BLD-Final | 12/3/2013 | 12/4/2013 | 12/4/2013 | P | PASS |
Mike Jordan
|
|
|
joe Phone #: ###-####. Ok for perm occ.
|
BLD-Final | 9/10/2013 | 9/11/2013 | 9/11/2013 | A | PART |
Jim Storey
|
|
|
joe Phone #: ###-#### temp ok pending p&z sign off// mike needs si close out letter.
|
FIRE-Final Inspection | 9/9/2013 | 9/10/2013 | 9/10/2013 | A | PASS |
Craig D. Hanson
|
|
|
|
FIRE-Final Inspection | 9/5/2013 | 9/6/2013 | 9/6/2013 | P | FAIL |
Troy Cobbley
|
|
|
Relocate the fire extinguisher to the Storage Room as per the approved plans and provide documentation or resubmittals that show the revised fire dept access on the east side of the building.
|
BLD-Energy code compliance | 6/10/2013 | 6/11/2013 | 6/11/2013 | A | PASS |
Mike Jordan
|
|
|
joe Phone #: ###-####
|
BLD-Energy code compliance | 6/6/2013 | 6/7/2013 | 6/7/2013 | A | PART |
Mike Jordan
|
|
|
joe Phone #: ###-####. airseal only ok.
|
BLD-Framing/Rough-in | 5/16/2013 | 5/17/2013 | 5/17/2013 | P | PASS |
Tom Arcoraci
|
|
|
call 1/2 hr prior//Paul Smith Phone #: ###-####
|
BLD-Framing/Rough-in | 4/3/2013 | 4/3/2013 | 4/3/2013 | P | PART |
Mike Jordan
|
|
|
Shear inspection please-- Phone #: ###-####. Exterior shear nailing ok. Need RFI from engineer of record deleting one MSTC strap from CMU wall to wood wall construction. Approved plan shows 2 mstc straps at each location.
|
BLD-Final | 3/29/2013 | 4/1/2013 | 4/1/2013 | A | CANC |
Mike Jordan
|
|
|
paul Phone #: ###-####
|
BLD-Conference | 4/1/2013 | 4/1/2013 | 4/1/2013 | A | PASS |
Mike Jordan
|
|
|
paul Phone #: ###-####. Received RFI paperwork from engineer of record noting the deletionof the 2nd. tension device and tghat the 21" all thread lenght being acceptable.
|
BLD-Other | 3/28/2013 | 3/28/2013 | 3/28/2013 | P | PART |
Mike Jordan
|
|
|
Roof fastening - Paul Phone #: ###-####. Lower roof nailing and diaphragm ok. Need RFI from engineer on HHDQ-S2.5 holdowns. Noted 21 inches of all thread rod before holdown device connection. Simson specs allow for 8" above surface with no reduction as long as bolt elongation has been accounted for. Enginner to review and also review the in place work for only one tension device in each location. Approved plan shows 2 devices in each location.
|
BLD-Other | 3/4/2013 | 3/5/2013 | 3/5/2013 | P | PASS |
Mike Jordan
|
|
|
roof sheathing//Joe Phone #: ###-####. Roof sheathing over gym ok. 1 1/8 ply has been substituted in lieu of 3/4 inch ply. Ledger blocking size also increased for proper bearing of roof joist. All lateral bracing on roof joist over gym ok and installed per truss engineering. MPAI130 straps used on roof sheating as well, strap size was aslo increased. Engineer of record to supply RFI for above noted changes.
|
BLD-Framing/Rough-in | 2/26/2013 | 2/27/2013 | 2/27/2013 | A | PASS |
Jim Storey
|
|
|
joe - roof framing Phone #: ###-#### 450 insp. ok
|
BLD-Conference | 2/12/2013 | 2/12/2013 | 2/12/2013 | P | DONE |
Mike Jordan
|
|
|
Stopped at jobsite to review special inspection reports and to talk with contractor about any issues or concerns he may have.
|
BLD-Final | 12/27/2012 | 12/28/2012 | 12/28/2012 | A | DEFR |
Tom Arcoraci
|
|
|
joe late morning if possible Phone #: ###-####
|
BLD-Other | 12/17/2012 | 12/18/2012 | 12/18/2012 | A | DEFR |
Mike Jordan
|
|
|
joe - grout Phone #: ###-####. Special inspector on site.
|
BLD-Other | 12/14/2012 | 12/17/2012 | 12/17/2012 | A | PASS |
Mike Jordan
|
|
|
block wall grouting - joe Phone #: ###-####.
|
BLD-Other | 12/11/2012 | 12/12/2012 | 12/12/2012 | A | PART |
Mike Jordan
|
|
|
joe - block wall grout Phone #: ###-####. south masonry wall, 8ft. to 12ft. elevation pending special inspetions. Contractor also working on detail for approved firestop system at expansion joints on south wall, will either be from metecaulk or hilti.
|
BLD-Other | 12/7/2012 | 12/11/2012 | 12/11/2012 | A | PART |
Mike Jordan
|
|
|
joe - grout Phone #: ###-####. 4ft. to 8ft. elevation, south wall, pending special inspection. Also noted to contractor to provide UL listing for expansion joint as the south wall is a fire rated wall. Will need access to back side. Also verified all special inspectors certifications.
|
BLD-Other | 12/4/2012 | 12/5/2012 | 12/5/2012 | A | PART |
Mike Jordan
|
|
|
masonry grout ins//Joe Phone #: ###-####. South wall, 0 to 4ft. elevation. Work in progress went over plans with masonry foreman and job super. Ok for grout placement after special inspector has passed in place work.
|
BLD-Footing | 11/6/2012 | 11/8/2012 | 11/8/2012 | P | PASS |
Jim Storey
|
|
|
footing and rebar///Joe Genovese Phone #: ###-#### interior ft rebar ok
|
BLD-Foundation | 9/14/2012 | 9/17/2012 | 9/17/2012 | A | CANC |
Mike Jordan
|
|
|
joe Phone #: ###-####
|
BLD-Energy code compliance | 9/17/2012 | 9/17/2012 | 9/17/2012 | A | PASS |
Mike Jordan
|
|
|
joe Phone #: ###-####. Rigid foam insulation, interior side of stemwall under slab on grade.
|
BLD-Foundation | 9/10/2012 | 9/13/2012 | 9/13/2012 | A | DEFR |
Mike Jordan
|
|
|
late am -- Joe Phone #: ###-####
|
BLD-Foundation | 9/10/2012 | 9/12/2012 | 9/12/2012 | A | PART |
Mike Jordan
|
|
|
late am -- Joe Phone #: ###-####. West stemwall, remainder of east footing. Work is in progress. Will be ok for concrete after special inspection has passed.
|
BLD-Foundation | 9/10/2012 | 9/11/2012 | 9/11/2012 | A | PART |
Mike Jordan
|
|
|
late am -- Joe Phone #: ###-####. Stem wall, south wall for 2hr. masonry wall. Work is in progress on placing forms. Needs to provide additional verts at masonry corners. Will be ok to place concrete after special inspection has passed.
|
BLD-Footing | 9/6/2012 | 9/10/2012 | 9/10/2012 | P | PART |
Mike Jordan
|
|
|
Joe Phone #: ###-####. East footing line, work in progress. Will be ok for concrete after special inspection has passed.
|
BLD-Footing | 9/6/2012 | 9/7/2012 | 9/7/2012 | P | CANC |
Mike Jordan
|
|
|
Joe Phone #: ###-####. Stemwall, north footing line.
|
BLD-Footing | 9/4/2012 | 9/6/2012 | 9/6/2012 | P | PART |
Mike Jordan
|
|
|
joe Phone #: ###-####. East footing line, work in progress. Will have special inspection. Ok for concreter after special inspector has passed area of work.
|
BLD-Footing | 9/5/2012 | 9/5/2012 | 9/5/2012 | P | PASS |
Mike Jordan
|
|
|
Reinforcemen ast south footing line for 2hr. masonry wall. ok. Will have special inspection.
|
BLD-Footing | 9/4/2012 | 9/5/2012 | 9/5/2012 | A | CANC |
Mike Jordan
|
|
|
|
BLD-Footing | 8/30/2012 | 9/4/2012 | 9/4/2012 | P | PART |
Mike Jordan
|
|
|
Late as possible - Joe Phone #: ###-####. North footing line.
|
BLD-Footing | 9/4/2012 | 9/5/2012 | 9/4/2012 | P | PART |
Mike Jordan
|
|
|
joe Phone #: ###-####. North footing. Will have special inspection.
|