BLD-Final | 2/7/2011 | 2/8/2011 | 2/9/2011 | P | PASS |
Jim Sly
|
|
|
junior Phone #: ###-#### OK for perm occ.
|
FIRE-Final Inspection | 2/7/2011 | 2/8/2011 | 2/8/2011 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Contractor to provide single action hardware on the womens restroom door.
|
BLD-Other | 1/23/2011 | 1/24/2011 | 1/24/2011 | A | PASS |
Jim Sly
|
|
|
Ceiling grid inspection Phone #: ###-#### >> Inspection requested via web by Les Seal
|
BLD-Wall cover | 1/3/2011 | 1/3/2011 | 1/3/2011 | A | PASS |
Jim Sly
|
|
|
Late Morning Requested---Please call jr 30min before ###-#### Phone #: ###-#### >> Inspection requested via web by Les Seal Note.....Talked to Jr about wall South of hood.... does not match approved plan. Will need Architect to submit change to PDS for approval. Provide New "approved" changes at final insp.
|
BLD-Framing/Rough-in | 12/17/2010 | 12/17/2010 | 12/17/2010 | A | PART |
Jim Sly
|
|
|
Junior phone ###-#### 1hr wall ok
|
BLD-Framing/Rough-in | 12/16/2010 | 12/16/2010 | 12/17/2010 | P | CANC |
Jim Sly
|
|
|
Jr Phone #: ###-#### Re-sched......
|