARKVIEW CONDOS - OFFICE/CLUBHOUSE) ***6/8/2011 PLAN MODIFICATION TO MODIFY STAIR CONSTRUCTION FOR OPEN RISERS PER IBC SECTION 1009.4.5. SRZ*** Significant remodel to an existing 1,193 sq. ft. office/clubhouse building in condominium development per approved plans. Demolition work to include: removal of non-load bearing partition walls, roof and roof framing, plumbing, exterior siding and interior finishes. New construction work to include: new exterior stairs, handrails, guards, landings; new roof and roof framing; new fully accessible restrooms; new non-load bearing interior wall partitions; new accessible ramp, handrail, landings; related interior finishes in compliance with chapter 8 of the 2006 IBC; electrical, mechanical, and plumbing work; and all other work per the approved plans, attached plan review report, and all other reviewing agencies approvals. This building is NOT fire sprinklered. Planning approval done under DRH10-00182. **SRZ**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
FIRE-Final Inspection7/1/20117/1/20117/1/2011PPASS
DetailsTroy Cobbley
life safety passed
BLD-Final6/29/20116/30/20116/30/2011APASS
DetailsTom Arcoraci
Call before arrival please--Cathy Phone #: ###-####
BLD-Final5/12/20115/13/20115/13/2011PPART
DetailsTom Arcoraci
Renee Phone #: ###-#### cn issued stairs and signs
FIRE-Final Inspection5/12/20115/13/20115/13/2011APART
DetailsTroy Cobbley
A temporary occupancy was given until the work is complete as per the city approved documents. A fire extinguisher is to be mounted at the lower level.
FIRE-Final Inspection5/10/20115/10/20115/11/2011ANR
DetailsForrest France
FIRE-Final Inspection5/5/20115/9/20115/9/2011PNR
DetailsForrest France
Incompleted correction items. Per contractor, hardware issues and a revision to the scope of work are all that remain.
FIRE-Conference5/6/20115/6/20115/6/2011PDONE
DetailsForrest France
Items discussed with contractor include certification tag for the fire extinguisher, repair directional exit sign on alternate power source, provide approved door hardware at the restrooms and the security gate from the pool enclosure, missing stamped plans on site.
BLD-Footing3/10/20113/10/20113/10/2011PPASS
DetailsTom Arcoraci
footing, stemwall,column and landing inspection for exterior stairs Phone #: ###-#### >> Inspection requested via web by John McCarthy
BLD-Wall cover2/17/20112/17/20112/17/2011APASS
DetailsTom Arcoraci
Inspection for second layer of drywall at lower entrance Phone #: ###-#### >> Inspection requested via web by John McCarthy
BLD-Wall cover2/16/20112/16/20112/16/2011APASS
DetailsTom Arcoraci
Inspection for first layer of drywall on ceiling in lower entry which will take three layers of drywall.
will be ready around 11:00 Phone #: ###-#### >> Inspection requested via web by John McCarthy
BLD-Framing/Rough-in1/28/20111/28/20111/28/2011PPASS
DetailsTom Arcoraci
interior framing for wall cover and drywall installation Phone #: ###-#### >> Inspection requested via web by John McCarthy
BLD-Framing/Rough-in1/20/20111/20/20111/20/2011PPART
DetailsJim Sly
nailing inspection for wall sheeting added for the 2'' extension on the existing walls. Phone #: ###-#### >> Inspection requested via web by John McCarthy
Talked to John about 2hr rated breezeway......OK to install weather barrier on West wall facing parking lot.
FIRE-Conference1/7/20111/7/20111/10/2011PDONE
DetailsForrest France
On site conference with contractor regarding fire code review notes and requirements for exit signage/EM lighting.
BLD-Framing/Rough-in1/6/20111/6/20111/6/2011PPART
DetailsTom Arcoraci
Roof sheeting inspection Phone #: ###-#### >> Inspection requested via web by John McCarthy
BLD-Conference12/23/201012/23/201012/23/2010APASS
DetailsTom Arcoraci
inspect nailing pattern for LVL four ply beam Phone #: ###-#### >> Inspection requested via web by John McCarthy