BLD-Final | 4/27/2011 | 4/28/2011 | 4/28/2011 | A | PASS |
Mike Jordan
|
|
|
dante Phone #: ###-####. ok for perm occ.
|
BLD-Final | 4/26/2011 | 4/27/2011 | 4/27/2011 | P | PART |
Mike Jordan
|
|
|
Dante Phone #: ###-####. Temp occ. granted. Needs specs on light transmitting panels in roof.
|
FIRE-Final Inspection | 4/25/2011 | 4/26/2011 | 4/26/2011 | P | PASS |
Troy Cobbley
|
|
|
life safety passed
|
FIRE-Final Inspection | 4/25/2011 | 4/25/2011 | 4/25/2011 | P | FAIL |
Troy Cobbley
|
|
|
Provide indicator at the main exit and provide the fire dept access designation as discussed.
|
FIRE-Final Inspection | 4/22/2011 | 4/22/2011 | 4/25/2011 | P | DEFR |
Forrest France
|
|
|
dante Phone #: ###-####
|
BLD-Energy code compliance | 4/1/2011 | 4/4/2011 | 4/4/2011 | A | PASS |
Mike Jordan
|
|
|
DANTE Phone #: ###-####
|
BLD-Framing/Rough-in | 3/31/2011 | 4/1/2011 | 4/1/2011 | P | PASS |
Mike Jordan
|
|
|
Dante Phone #: ###-####
|
BLD-Other | 2/23/2011 | 2/28/2011 | 2/28/2011 | P | PASS |
Mike Jordan
|
|
|
re-bar tension tie//Dante Phone #: ###-####
|
BLD-Foundation | 2/11/2011 | 2/14/2011 | 2/14/2011 | A | PASS |
Mike Jordan
|
|
|
Dante Phone #: ###-####
|
BLD-Footing | 2/8/2011 | 2/9/2011 | 2/9/2011 | P | PART |
Mike Jordan
|
|
|
dante Phone #: ###-####. Work in progress on vertical reinforcement install. Special inspector was on site.
|