Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberBLD10-02170
StatusFinaled
Name HANDYMAN CONNECTION
Site Address 4714 W STATE ST
Project NameCOLLISTER SHOPPING CENTER
Customer Number 
ePlanReviewNo
Description
(GREEN CHUTES & SALT TEARS COFFEE SHOP) One-hr construction and fire sprinklers are used for building area increase. To remodel an existing 11,236 square foot tenant space (total of 11,566 square feet after a 330 square foot mezzanine is constructed) for a restaurant and retail sales tenant. No cooking operations that create grease laden vapors are allowed within this tenant space or under the canopy. The proposed BBQ is required to be located outside of this building in an area that is open to the sky. Work is to include two restrooms accessible to the disabled, interior nonbearing partitions, four 160 square foot shipping containers to function as rooms, ramps and landings to provide access to the shipping containers, millwork, interior finishes, dining tables and chairs, service counters, a Type II hood, and kitchen equipment. The shipping containers are to have the doors welded in the open position. Mezzanine work includes wood stud bearing walls, gypsum board shear walls, wood floor joists, and wood floor sheathing. The mezzanine floor and the supporting walls are required to be of 1-hr fire-resistance-rated construction. Mezzanine stairway work includes steel stringers, steel columns, steel beams, and steel treads. This building is required to be maintained as a Type V-A building (i.e. 1-hr fire-resistance-rated). Work includes removing the existing suspended 1-hr ceiling and creating a 1-hr fire-resistance-rated roof-ceiling assembly using a gypsum board membrane. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to be maintained in compliance with NFPA 13 as regulated by the Fire Department. **CJW**
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/13/20111/13/20111/13/2011PPASS
DetailsMike Jordan
ok for perm occ.
BLD-Final1/12/20111/13/20111/13/2011APART
DetailsMike Jordan
Call 30 min prior--Karen Phone #: ###-####. Ok for Temp occ. Need final letter from special inspection agency.
FIRE-Final Inspection1/12/20111/13/20111/13/2011APASS
DetailsTroy Cobbley
Life safety passed
FIRE-Conference1/10/20111/10/20111/10/2011PDONE
DetailsTroy Cobbley
Carl Westfall is ok with the exit sign that was shown to be installed at the top of the stairs to the mezzanine to be deleted.
FIRE-Conference1/7/20111/7/20111/7/2011PDONE
DetailsTroy Cobbley
I went over life safety requirements prior to the final inspection. This included verifying that the existing exit discharge lights still function, verifying the new exit signs/emergency lights work, tagging the fire exitinguishers and providing the correct occupant load sign for the coffee shop.
BLD-Other1/5/20111/6/20111/7/2011APART
DetailsTony Young
Dave Phone #: ###-####,, final walk through conf.
BLD-Framing/Rough-in12/14/201012/15/201012/14/2010APASS
DetailsTony Young
dave Phone #: ###-####,, bathroom frame ok
BLD-Final12/13/201012/14/201012/14/2010ANR
DetailsTony Young
dave Phone #: ###-####,, not a final,, bathroom frame ok
BLD-Conference11/29/201011/29/201012/7/2010PPART
DetailsTony Young
Mark Phone #: ###-####,, fire blocking in tall wall ok
BLD-Framing/Rough-in11/23/201011/24/201012/2/2010APART
DetailsTony Young
Mark Phone #: ###-####,, conf only on framing
BLD-Framing/Rough-in11/22/201011/22/201011/24/2010PPART
DetailsTony Young
Mark Phone #: ###-####,, last of ceiling ok
BLD-Wall cover11/17/201011/18/201011/18/2010APART
DetailsJim Sly
mark Phone #: ###-####
On going Ceiling insp....OK
BLD-Framing/Rough-in11/16/201011/17/201011/17/2010APART
DetailsTony Young
mark Phone #: ###-####,, work in progress,, tune sheetrocker up on screw patterns, laps on base and face layer,, contractor is applying a 20 min rating on finished product
BLD-Wall cover11/12/201011/15/201011/15/2010APASS
DetailsDave Hannah
Mark,, ###-####,, ceiling layer first and second layers look ok beams also ok crew is about 25 % done with ceiling
BLD-Wall cover11/9/201011/10/201011/15/2010PPART
DetailsTony Young
###-####,, ceiling layer,, work in progress
BLD-Framing/Rough-in11/9/201011/10/201011/12/2010APART
DetailsTony Young
###-####,, working on west side
BLD-Wall cover11/10/201011/12/201011/12/2010APART
DetailsTony Young
###-####,, 1st ceiling layer on west/north side ok
BLD-Framing/Rough-in11/8/201011/9/201011/12/2010PPART
DetailsTony Young
###-####,, work in progress on draft stops,, and first layer,,
BLD-Framing/Rough-in11/3/201011/8/201011/8/2010APART
DetailsTony Young
Larry Phone #: ###-####,, hat channel,, work in progress,, I requested contractor to get a conf on mechanical and sprinkler for inspection prior to cover ceiling
BLD-Framing/Rough-in11/3/201011/3/201011/4/2010PPART
DetailsTony Young
Larry Phone #: ###-####,, ok to put hat channel up on ceiling area