BLD-Final | 1/13/2011 | 1/13/2011 | 1/13/2011 | P | PASS |
Mike Jordan
|
|
|
ok for perm occ.
|
BLD-Final | 1/12/2011 | 1/13/2011 | 1/13/2011 | A | PART |
Mike Jordan
|
|
|
Call 30 min prior--Karen Phone #: ###-####. Ok for Temp occ. Need final letter from special inspection agency.
|
FIRE-Final Inspection | 1/12/2011 | 1/13/2011 | 1/13/2011 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed
|
FIRE-Conference | 1/10/2011 | 1/10/2011 | 1/10/2011 | P | DONE |
Troy Cobbley
|
|
|
Carl Westfall is ok with the exit sign that was shown to be installed at the top of the stairs to the mezzanine to be deleted.
|
FIRE-Conference | 1/7/2011 | 1/7/2011 | 1/7/2011 | P | DONE |
Troy Cobbley
|
|
|
I went over life safety requirements prior to the final inspection. This included verifying that the existing exit discharge lights still function, verifying the new exit signs/emergency lights work, tagging the fire exitinguishers and providing the correct occupant load sign for the coffee shop.
|
BLD-Other | 1/5/2011 | 1/6/2011 | 1/7/2011 | A | PART |
Tony Young
|
|
|
Dave Phone #: ###-####,, final walk through conf.
|
BLD-Framing/Rough-in | 12/14/2010 | 12/15/2010 | 12/14/2010 | A | PASS |
Tony Young
|
|
|
dave Phone #: ###-####,, bathroom frame ok
|
BLD-Final | 12/13/2010 | 12/14/2010 | 12/14/2010 | A | NR |
Tony Young
|
|
|
dave Phone #: ###-####,, not a final,, bathroom frame ok
|
BLD-Conference | 11/29/2010 | 11/29/2010 | 12/7/2010 | P | PART |
Tony Young
|
|
|
Mark Phone #: ###-####,, fire blocking in tall wall ok
|
BLD-Framing/Rough-in | 11/23/2010 | 11/24/2010 | 12/2/2010 | A | PART |
Tony Young
|
|
|
Mark Phone #: ###-####,, conf only on framing
|
BLD-Framing/Rough-in | 11/22/2010 | 11/22/2010 | 11/24/2010 | P | PART |
Tony Young
|
|
|
Mark Phone #: ###-####,, last of ceiling ok
|
BLD-Wall cover | 11/17/2010 | 11/18/2010 | 11/18/2010 | A | PART |
Jim Sly
|
|
|
mark Phone #: ###-#### On going Ceiling insp....OK
|
BLD-Framing/Rough-in | 11/16/2010 | 11/17/2010 | 11/17/2010 | A | PART |
Tony Young
|
|
|
mark Phone #: ###-####,, work in progress,, tune sheetrocker up on screw patterns, laps on base and face layer,, contractor is applying a 20 min rating on finished product
|
BLD-Wall cover | 11/12/2010 | 11/15/2010 | 11/15/2010 | A | PASS |
Dave Hannah
|
|
|
Mark,, ###-####,, ceiling layer first and second layers look ok beams also ok crew is about 25 % done with ceiling
|
BLD-Wall cover | 11/9/2010 | 11/10/2010 | 11/15/2010 | P | PART |
Tony Young
|
|
|
###-####,, ceiling layer,, work in progress
|
BLD-Framing/Rough-in | 11/9/2010 | 11/10/2010 | 11/12/2010 | A | PART |
Tony Young
|
|
|
###-####,, working on west side
|
BLD-Wall cover | 11/10/2010 | 11/12/2010 | 11/12/2010 | A | PART |
Tony Young
|
|
|
###-####,, 1st ceiling layer on west/north side ok
|
BLD-Framing/Rough-in | 11/8/2010 | 11/9/2010 | 11/12/2010 | P | PART |
Tony Young
|
|
|
###-####,, work in progress on draft stops,, and first layer,,
|
BLD-Framing/Rough-in | 11/3/2010 | 11/8/2010 | 11/8/2010 | A | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, hat channel,, work in progress,, I requested contractor to get a conf on mechanical and sprinkler for inspection prior to cover ceiling
|
BLD-Framing/Rough-in | 11/3/2010 | 11/3/2010 | 11/4/2010 | P | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, ok to put hat channel up on ceiling area
|