BLD-Final | 4/7/2011 | 4/7/2011 | 4/7/2011 | P | PASS |
Mike Jordan
|
|
|
ok for perm occ. Bond has been posted.
|
BLD-Final | 4/6/2011 | 4/7/2011 | 4/7/2011 | A | NH |
Mike Jordan
|
|
|
Ryan Phone #: ###-####. No one at jobsite, no call back, no access.
|
BLD-Final | 3/28/2011 | 3/28/2011 | 3/28/2011 | P | FAIL |
Mike Jordan
|
|
|
Ryan-Please call prior to inspection Phone #: ###-####. Needs zoning sign off or post bond. Provide vertical grab bars in restrooms also provide the mirros in restroom. Install handrails for stairs and ramp at west side of building.
|
FIRE-Final Inspection | 3/24/2011 | 3/25/2011 | 3/25/2011 | A | PASS |
Forrest France
|
|
|
Reinspection passed, C/N items are complete. Manual thumbturns have been removed.
|
FIRE-Final Inspection | 3/24/2011 | 3/24/2011 | 3/24/2011 | P | FAIL |
Forrest France
|
|
|
Missing premise identification, remove manual thumbturns at two locations including the main entry/exit.
|
BLD-Framing/Rough-in | 2/18/2011 | 2/18/2011 | 2/18/2011 | P | PASS |
Jim Sly
|
|
|
follow up//call when on way --Ryan Phone #: ###-#### Header above N. door ......and micro installed to 3 ply truss OK per Eng.....
|
BLD-Framing/Rough-in | 2/11/2011 | 2/14/2011 | 2/14/2011 | A | PASS |
Mike Jordan
|
|
|
Ryan Phone #: ###-####. ok to rock.
|
BLD-Framing/Rough-in | 2/11/2011 | 2/11/2011 | 2/14/2011 | P | PART |
Mike Jordan
|
|
|
late pm please//Ryan Phone #: ###-####. ok to insulated. Pending electrical rough in. Also needs to provide header calc for three ply girder and provide straps on top plates and noted locations.
|
BLD-Footing | 11/29/2010 | 11/30/2010 | 11/30/2010 | A | PASS |
Mike Jordan
|
|
|
nate - first thing in the morning if possible please Phone #: ###-####
|