Hewlett Packard-Building 5 1st & 2nd floor- Permit for minor tenant improvements to existing spaces on the first and second floors of building #5 with work to include the removal of misc. interior non bearing partition walls and the construction of new non-bearing partition walls and associated electrical, plumbing and mechanical for a break room and small focus room per the approved plans. This is a fully sprinklered building:any alterations to the sprinkler system will require a separate permit and shall comply with NFPA 13 as regulated by the fire department. CDM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled  11/21/2011 DONE
DetailsTisha Gallop
passed all inspections
BLD-Final11/9/201111/15/201111/15/2011APASS
DetailsDave Hannah
BLD-Final11/4/201111/4/201111/9/2011PPART
DetailsDave Hannah
everything ok but needs plumbing final
FIRE-Final Inspection11/4/201111/4/201111/4/2011PPASS
DetailsTroy Cobbley
Life safety passed. Second floor work is complete.
FIRE-Final Inspection11/3/201111/3/201111/3/2011PFAIL
DetailsTroy Cobbley
Contractor did not have the city approved plans. No inspection performed
BLD-Framing/Rough-in9/1/20119/1/20119/2/2011PPART
DetailsDave Hannah
rooms ok need more detail on hard lid in common area.
BLD-Conference8/22/20118/22/20118/22/2011PPART
DetailsDave Hannah
bldg 5 level 2 e club ph 1 walls and soffits ok
BLD-Conference6/3/20116/3/20116/3/2011PPASS
DetailsDave Hannah
BLD-Final3/4/20113/4/20113/7/2011APART
DetailsDave Hannah
ok to occ rooms on first floor and east end of second floor
FIRE-Final Inspection3/4/20113/4/20113/4/2011APART
DetailsForrest France
Fire life safety inspection completed acceptable for the first floor east B5 and west B5 lower focus rooms- also to include the east BU 2nd floor upper focus rooms. Note: upper center link focus rooms and break room not yet completed.
BLD-Conference3/3/20113/3/20113/4/2011APASS
DetailsDave Hannah
BLD-Other2/15/20112/15/20112/15/2011PPART
DetailsJim Sly
gene - ceiling grid for cover Phone #: ###-####
Grid....Upper East.....Bldg 5 4 focus rooms and 1 hallway
BLD-Framing/Rough-in1/20/20111/21/20111/21/2011APASS
DetailsJim Sly
gene - ceiling grid and framing Phone #: ###-####
Bldg #5 Frame OK....Ceilings in (2) focus rooms...OK.
BLD-Framing/Rough-in12/6/201012/7/201012/7/2010PPART
DetailsJim Sly
Gene Phone #: ###-####
Rooms 501 thru 507......OK